Procurement of various type of control transformers for local control panel at 2*250 MW BLTPS, padva.
Gujarat State Electricity Corporation Limited · Bhavnagar, Gujarat·321739
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
Published
11 Jul 2026
Closes
18 Sept 2026
EMD
₹1.0 L
Key dates
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
8
Notice / invitation date
E-Tender Notice No. 128(B)/BLTPS/2026 for Sr. 6 to 10 is signed for & on behalf of GSECL on 10.07.2026 by A.C.E. (Gen), Station Head, BLTPS.
No separate formal 'publication date' field is printed beyond the notice signature date 10.07.2026.
After Extension-3, last date & time for online (e-tendering) uploading of tender documents and filling price is 08.09.2026 up to 17.30 hrs (mandatory) for Sr. 06 to 08 & 10, including this tender Sr.10.
Extended thrice from original 01.08.2026 → Ext-1 13.08.2026 → Ext-2 25.08.2026 → Ext-3 08.09.2026.
Bid downloading also stated as up to 17.30 Hrs as per Tender Notice No.128 in the tender booklet.
No tender accepted after due date/time of receipt of proof of tender fee and EMD payment.
Technical / preliminary bid opening
Online opening of Preliminary & Technical Bid is on 08.09.2026 at 18.00 hrs onwards (if possible), same working day as bid due date.
Extended with the same chain as submission: original 01.08.2026 → 13.08.2026 → 25.08.2026 → 08.09.2026 (Extension-3).
Authorized representative (only one) must produce authorization letter at opening if attending.
Price bid opening
Tentative online price-bid opening is not fixed as a calendar date; bidders must track https://tender.nprocure.com and emails from the portal. Opening is after technical evaluation and only for technically qualified bidders.
Notice column: 'Tentative date of on-line opening of price bid (if possible) — Party has to be in touch with website https://tender.nprocure.com and also with e-mail sent by above website'.
Tender booklet: time and date of Price Bid opening determined by Corporation and intimated only to technically qualified tenderers.
Bid / offer validity
Offer validity is 120 days from the date of actual opening of Technical Bid for this supply tender; less than 120 days leads to cancellation/rejection of tender.
Tender notice table also prints Validity 120 Days against RFQ 77176.
Works validity of 180 days is stated in the same table but this tender is supply.
Commercial terms likewise require 120 days from technical bid opening; extension of validity may be sought without price change.
Pre-bid / clarification deadline
No pre-bid meeting date or formal clarification cut-off date is specified in the tender documents.
Technical questions/clarifications are to be referred to Chief Engineer (Gen)/contacts listed; bidders must watch websites for revision/corrigendum till due date.
Physical instrument submission after technical opening
If EMD/tender fee is by Demand Draft/Pay Order/Bank Guarantee, the instrument must reach the BLTPS office within 5 days from date of opening of Technical Bid by Registered Post A.D. or Speed Post.
Addressed to The Chief Engineer(Gen), GSECL, Bhavnagar Lignite Thermal Power Station, Padva, Ta: Ghogha, Dist. Bhavnagar, Pin-364050.
Post-award timelines
Security Deposit is due within 10 days of LOI receipt under the tender booklet; delivery of entire supply is within 12 weeks from date of LOI.
Detailed Purchase Order issued only after remittance of Security Deposit.
General Supply Terms also state SD within 15 days of LOA — conflict noted under contradictions; tender booklet table is the specific SD schedule for this NIT.
Agreement bond required at LOI/order for order more than Rs.5 lacs.
Financials
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
9
Estimated / tender value
No estimated cost or tender value is stated in the tender documents for ME-128/10/874/BLTPS/2026.
Only EMD Rs.1,01,185/- and tender fee are quantified; bidders must self-assess value from Schedule-B quantities.
Tender document fee
Tender fee is Rs.2,500 + GST Rs.450 = Rs.2,950/- (non-refundable under normal circumstances).
Acceptable through Demand Draft/RTGS/NEFT; cash up to Rs.10,000/- at office address, or RTGS/NEFT/online.
Without tender fee (if not exempt under Annexure-A), tender is rejected without further correspondence.
If GSECL scraps/cancels tender without bidder fault, fee may be refunded at purchaser's sole discretion.
Scan/PDF of tender fee payment details must be uploaded on n-procure (mandatory).
EMD / bid security
EMD is Rs.1,01,185/- (refundable), payable by DD/Pay Order/RTGS/NEFT/Bank Guarantee from approved banks; BG validity at least six months from bid submission; corporate guarantees and cheques not allowed.
