20 kWp rooftop solar EPC
Design, engineer, procure/supply, erect, test and commission a total 20 kWp grid-connected rooftop solar PV project on various KLTPS plant and S.K. Varmanagar colony buildings, including civil/electrical works, synchronization, net metering and handover. The system has no battery storage and does not operate during grid outage.
Principal equipment and deliverables
Provide DCR bifacial half-cut modules of at least 580 Wp from the latest approved ALMM-II list; module structures/pedestals, junction boxes, PCU/inverters with monitoring/MPPT, AC evacuation panels, protection, cabling, earthing/lightning protection, net/main and backup meters, module-cleaning arrangements, safety systems, signage and all incidental items/services needed for commissioning.
Approvals, testing and handover
The contractor must obtain drawing, GEDA/DISCOM, net-metering, electrical-inspector, fire/factory and other applicable approvals; pre-commission and commission all equipment, run load trials, achieve grid certification and provide the commissioning certificate. Minimum commissioning PR is 75%.
Roof and site constraints
Use pedestal mounting without roof puncture, preserve drainage and waterproofing, and rectify any resulting seepage at contractor cost. Design structures for local heavy rain, strong wind and earthquake. GSECL provides available open space and, if available, one water tapping point; loading, storage, security and unavailable water arrangements remain with the contractor.
Completion programme
Complete commissioning within six months of LOI/NTP. Milestones include drawings/net-meter application by D+15, approvals by D+90, major supply by D+100, installation/interconnection by D+130, testing by D+150, and PR test within 20 days of COD. Partial commissioning is not accepted.
Standards and warranties
All components must meet the latest applicable BIS/IEC and listed standards. PV output must remain at least 90% at year 10 and 80% at year 25; modules, mechanical structures, electrical works, plant equipment/components and workmanship carry the stated 25-year warranties, while inverter OEM warranty is to be furnished with the bid.