Construction and Redevelopment at Pratibimb-II Housing Society
Proposed construction and redevelopment at plot no. A of existing building no. 7 to 11, Pratibimb-II 82 HIG Allottees Co. Op. Housing Society, CTS No. 5, Kh. No. 19/1, 20 and 21, Mouza - Parsodi, Trimurti Nagar, Bhamti Parsodi, Nagpur.
Maharashtra Housing and Area Development Authority · Nagpur, Maharashtra·2026_MHADA_1328494_1
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
Published
14 Aug 2026
Closes
2 Sept 2026
Estimated value
₹37.4 Cr
EMD
₹18.7 L
Key dates
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
7
Publication / document sale start
Tender published on 14.08.2026; document sale and bid submission start 14.08.2026 at 15.00 Hrs.
Portal: http://mahatenders.gov.in (also notified on http://mhada.gov.in).
No corrigenda are present in the tender pack; these are the applicable dates.
Pre-bid meeting / clarification deadline
Pre-bid meeting on 21.08.2026 at 15.00 Hrs at Conference Hall, Griha Nirman Bhavan, Civil Lines, Nagpur; written questions due at least one week before the meeting.
Conducted by Chief Engineer-II/Authority.
Replies uploaded on the e-tender portal form part of the agreement; points not reflected in CSD/addendum after pre-bid are deemed rejected.
Bid submission / document sale end
Document sale end and bid submission end: 28.08.2026 at 17.00 Hrs.
Online two-envelope submission only on mahatenders.gov.in.
Hard copy of the bid is mandatory within 72 hours after locking of bid on the e-portal (see requiredDocuments).
Technical bid opening
Technical bid opening: 01.09.2026 at 16.00 Hrs (or thereafter).
Opened by Dy. Chief Engineer / Executive Engineer-I, Nagpur Board.
Only technically eligible bidders proceed to financial opening.
Financial / price bid opening
Financial bid & price bid opening scheduled 10.09.2026 at 16.00 Hrs, subject to approval of Competent Authority; ITB also says the date will be informed separately.
Only envelopes of bidders found eligible in Technical Envelope-I are opened.
Bid validity
Tender remains valid and open for acceptance for 120 days from the date of opening of the financial bid (including any extended opening date).
Board may request extension of validity; bidder may refuse without forfeiting earnest money, or agree and must extend EMD validity correspondingly.
Completion period and post-award timelines
Completion period is 24 months including monsoon; agreement to be signed within a month of acceptance; initial performance security within 10 days of LOA.
Time reckoned from date of Work Order (Clause 22).
Defect liability / maintenance period: 3 years after satisfactory completion; also 3 years comprehensive maintenance of lifts, pumps, generator & structure from OC.
Financials
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
6
Estimated / approximate value and payable BUA
Approximate value of work Rs. 37,38,59,464/- for payable built-up area 10,252.535 sqm; quote as Rs per sqm of payable BUA.
Annexure-I (Vol-III): 102 MIG tenements in 1 building of 2 wings; total payable BUA 10252.535 sqm.
Tender document fee
Non-refundable blank bid document cost Rs. 3,000 + GST Rs. 540 = Rs. 3,540/-, payable online only via the e-tender gateway.
Scanned online receipt must accompany the bid; missing receipt makes bid invalid.
Paid from bidder’s own account (with EMD).
EMD / bid security
Bid security/EMD Rs. 18,69,300/- (0.5% of estimated cost), payable online via e-tender gateway from the bidder’s own account; no exemption.
Scanned online receipt to be uploaded; bid without acceptable bid security is non-responsive/invalid.
EMD paid separately for each work; earlier standing EMD exemptions cancelled.
Forfeiture triggers include: withdraw after opening during bid validity; not accepting bid price correction; successful bidder failing to sign agreement or furnish required performance security/solvency within time; failure after acceptance to complete contract documents and pay security deposit/surety.
Discharged when successful bidder signs Agreement and furnishes required Performance security.
If validity is extended, EMD validity must be extended correspondingly.