As EMD is not more than Rs.3 Lakhs, cash (up to Rs.10,000 at office) or RTGS/NEFT/online also permitted under tender booklet wording; BG on Rs.300/- stamp paper in GUVNL prescribed format.
Without EMD (if not exempt under Annexure-A), bid rejected.
No interest on EMD.
Online/NEFT/RTGS must be from official business account, not personal account.
Unsuccessful bidders: EMD in cash/DD/banker's cheque returned within 07 days of placing order on successful tenderer (notice/tender booklet); technically disqualified within 15 days of price-bid opening.
Successful bidder: EMD returned only on submission of Performance Guarantee towards execution (Security Deposit).
Forfeited if tender withdrawn during offer validity.
Bank list: all nationalized banks plus listed private/co-operative banks with guarantees accepted for period up to 31-03-2027 (cut-off is date of issue of BG).
GSECL bank details for fee / EMD / SD
Payments to Name of Account – G.S.E.C.L., SBI Koliyak Branch, A/c 00000037955942125, IFSC SBIN0060191, MICR 364002010; GSECL GST 24AAACG6864F1ZO.
Limited categories may claim exemption (mainly EMD for eligible MSE manufacturers/service providers with Udyam; other listed categories in Annexure-A).
MSE manufacturers/service providers with valid Udyam for the tendered product/service — traders/re-sellers not eligible for EMD exemption.
DPIIT-recognised Start-ups with Udyam for the product/service.
Gujarat Khadi Gramodyog Board / KVIC / Commissioner of Cottage Industries registration for the manufacturing product.
Central/State Board/Corporation/PSU for own manufactured items.
Specified State-recognised organisations (blinds/disabled etc.; women's SHG of Gujarat Livelihood Promotion Company) manufacturing/providing the product/service.
OEM/service providers with annual turnover INR 500 Crore or more rendering services directly.
Sellers/Service Providers holding BIS license for Primary Product Category validated via BIS database.
Security Deposit (execution period / performance towards supply)
Under the tender booklet, SD is due within 10 days of LOI: generally 5% of order value; Annexure-A exempted entities pay 3% if order > Rs.5 Lakhs (exempt if order ≤ Rs.5 Lakhs); no SD if order value < Rs.2 Lakh.
Payable by RTGS/NEFT/DD/Bank Guarantee/E-Bank Guarantee from approved bank list; DD in favour of GSECL payable SBI Koliyak Branch.
BG one-time validity till completion of order in all respects; interim BG not allowed; renew at least one month before expiry if supply period extended; corporate BG not allowed.
Returned only on satisfactory/successful execution and NOC from user department.
PO issued only after SD remittance.
Formats for Banker's Undertaking towards execution/supply period PBG and warranty PBG are in LOI ACCEPTANCE SD PBG - SUPPLY.PDF on Rs.300/- stamp paper.
General Supply Terms additionally prescribe item-wise SD/PBG tables and 15-day LOA timeline and state SD irrespective of SSI — see contradictions; Clause 9.3 says BG as per Tender terms.
Warranty-period Performance Bank Guarantee
General Supply Terms require PBG towards warranty/guarantee before last supply completion, with validity covering guarantee period plus one month; for 'Transmission items, Generation & other' the printed table shows 10% of contract value (MSME/non-MSME) and 04% for Gujarat-based Micro & small.
Tender booklet guarantee period is 18 months from receipt at site or 12 months from commissioning, whichever earlier — PBG validity should align.
Separate Banker's Undertaking format provided for PBG towards Guarantee/Warrantee Period.
Supplier may submit one combined BG considering PG requirement (STC 9.4 / 41.5).
Payment terms
No advance. Standard supply payment: 80% of FOR destination price within 30 days of material receipt against TRC (GST/cess retained until GST proof/return reflection); balance 20% against S.R. Note within 45 days of receipt at site in good condition; payment by RTGS/NEFT.
Bidder must furnish bank account details with offer (A/c no., type, bank, branch, contact, IFSC, Swift).
If any work part in supply order, payment within 30 days from recording of bill.
Rates firm, FOR Destination BLTPS Padva; packing/forwarding, freight, insurance and GST structure to be shown in price bid.
Taxes and price basis
GSTIN, HSN and PAN mandatory in technical bid; applicable GST rates in GST column; composition dealers mark “C” and GST amount “0”.
Tenders without Active GSTIN rejected; cancelled GST registration requires No-due Certificate from GST Department.
