Tender uploaded on 05/08/2026 at 17:42; online bidding starts 17/08/2026 and closes 31/08/2026 at 15:00.
- Original/revised bids may be submitted only up to the closing date and time.
Loading…
Provision of Boundary wall at approaches of cities vulnerable for encroachment in WDS-DUD section under ADEN/SUR
Central Railway · Solapur, Maharashtra22-2026-SrDENS~CR
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
5 Aug 2026
31 Aug 2026
₹6.3 Cr
₹12.6 L
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
Tender uploaded on 05/08/2026 at 17:42; online bidding starts 17/08/2026 and closes 31/08/2026 at 15:00.
No pre-bid conference is required; the tender documents do not state a separate clarification deadline or bid-opening date/time.
The offer must remain valid for 60 days.
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
Advertised value is ₹62,843,290.02 and tender document cost is ₹0.00.
Bid security is ₹1,256,900.00. It may be paid in cash through the e-payment gateway or furnished as a scheduled-commercial-bank BG; startups recognized by DIPP are exempt and Labour Cooperative Societies pay 50%.
Security Deposit is 5% of contract value. The balance after retained bid security may be deposited in cash/TDR/irrevocable BG or recovered at 6% from bills until fully recovered.
The successful bidder must furnish a Performance Guarantee equal to 5% of original contract value within 21 days of LOA and before signing the agreement.
On-account payments are made for measured work certified by the Engineer, subject to deductions and 6% retention until the 5% Security Deposit is reached; final payment follows certified completion and final measurement/account settlement.
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
During the seven years ending on the last day of the month before invitation, the bidder must have successfully or substantially completed either three similar works each at least 30%, two each at least 40%, or one at least 60% of advertised value.
Similar work is any civil work including buildings/structures, pipelines, underground or overhead tanks, foundation treatment in Railway embankment/cutting, earthwork, platform covers, bore wells, level crossings including lifting barriers, or cement-concrete aprons.
Private-individual certificates are not accepted. Government certificates are accepted; a listed-company certificate is accepted only where the company meets the ₹500 crore three-year turnover, listing, and five-year-incorporation conditions and the bidder supplies the prescribed supporting records.
Minimum average annual contractual turnover is V/N or V, whichever is less, where V is advertised value in crores and N is the prescribed completion period in years; average is based on total contractual payments in the previous three financial years.
Joint ventures and consortium bids are not permitted; zero members are allowed for each.
A partnership bidder must be legally valid, formed before bid submission, and either registered or operating under a notarized partnership deed; it must have its own PAN/TAN and bid in the firm's name.
The bidder and applicable constituents must not be blacklisted/debarred by Railways or any Government of India ministry/department on bid date, must certify bid information as true, and bidders from a country sharing a land border with India must hold competent-authority registration.
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
Construct boundary walls at city approaches vulnerable to encroachment under ADEN/SUR, with tender schedules identifying MO & MA under Sr.ADEN/N/SUR and AKOR & DUD under ADEN/S/SUR.
The BOQ covers excavation and filling, concrete and reinforced concrete, formwork, reinforcement/structural steel, surface finishing/epoxy paint, fencing with GI barbed wire and angle posts, and M30 concrete pavement work.
Completion period is 12 months, followed by 12 months of contractor maintenance/defect rectification at the contractor's cost.
After one month for mobilization, the contractor must deploy enough resources to construct at least 481 metres of boundary wall per month during the remaining 11 months.
Concrete must comply with IS 456:2000; reinforcement and structural steel with IS 1786 and IS 2062. Design mixes and material/cube tests require approval and testing through Government engineering colleges or reputed NABL-approved labs, at contractor cost.
No work may occur within 2 metres of live OHE unless it is made dead and earthed and a TRD permit-to-work is obtained; contractor personnel working near OHE require prescribed competency certification.
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
Submit the bid electronically on IREPS under the Single Packet System; manual offers are prohibited and ignored.
Tender documents must be signed by a legally competent person; qualifying support must be self-attested/digitally signed. CA-certified documents must carry UDIN wherever applicable or they will not be considered.
If bid security is a BG, upload its scan on IREPS and deliver the sealed original in person to the nominated official within 5 working days before the bid-closing date; failure of either step summarily rejects the bid.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
The AI found nothing to report for this question.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
The NIT name describes WDS-DUD under ADEN/SUR, but the priced schedules describe MO & MA under Sr.ADEN/N/SUR and AKOR & DUD under ADEN/S/SUR. The schedule locations are more specific for pricing, but the Railway should clarify the complete site list before bid.
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Please issue the definitive site/chainage list and reconcile WDS-DUD in the work title with MO & MA and AKOR-DUD in the BOQ schedules; this materially affects mobilization, access and pricing.
Confirm how the ₹5,000/week per 100 m shortfall is calculated after each quarterly review, whether partial 100 m shortfalls are rounded, when the penalty stops, and whether it is cumulative with GCC liquidated damages.
Provide the referenced RDSO drawings, assumed SBC/geotechnical basis and locations; confirm whether changed quantities/designs due to actual SBC are paid as variations even though redesign and proof-checking costs are assigned to the contractor.
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
Contractor delay attracts weekly LD under Clause 17B, capped at 5% of contract value, while failure to sustain 481 m/month after quarterly review separately attracts ₹5,000/week for every 100 m shortfall.
The contractor bears the cost of redesign and independent proof-checking if actual site conditions or SBC differ from the RDSO drawing assumptions, creating unquantified geotechnical/design exposure.
The contractor funds recurring NABL/Government-college tests, third-party testing, a site laboratory, a diploma civil engineer proficient in AutoCAD, laptop/accessories, special shuttering and night-block lighting; non-provision of the engineer/equipment attracts an unspecified site-engineer-decided penalty.
Work near live OHE requires shutdown/earthing, TRD permits, authorized staff and competency certification; excavation must protect cables, rail bonds and mast foundations. Block and coordination availability can constrain production, while safety responsibility remains with the contractor.
The contractor carries a 5% PG plus 5% Security Deposit; 6% is retained from running bills until SD is complete, and GST non-compliance can place otherwise due payments on hold.
Recorded-measurement objections must be raised within seven days; exaggerated/false measurements varying by 5% or more of the claimed gross bill trigger LD of 10% on first occurrence and 15% on the next.
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
DRM/W/SUR, Solapur Division Engineering, Central Railway invites the e-tender on behalf of the President of India; the tender is signed by Sourav Kumar, Sr.DEN/South.