Clause 2.28.1 also refers to scanned Online Receipt/Bank Guarantee (see contradictions).
Performance security / security deposit
Performance security deposit 1% of contract/estimated amount: 50% initial (FDR/BG/Surety Bond of Nationalized/Scheduled Bank) within 10 days of LOA; remaining 50% recovered from R.A. bills; instruments valid 3 years beyond stipulated completion.
Also produce surety bond on stamp paper for amount equivalent to Security Deposit (2.29.5).
RA-bill PSD portion cannot be converted to BG (2.29.4).
Late initial PSD may attract interest at 22% p.a. at NHADB/MHADA discretion (2.29.6).
50% deducted from RA bills refunded 3 months after final bill payment; BG/FDR/Surety portion refunded after maintenance period (3 years from completion) ends.
Annexure-I BG format and Annexure-III Performance Guarantee Bond printed in tender.
If L1 quotes below estimated cost, additional performance security (FDR/BG/Surety Bond of Nationalized/Scheduled Bank) is required within 8 days of financial bid opening; failure forfeits EMD and tender is not accepted.
Upto 10% below: 1% of estimated cost.
More than 10% below: (quoted % below − 10%) + 1% (e.g. 14% below → 5%).
More than 15% below: stepped formula; e.g. 19% below → 14% total (1% + 5% + 8%).
Instrument in favour of Chief Accounts Officer / Nagpur Board (NHADB); extendable through extensions; refund after satisfactory completion & handing over; validity to be extended beyond one month of DLP.
If L1 fails to submit APS in 8 days, L2 may be invited to match/revise at or below L1 rate.
Self-attested affidavit that APS is enclosed in Envelope No.2 is also required in technical envelope (process conflict — see contradictions).
Payment terms, advances, taxes and deductions
Lump-sum turnkey payment on payable BUA as per staged Plan of Payment (Vol-III); rates exclusive of GST (paid separately on tax invoice); escalation payable; optional mobilization advance 10% of contract value against BG/Surety at prevailing interest.
Interim/final payments per stage percentages in Plan of Payment (foundation through OC/NOCs totaling 100%).
Payment by RTGS/NEFT (Bank of Maharashtra process).
No extra claims for less/more quantity up to any extent; payment as per tendered rate and BUA.
Statutory deductions: Income Tax @ 2% (or revised), Labour Welfare Cess @ 1%, insurance etc. from RA bills; TDS on GST when applicable.
Royalty and material testing charges borne by contractor but reimbursed on submission of receipts/NO dues.
Architect M/s Art A Roof Innovators appointed by MHADA: agency must factor 2% architect fee on tendered amount; 1% each deducted from 1st and 2nd RA bills and paid by MHADA to architect (tender amount exclusive of GST; GST paid separately to architect and contractor).
Infrastructure works if any not included in tender paid AT PAR on prevailing PWD/MJP DSR of year of execution.
Eligibility
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
7
Open competitive bidding; no Govt. registration mandatory; JV barred
Open to all competent bidders; registration with PWD/CPWD/MES/MHADA/CIDCO etc. not mandatory; joint venture bids not acceptable; one bid per package only.
Sub-contractor experience/resources generally not counted toward qualifying criteria.
PMC or non-structural roles not counted as qualifying experience.
Organisation age and housing experience
Organisation age not less than 10 years; at least 10 years’ experience in housing work.
Financial capacity — turnover, net worth, cash accruals, bidding capacity
Max annual civil construction turnover in last 3 years ≥ Rs. 14.02 crore; net worth > 20% of project (CA certified); net cash accruals ≥ Rs. 3.74 crore positive each of last 3 FYs; bidding capacity ≥ cost of work.
Turnover formula: 75% × (total contract value / 2 years) = Rs. 14.02 crore; last three consecutive audited balance sheets required; zero-turnover years still count in average.
Also: no corporate debt restructuring in process/unresolved as of 1 month before application due date (CA certificate); “No default certificate” from bankers for loans availed.