Evaluation uses taxes/duties, P&F, freight, insurance as indicated in Schedule-B.
Eligibility
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
9
Who may bid
Sealed/online rate tenders invited from reputed suppliers with sound engineering background, experience and financial capability fulfilling the stated qualifying requirements for supply at BLTPS, Padva.
Vendor registration with GSECL is expressly not compulsory for this NIT (overrides general compulsory registration in Supply Terms — see contradictions).
Past supply / similar-item experience
Only offers from parties who have executed supply orders of same/similar items to Government utilities, PSUs, Corporation bodies, SEBs, GUVNL & subsidiaries, or Private/Public Limited Companies will be considered; executed order copies must be enclosed with technical bid else offer ignored without reference.
Also required: list of recent orders not more than 5 years old for similar works with organisation names, order no. & date, and performance certificates for supplied items.
Satisfactory completion certificates of supply orders executed.
TPIA/CA digital authentication of Technical QR supporting documents applies by estimated-cost band (≤ or > Rs.1.0 Crore without tax), with listed exceptions for proven OEM/OES/PSU track record and past GSECL orders.
Technical / make acceptability
Bidder must offer specified makes/technical specifications/standards only; material must be interchangeable one-to-one retrofit with existing LCP control transformers without site mechanical/electrical/dimensional modification.
Approved/existing makes listed (indcoil, pragati, indian transformers, EL, procon/proton controls, Quantam R-core, industrial transformers, star electrical, Accurate, Gujarat plug-in, Trans-power, PTL, AE, kalpa, precise electrical) or any other standard make supplied to Govt utilities/PSUs/SEBs/GUVNL subsidiaries or Pvt/Public Ltd companies.
Interchangeability cum retrofitment certificate required with supply; site visit allowed to measure dimensions; plant will not send photos.
Mandatory registrations
Active GSTIN registration and PAN with documentary proof are mandatory; without Active GSTIN offer is rejected and price bid not opened.
If one of two GST registrations is cancelled, No-due Certificate from GST Department required.
GSTIN, HSN Code & PAN must be mentioned in technical bid.
Stop-deal / blacklisting bar
Bidder and/or proprietor/partner/director must not be on stop dealing / banned for business dealing / blacklisted by GUVNL or any subsidiary (GSECL/GETCO/DGVCL/MGVCL/UGVCL/PGVCL); undertaking required with technical bid.
Conflict of interest / multi-bid / agent rules
Bidder with conflict of interest with other bidders for a quoted item is disqualified; participation in more than one bid disqualifies all related bids; one agent cannot represent two manufacturers; one manufacturer only one agent; holding/sister units only one quote.
Conflict covers common proprietor/partner/director, subsidies, same legal representative, information-sharing relationships, consultant who prepared specs, competition-act violations.
Employee relationship: if GSECL employee/relative holds ≥10% interest in bidder, GSECL will not deal; non-disclosure disqualifies.
Cartel / competition-act risk
If cartel is found or apprehended, GSECL may allot quantities to non-cartel bidders, initiate Competition Act actions, and/or blacklist/stop-deal bidders at sole discretion.
Consortium / JV
No consortium or joint-venture bidding framework is provided in this tender set.
Rules address single bidders, agents of manufacturers, and sister/holding units rather than JV equity structures.
Commercial acceptances required
Bidder must accept GSECL payment terms, penalty, security, delivery period as required, minimum 120-day validity, and Purchase Agreement clause (confirmed in Annexure-10).
Price justification undertaking (Annexure-13): not accepted/executed LOA/PO at lower unit ex-works price in GSECL/GUVNL subsidiaries/CPSU/SPSU/IPP from 6 months before to 2 months after bid submission date.
Scope of work
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
7
Procurement summary
Supply (goods) of various types of control transformers for local control panels at 2×250 MW Bhavnagar Lignite Thermal Power Station (BLTPS), Padva under Tender ME-128/10/874/BLTPS/2026, RFQ EMD/77176, n-Procure tender ID 321739.
Schedule covers 25 control-transformer variants totalling 143 numbers, ranging from 50 VA to 10 kVA (and one 10 kW/10 kVA unit), predominantly 1-ph dry-type units with 415 V class primaries and 24/110/230/240 V secondaries as specified per line.
Key quantities include: 50VA 415/110 — 50 Nos; 5 kVA 415/240 — 12 Nos; 100VA 230/24 — 10 Nos; 220VA/200VA 415/110 — 7 Nos; multiple 100VA–3kVA lines at 2–6 Nos; 10 kVA dry — 3 Nos; 10 kW/10 kVA 415 to 160/170/180 V — 1 No.