Statement of annual turnover, assets/liability & net worth for last 5 years (CA certified) to be uploaded.
Bidding Capacity = (2 × A × N) − B, with A = max turnover any one of last 3 years (completed + in progress) enhanced 10% p.a. simple; N = years prescribed for completion; B = value of existing commitments during the completion period.
Solvency certificate for 20% of estimated cost from Nationalized/Scheduled Bank, valid one year — tender not opened without it.
Similar work experience (multi-storeyed G+9 / S+9)
Successfully completed similar multi-storeyed buildings (minimum G+9/S+9) in last 5 years ending last date of tender submission, certified by officer not below Executive Engineer, meeting value and quantity thresholds.
Either: three similar completed works each ≥ 40% of estimated cost; OR two ≥ 50%; OR one ≥ 80%.
Maximum turnover during five years should not be less than Rs. 14.02 crore (75% of annual value of construction).
Similar work: Construction of Residential building – Minimum G+9/S+9 & above with same technology as proposed, with internal water supply, sanitary, fire fighting, lifts and internal electric installation.
Executed works valued at current costing by enhancing actual value at 10% p.a. simple from completion date to last date of receipt of applications.
Also completed RCC work of a single project with BUA not less than 80% BUA of this project in any year of last 5 years.
Qualifying project structures must conform to prevailing IS codes / NBC parameters (safety, durability, weathering, chemical resistance, etc.), certified by IIT/VJTI Mumbai/VNIT Nagpur/COE or equivalent; certificates in technical envelope.
Works must be with the technology proposed (conventional cast-in-situ).
Minimum quantities in any one year of last five years: Concrete M-30+ 1252 cum; Flooring & Dado 4624 sqm; UPVC windows 255 sqm; Colouring 15314 sqm; Reinforcement 240 MT; 13-passenger lift 1; 8-passenger lift 1; 10 KWP Solar Grid 1; Fire fighting system 1.
Registrations, licences and certifications
Valid GST, PAN & Income Tax certificate; ISO 9001-2015, ISO 14001-2015 and ISO 45001:2018; valid Electrical Contractor licence from I.E. & L. Dept., Govt. of Maharashtra.
Successful bidder must produce valid current Contract Labour Act 1979 licence before starting work, else acceptance withdrawable and EMD + initial SD forfeited.
Copy of electrical contractor licence of the agency executing electrical work at site required in technical envelope.
Plant, equipment and key personnel
Must demonstrate ownership/availability of specified key plant (Annexure-I) and key personnel (Annexure-II); scanned proof of ownership of machinery for site use required.
Key plant (max age as on 01.07.2026): Excavator/JCB ×2 (5 yrs); Transit Mixer ×2 (5); Water Tanker 5000 L ×2 (5); Truck/Tractor ×3 (5); Concrete Batching & Mixing Plant min 30 m³/hr ×1 (5).
Key personnel: Project Manager (BE Civil +15 yrs, 5 as Manager); Site Engineer Civil (BE +10, 5 in building); Plant Engineer (BE Mech +10 or Dip Mech +15); QS (BE Civil +7 or Dip +10); Soil & Material Engineer (BE Civil +10); Survey Engineer (BE Civil +5 or Dip +8); Site Engineer Elect (BE Elect +5 or Dip +8) — total 7.
Detailed construction planning/methodology with plant cycle times required.
Debarment, blacklisting and other disqualifiers
Agencies debarred or blacklisted in India or abroad as on bid submission date are summarily rejected; notarised Rs.500 stamp undertaking (Annexure-VIII) mandatory; false documents, poor performance or prior unreasonable bids can disqualify.
Disqualification also for misleading/false representations; abandoning works; delays; litigation history; financial failures; prior same-work unreasonably high bid without justification.
Conditional tenders summarily rejected.
False documents may forfeit EMD and lead to blacklisting.
Scope of work
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
3
Project and location
Lump-sum turnkey construction and redevelopment at plot no. A of existing buildings 7–11, Pratibimb-II 82 HIG Allottees Co-op Housing Society, CTS No. 5, Kh. No. 19/1, 20 & 21, Mouza-Parsodi, Trimurti Nagar, Bhamti Parsodi, Nagpur.
Inviting authority: Executive Engineer-I/NB, Nagpur Housing and Area Development Board (MHADA regional unit).
Form “C” open e-tender; construction of MIG residential tenements (Annexure-I: 102 MIG tenements, 1 building / 2 wings).
Payable BUA 10,252.535 sqm; completion 24 months including monsoon.
Core deliverables and contractor responsibilities
Full construction to drawings, statutory approvals/NOCs/OC/completion certificates, demolition of existing structures, site investigations, and handover including 3-year post-OC comprehensive maintenance of lifts, pumps, generator and structure.
Approvals from local Municipal Authorities, MSEDCL, MJP, PWD, MIDC, MoEF, CFO, AAI and other GOM/GOI bodies as required; RERA compliances.
MHADA has appointed Architect M/s Art A Roof Innovators, Nagpur; agency executes to architect-provided drawings; structural designs vetted via architect through GCOEN/IIT/VNIT/VJTI/Govt. Engg. College etc.
Technology: conventional cast-in-situ.
Scope includes surveys, trial bores/pits/soil tests (no claim for deeper foundations, hard rock or piles), joint land measurement/PR cards/7-12, plinth CC/further CC, MoEF if required, infrastructure design & execution as specified, fire fighting, lifts, DG, solar, electrification, sanitary/plumbing, rainwater harvesting, podium garden, paver blocks, etc. (per Plan of Payment heads).
Existing structures on plot demolished/removed by bidder at no extra cost; salvage becomes contractor’s property.
50-year durability undertaking for the structure required.
DLP 3 years after satisfactory completion.
Standards, measurement and exclusions / scope variability
Work per approved drawings, PWD Maharashtra Standard Specifications 1982, relevant IS and additional specs; BUA measurement rules fixed; scope may reduce with demand without additional claims.
Payable BUA: actual construction area with lift, staircase, lift room, pump & meter room, common passages, society office; refuge floor and stilt each at 50% floor area; CE-II/MHADA decision final.
Rate inclusive of all works in scope for local authority requirements; no extra payment on any account for those.
Some infrastructure works if not in tender paid separately AT PAR on PWD/MJP DSR.
Owner-side payments to local/approving authority as project owner paid by MHADA; other charges by agency.
Carpet areas of MIG/LIG/EWS as per MHADA norms (technical planning brief).
Required documents & submission
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
40
Submission mode, portal and envelopes
Online two-envelope e-tender on http://mahatenders.gov.in: Technical Envelope-I (T1) and Financial Envelope-II (C1); Class-3 DSC encryption/signing mandatory.
Also notified on http://mhada.gov.in.
Bidder must enroll on e-tendering system.
Financial offer: Rs per sqm BUA in Schedule F / BOQ; download Schedule F, fill, upload scanned PDF in Envelope-2 with DSC.
On/before last submission date, re-upload and re-encrypt all bid-preparation documents with DSC.
Tenders not in this manner rejected forthwith.
English language; prices in INR only.
Hard-copy and original verification
Hard copy of the bid document must be submitted to EE-I/Nagpur Board within 72 hours after locking of bid on e-portal; originals to be produced if called for.
Letter of Transmittal: scanned copy uploaded; original to be produced when called for.
Agreement signing with stamp duty within one month of acceptance.
Signing and digital signature rules
Bid signed with DSC by proprietor / partner holding registered PoA / authorised company person holding registered PoA; written Power of Attorney to accompany tender.
Partnership: certified copy of registered PoA plus partners/directors address statement.
Company: certified copy of registered PoA; may need existence evidence before award.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
1
No corrigendum / addendum in the document set
The downloaded tender pack contains only the NIT, Tender Document, Drawings and BOQ; no corrigendum or addendum file is present, so original document values currently apply.
Bidders should still monitor http://mahatenders.gov.in and http://mhada.gov.in for any later CSD/addendum after the 21.08.2026 pre-bid.