IRRESPECTIVE OF ITEM CODE AND DESCRIPTION, material must be supplied as per DETAIL TECHNICAL SPECIFICATION only (pages 31–33 / 15–17).
Applicable standards cited on selected lines include IS 2026, IS 11171, IS 12021, IEC-60076.
HSN codes columns are blank for bidder fill-in on technical/price schedules.
Delivery location, packing and documents with supply
Delivery F.O.R. main store, BLTPS, Padva, Bhavnagar; well packed to avoid transit damage; datasheet and GA drawing for each transformer with supply; interchangeability cum retrofitment certificate with supply.
Transit-damaged material replaced free of cost by bidder without delay.
Rejected materials to be collected within 30 days of rejection intimation or may be disposed and forfeited.
Delivery period
Entire supply to be delivered within 12 weeks from the date of LOI.
Bidder must confirm delivery period as per GSECL requirement in technical bid / Annexure-10.
Guarantee / warranty of supplies
Guarantee 18 months from date of supply/receipt at site or 12 months from commissioning, whichever earlier, covering manufacturing defect, transit damage and poor workmanship; free replacement.
Inspection / testing
GSECL reserves rights to test supplied items; if results not as per specifications/dimensionally unfit, entire/part supply may be rejected.
General commercial terms also provide pre-dispatch inspection notice (15 days general stores / 30 days plant & equipment) and audit-inspection sampling with up to 30% end-cost deduction if consumed non-conforming lots.
Exclusions / not in scope
Scope is supply of control transformers only; no erection/commissioning package is described as bidder scope in the technical conditions (though general penalty wording also mentions erection/testing delays if ordered).
Site photos will not be sent; dimensional confirmation is bidder's responsibility via optional site visit.
Required documents & submission
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
33
Submission mode and portal
100% e-tender on https://tender.nprocure.com: technical bid PDF (300 dpi or higher), notarized or self-attested, online only; price bid only on n-procure Schedule-B; no hard-copy tender documents accepted for bid evaluation.
Also view/download from www.gsecl.in and www.guvnl.com.
Uploaded scanned PDFs must remain legible and not password-protected.
Fill all online annexures/forms (word file attached) line-by-line with supporting authentic documents.
Evaluation only on online data/details/documents.
Shortfall/clarification docs may later be sought in physical form or e-mail.
Digital signature
DSC Category IIIb required for e-procurement; certifying agencies listed (SafeScrypt, TCS, MTNL, (n)Code Solutions/GNFC); training/support via (n)Code Solutions Ahmedabad.
Toll Free DSC Support 1800-233-1010; nProcure Support 1800-233-7944; Phone 079-26857316/17/18.
Physical originals (instruments only)
Despite 'no hard copy documents' for the bid set, Demand Draft/Pay Order/Bank Guarantee originals (where used for fee/EMD) must be sent by RPAD/Speed Post within 5 days of Technical Bid opening to CE (Gen), BLTPS Padva.
See contradictions for tension with blanket no-hard-copy wording.
Signing / attestation
Tender documents to be notarized or self-attested; all annexures duly signed; tender submitted duly signed without removing pages; Integrity Pact and undertakings with seal & signature.
Agreement (post-award, order > Rs.5 lacs) on non-judicial stamp paper of Rs.300/- duly notarized; seal and sign on each page of agreement required.
EMD/SD/PBG bank guarantees on Rs.300/- stamp paper (formats).
Corrigendum analysis
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
2
Three time-limit extensions (date chain only)
Only amendments issued are successive due-date extensions for online submission and technical opening of Sr. 6–10 (Ext-3 covers Sr. 06 to 08 & 10, which includes this Sr.10 tender); no change to scope, EMD, fee or commercial conditions found in corrigendum PDFs.
Original NIT 128(B) for Sr 6 to 10: last upload/price fill and tech opening 01.08.2026 (upload to 17:30; opening 18:00 if possible).
Extension-1: 13.08.2026 for both submission and tech opening.
Extension-2: 25.08.2026 for both.
Extension-3: 08.09.2026 for both (Sr 06 to 08 & 10).
EMD Rs.101185/- and tender fee Rs.2950/- unchanged across notices for ME-128/10/874.
Action for bidder: submit by 08.09.2026 17:30 on n-procure; watch portal for price-bid opening mail.
Final applicable snapshot after all corrigenda
Finally applicable for ME-128/10/874 (Sr.10, ID 321739): bid upload & price fill by 08.09.2026 17:30; preliminary/technical opening 08.09.2026 18:00 (if possible); price bid opening via n-procure intimation; EMD Rs.1,01,185/-; tender fee Rs.2,950/-; validity 120 days from actual technical bid opening; other booklet/STC conditions unchanged by corrigenda.
Impact: three extensions only — pure calendar relief; no commercial renegotiation via corrigendum.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
6
No hard-copy bid vs physical DD/PO/BG within 5 days
NIT repeatedly says no hard copy documents shall be accepted and evaluation is online-only, yet the tender booklet requires physical submission of DD/Pay Order/BG to BLTPS within 5 days of Technical Bid opening.
Prevailing practical reading: bid content is online-only; original fee/EMD instruments (if not pure online transfer) still follow the 5-day physical route stated in the tender booklet notice page.
Supply Terms also still speak of EMD cover documents in physical form for type tests — largely generic and may not fit this e-only NIT.
Vendor registration compulsory vs not compulsory
E-tender notice states vendor registration with GSECL is not compulsory for this tender; general Supply Terms say vendor registration is compulsory to participate and price bid may be blocked without registration certificate.
For this NIT, the specific notice line that registration is not compulsory should be followed for bid submission eligibility; general STC registration regime is the conflicting baseline document.
Security Deposit quantum and timeline — tender booklet vs Supply Terms
Tender booklet: SD within 10 days of LOI at 5% (or 3%/exempt bands) and nil if order < Rs.2 Lakh. Supply Terms: SD within 15 days of LOA, payable irrespective of SSI/NSIC exemption, with separate item-wise % tables (OCR incomplete for Generation SD row) and warranty PBG tables.
STC Clause 9.3/41.3 state Bank Guarantee / Performance Guarantee 'shall be considered as per Tender terms' — supporting preference for the ME booklet SD table on execution SD percentage/timeline, while warranty PBG still comes from STC/LOI formats.
Bidder should clarify which SD% and whether warranty PBG is additionally demanded before accepting LOI.
EMD instrument threshold wording differs
Tender booklet uses Rs.3 Lakhs threshold for mandatory DD/BG options; Supply Terms clause 8.8 uses Rs.1 Lac threshold and different unsuccessful-EMD return period (15 days vs 07 days in booklet/notice).
This tender's EMD is Rs.1,01,185/- so both thresholds are relevant differently; tender-specific booklet/notice terms should be applied first, with STC as general background.
Item description vs detailed technical specification mismatches
Several Schedule-B/technical-bid short descriptions disagree with the mandatory DETAIL TECHNICAL SPECIFICATION block (which prevails per explicit note).
Example: Sr.2 short text '220VA' vs detail 'RATED OUTPUT: 200VA'.
Example: Sr.19 schedule 'Pri: 0-380-400-420-440, Sec: 0-22-24-26 V' vs detail rating 63VA model A1302 Pri 0-220 / Sec 0-24V.
Example: Sr.16/17 schedule VS=0-24-110 V or 24 V vs detail Sec 55-0-55V.
Action: quote and manufacture strictly to DETAIL TECHNICAL SPECIFICATION and confirm via site measurements for retrofit.
EMD exemption lists differ in framing (Annexure-A vs STC Gujarat purchase policy/SSI-CSPO path)
Booklet Annexure-A lists Udyam MSE manufacturers, Start-ups, Khadi/KVIC, PSUs, large OEMs ≥500 Cr, BIS-validated sellers, etc.; Supply Terms emphasize Gujarat SSI with CSPO/NSIC/DGS&D path and Gujarat Purchase Policy-2016, and state outside-Gujarat parties get no PBG relaxation.
Bidders should map their exemption claim to Annexure-A as printed in this tender/NIT and upload matching proofs; do not assume STC-only Gujarat SSI path is the sole route.
Pre-bid queries
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
6
Which text governs conflicting transformer ratings?
Confirm that DETAIL TECHNICAL SPECIFICATION (and existing installed nameplate dimensions) overrides conflicting short descriptions in Technical Bid/Schedule-B for all 25 lines, and whether GSECL will share nameplate data if site visit is not feasible.
Material commercial impact: wrong VA/ratio/taps causes rejection and free replacement under retrofit clause.
Documents say no photos will be sent from plant.
Is GSECL vendor registration required before price-bid opening?