Final applicable snapshot: Publish 14.08.2026; sale/submission 14.08.2026 15:00 to 28.08.2026 17:00; pre-bid 21.08.2026 15:00; technical opening 01.09.2026 16:00; financial opening 10.09.2026 16:00 (subject to approval); EMD Rs.18,69,300; fee Rs.3,540; estimate Rs.37,38,59,464; completion 24 months including monsoon; bid validity 120 days from financial opening.
Contradictions
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
4
Additional Performance Security — when and how submitted
Technical envelope requires a self-attested affidavit that APS is enclosed in Envelope No. 2, but the APS clause only applies to below-estimate L1 and requires deposit within 8 days after financial opening — these mechanics conflict.
2.25.7(II): affidavit in Envelope-1 that APS is enclosed in Envelope-2.
2.31: APS only if quoted below estimate; L1 submits within 8 days of financial bid opening; otherwise EMD forfeited.
Bidder action: seek pre-bid clarification on whether any APS instrument/affidavit is needed at bid stage for at-par/above quotes, and what Envelope-2 should contain.
EMD instrument — online only vs Online Receipt/Bank Guarantee
Fee/EMD clauses insist on online gateway payment only, while Bid Security clause 2.28.1 also refers to scanned Online Receipt/Bank Guarantee.
Practical reading for bid submission: online EMD via mahatenders gateway is mandatory per 2.8/3.11.1(b).
BG reference may be residual drafting; confirm at pre-bid whether BG is acceptable alternate.
Financial bid opening date — fixed schedule vs ‘informed separately’
Schedule states Financial Bid Opening 10.09.2026 @ 16.00 Hrs subject to Competent Authority approval, while ITB 3.12 says financial bids open on a date informed separately.
Both can be read together: 10.09.2026 is the planned date, still contingent on authority approval and separate intimation after technical evaluation.
Project housing category label — MIG vs HIG society name
NIT invitation text and Vol-III Annexure-I describe MIG tenements/102 MIG units, while the project title repeatedly refers to Pratibimb-II 82 HIG Allottees Society.
For pricing/scope, Annexure-I and payable BUA (10252.535 sqm, 102 tenements) are the operative work description; HIG appears as the existing society name in the site title.
Confirm product mix/carpet norms at pre-bid if bidding depends on unit typology.
Pre-bid queries
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Please clarify whether every bidder must upload an Envelope-2 APS instrument/affidavit at bid submission, or only L1 after financial opening when quoting below estimate, and what at-par/above bidders should upload under 2.25.7(II).
Material to bid validity and risk of technical rejection for missing affidavit/instrument.
EMD form acceptability (online vs BG)
Confirm that only online gateway EMD is acceptable and whether any Bank Guarantee EMD will be treated as responsive under 2.28.1.
Which infrastructure items are inside the lump-sum BUA rate vs DSR AT PAR extras?
Request a clear split of building works, on-plot infrastructure and external infrastructure included in the per-sqm rate versus items payable AT PAR on PWD/MJP DSR under 3.2(i).
Directly affects pricing risk on roads, STP, substations, compound wall, landscaping, etc.
Existing buildings 7–11 demolition scope and constraints
Provide as-is survey/condition of structures to be demolished, any occupied tenements, hazardous materials, utility disconnection responsibility, and disposal constraints; confirm salvage ownership and that no extra payment applies even if quantities differ.
Demolition is bidder’s cost with salvage as only recovery — major bid/no-bid and pricing item.
Scope reduction for demand — payment and idle mobilisation protection
If tenement demand reduces scope, how and when is payable BUA adjusted, are fixed costs compensated, and can the contractor refuse partial work below a threshold?
Clause bars additional claims for reduction — high commercial risk on a 24-month turnkey job.
Architect fee 2% cash-flow and rate build-up
Confirm that bidders must load 2% architect fee into the BUA rate, that MHADA deducts 1% each from 1st and 2nd RA bills, and whether estimated cost Rs.37.38 Cr already embeds this fee for below-quote APS calculations.