Seek written confirmation that the NIT line 'Vendor registration with GSECL is not compulsory' prevails over Supply Terms compulsory registration / price-bid blocking language.
Bid/no-bid and compliance cost hinge on this for unregistered suppliers.
Execution SD % / timeline and whether warranty PBG is extra
Confirm applicable Security Deposit percentage and due date (10 days from LOI at 5%/3% per booklet vs 15 days LOA and STC item-wise table), and whether a separate Generation & other warranty PBG (10%/4%) is mandatory in addition to execution SD.
Cash-flow and BG arrangement risk; LOI pack contains both BG formats.
Physical instrument courier vs pure online EMD
If EMD/fee is paid fully by RTGS/NEFT/online from business account and proof uploaded, confirm that no physical document is required despite the 5-day DD/PO/BG clause.
Acceptability of 'any other standard make' evidence
Clarify minimum proof for alternate make (PO + performance to utilities/PSUs/etc.) and whether type-test reports are required for control transformers under this NIT (STC type-test clause is generic).
Eligibility pass/fail for non-listed brands.
Partial item bidding and evaluation basis
Confirm whether bidder must quote all 25 items or may offer partial lines, and whether evaluation/order is item-wise L1 or overall package.
Schedule-B has quantity-offered column suggesting possible partial offers; NIT also notes committee discretion if technical vs price quantities differ.
Risks
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
8
Delay liquidated damages / penalty
Delay beyond contractual period attracts penalty @ 0.5% per week or part thereof on delayed portion (end cost with taxes), capped at 10% of order value (end cost); taxes may be charged on penalty; receipt date at store used.
12-week full delivery for 25 varied ratings including 50 nos of 50VA is operationally tight if retrofit measurements slip.
Agreement also allows risk-and-cost purchase and damages on breach.
Retrofit / interchangeability absolute fit risk
Supply must be exact one-to-one interchangeable retrofit without any site modification; dimensional mismatch or failed tests can reject entire/part lot with free replacement obligation.
No plant photos; bidder must visit to measure all existing transformers.
Interchangeability certificate mandatory with supply.
Payment cash-flow and GST retention
No advance; only 80% on TRC in 30 days with GST retained until return proof; 20% waits for SR Note up to 45 days after good receipt — working-capital heavy for multi-item supply.
Security stack and BG conditions
EMD plus execution SD (typically 5%) plus possible warranty PBG (STC Generation table 10%) create stacked bank limits; corporate BG banned; one-time full-validity BG; encashment if not renewed before extension.
EMD forfeited on withdrawal during validity or failure to furnish execution PG (per STC 8.11).
If audit samples fail and material already consumed, GSECL may deduct up to 30% of end cost plus GST for the rejected lot; retesting costs on supplier.
Pre-dispatch inspection can still be waived and shifted to consignee final inspection.
Document incompleteness is fatal
Missing Active GSTIN, EMD/fee, executed order copies, or other required technical documents can cause outright ignore/rejection without correspondence; shortfall may be sought later only at GSECL option.
Annexure-13 lower-price undertaking widens post-bid price challenge window from 6 months before to 2 months after submission.
Unilateral process rights and cartel/blacklisting exposure
GSECL may accept/reject/cancel any offer, extend dates, re-advertise or modify process without assigning reasons; cartel findings may trigger stop-deal/blacklist and quantity reallocation.
Bidder bears all bid preparation/site visit costs with no reimbursement.
Dispute forum locked to Gujarat High Court Arbitration Centre
Unresolved disputes go to Arbitration Centre (Domestic and International), High Court of Gujarat at Ahmedabad under its rules; English proceedings; award final and binding.
Amicable settlement window 30 days first.
Contacts
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
5
Inviting / ordering authority
Addl. Chief Engineer (Generation) / A.C.E. (Gen), Station Head, GSECL BLTPS invites the e-tender; technical clarifications to The Chief Engineer (Gen), GSECL, Bhavnagar Lignite Thermal Power Station, Padva – 364 050, Dist. Bhavnagar.
Application Service Provider M/s. (n) Code Solutions, 301, GNFC Info tower, Bodakdev, Ahmedabad — DSC/nProcure support contacts as printed.
DSC Support toll-free 1800-233-1010; nProcure Support 1800-233-7944; Phone 079-26857316/17/18; Fax 079-26857321.
Portals to watch
Submission/view: https://tender.nprocure.com; view/download also www.gsecl.in and www.guvnl.com — bidders must self-monitor corrigenda; no separate correspondence.