FIDIC bonus/penalty rates not quantified
Clause 13 says delay penalty and early-completion bonus are “according to FIDIC” without stating percentages/caps beyond Clause 22’s 1%/day up to 10% — please specify the applicable FIDIC edition and exact bonus/LD schedule.
80% BUA single-project criterion base figure
Confirm whether “80% BUA of this project” is 80% of payable BUA 10,252.535 sqm (i.e. 8,202.028 sqm) and whether stilt/refuge measurement rules apply to the qualifying project certificate.
Risks
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
6
Severe delay LD and milestone regime
Time is essence; compensation 1% of estimated cost per day of shortfall against milestones, capped at 10%; milestones require 100% work by 90% of time and handover at 100%.
Milestones from Work Order: 25% work by 30% time; 60% by 50%; 90% by 75%; 100% by 90%; handing over completed project at 100% time.
Clause 22A allows rescission, departmental completion or retendering with cost recovery and SD forfeiture for serious default.
24 months includes monsoon plus all approvals — approval delays are high-risk unless extension is granted.
Lump-sum geotechnical and demolition risk on contractor
No claims for deeper foundations, hard rock or piles after contractor’s own investigations; existing structures demolished at contractor cost with only salvage recovery.
Site data in tender is general information only; bidder deemed to have full site knowledge.
Employer-side scope cut without compensation
Scope may reduce based on public demand for tenements with no additional claims — stranded mobilisation/overhead risk.
Security package, APS ladder and forfeiture exposure
Stacked securities (online EMD, 1% PSD, possible high APS for deep discounts, surety bond) with multiple forfeiture triggers and 22% interest on late initial PSD.
Deep below quotes can require APS up to double-digit % of estimate (example 19% below → 14% APS) within 8 days or lose EMD.
PSD instruments must remain valid 3 years beyond stipulated completion; DLP 3 years; plus 3-year comprehensive maintenance of lifts/pumps/generator/structure from OC.
50-year durability undertaking is an unusually long post-construction exposure.
Payment and deduction cash-flow risks
Stage-payment plan, 2% architect fee skimmed from early RA bills, 1% labour cess, 2% IT, and GST-exclusive quoting require careful working-capital planning; no extra for quantity variation.
Mobilization advance only 10% and interest-bearing against BG.
Consumer forum liability for quality disputes is contractor’s responsibility within scope.
No JV and high qualification bar
JV banned while requiring G+9 similar works, Rs.14.02 Cr turnover, 20%+ net worth, 20% solvency, ISO trio, electrical licence and owned plant — capacity concentration risk.
False-document blacklisting and mandatory 72-hour hard-copy submission are pass/fail process risks.
Contacts
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
4
Inviting authority / Executive Engineer-I
Executive Engineer-I/NB, Nagpur Housing and Area Development Board (MHADA regional unit), Griha Nirman Bhavan, Near MLA Hostel, Civil Lines, Nagpur-440001; Tel 0712-2560649, 2562239; email [email protected].
On behalf of Chief Engineer-II, Authority.
Physical hard-copy bid submission address: office of Executive Engineer I/ Nagpur Board at the above location.
Agreement to be entered with Executive Engineer-I, Nagpur Housing & Area Development Board.
Pre-bid meeting venue and authority
Pre-bid on 21.08.2026 at 15.00 Hrs conducted by Chief Engineer-II/Authority at Conference Hall, 1st floor, Griha Nirman Bhavan, Nagpur Housing Area Dev. Board Office, Civil Lines, Nagpur-440001.
Written questions to EE-I/N.B/NHADB not later than one week before the meeting.
e-Procurement service desk
For e-tender portal queries: toll-free 18002337315; mobile 7878007972/7878007973; email [email protected] (as printed).
Main portal http://mahatenders.gov.in; MHADA portal http://mhada.gov.in.
Additional performance security beneficiary
FDR/BG/Surety Bond for additional performance security to be issued in favour of Chief Accounts Officer / Nagpur Board (NHADB, Nagpur).