Bid publication date
Bid document is dated 13-08-2026 (GeM Bid Number GEM/2026/B/7916153).
- No corrigendum in the tender pack amends this date.
Loading…
Information Technology Electronics Department Uttar Pradesh · Uttar Pradesh9754345
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
13 Aug 2026
17 Sept 2026
₹17.5 Cr
₹17.5 L
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
Bid document is dated 13-08-2026 (GeM Bid Number GEM/2026/B/7916153).
Pre-bid is on 20-08-2026 at 15:00 at UPDESCO Conference Hall, Lucknow; consolidated queries must be emailed by 20.08.2026, 01:00 P.M.
Bid End Date/Time is 05-09-2026 15:00:00.
Bid Opening Date/Time is 05-09-2026 15:30:00.
Bid Offer Validity is 90 days from the bid end date.
GeM contract period is 1 year; delivery/installation/commissioning is within 90 days of GeM Contract/work order; comprehensive onsite warranty is 36 months from installation/site acceptance.
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
Estimated Bid Value is INR 17,50,00,000 (inclusive of all taxes).
EMD is INR 17,50,000 (1% of estimated value); no exemption to any bidder; scanned proof with e-bid and original within 5 days of technical bid opening.
No tender fee or bid participation fee is stated in the bid or ATC.
Performance security is 5% of total Contract/Work Order value for 38 months from GeM Contract issuance.
Payments are milestone-based and back-to-back on receipt of IndiaAI funds by UPDESCO: 80% on SITC/installation certificates and 20% on operationalization/final completion; GeM also states payment within 45 days of SDAC.
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
Bidder must be a Company (Companies Act 2013/1956), LLP, Partnership Firm, or Proprietorship, with incorporation/registration, PAN and GST.
Minimum average annual turnover ₹8.75 Crore during any three consecutive financial years out of FY 2021-22, 2022-23, 2023-24 and 2024-25.
Bidder must have positive net worth in FY 2023-24 and 2024-25.
In last four FYs from 01.04.2022, complete similar ICT/computer/AI lab etc. projects for Central/State Govt/PSU/Govt educational institutions: 1×≥₹14 Cr OR 2×≥₹8.75 Cr OR 3×≥₹7 Cr.
Ink-signed bid-specific MAF required from OEMs of Workstation, All-in-One, Printers, IFPD/Digital Whiteboard, UPS and Network Switch; authorized dealer/channel partner may quote only one make & model per equipment type.
Workstation OEM must be Indian-registered company, ≥₹70 Cr average turnover (any 3 consecutive of FY 2022-23 to 2025-26), ≥3 years existence, UP service support, ≥300 workstations supplied to Govt/PSU/Govt institutes in FY 2023-24 to 2025-26 incl. current FY, not blacklisted, embossed motherboard logo, factory pre-loaded OS with DPK.
AIO OEM must meet same corporate/turnover/existence/support/blacklist/logo/OS conditions, plus supply of 4,450 AIO units with at least one single order of minimum 3,500 units to Govt/PSU/Govt institute in FY 2023-24, 2024-25 & 2025-26 including current FY.
Bidder must have operational office/service support centre in Uttar Pradesh, or undertake to establish a Project Coordination Office in UP within 15 days of Work Order.
OEMs of quoted Workstations and All-in-One Systems must hold valid ISO 9001, ISO 14000, ISO 20000 and ISO 27001; bidder must submit OEM datasheets and full technical compliance.
Bidder must not be blacklisted/debarred by Central/State Govt, PSU or Govt educational institution as on bid publication date; must hold valid PAN, GST and applicable statutory registrations.
No consortium/JV bidding structure is provided; subletting the project is prohibited and grounds for rejection.
MII Compliance is Yes; MSE Purchase Preference is No; Format-11 requires OEM local content/class/country-of-origin certification.
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
Selection of a System Integrator to establish 62 AI Data Labs across Uttar Pradesh under IndiaAI Mission: supply, installation, configuration, commissioning and comprehensive maintenance of lab IT equipment.
Each lab gets 2 high-end workstations, 18 mid-level AIOs, 1×10 KVA online UPS, 1 digital whiteboard/IFPD, networking/audio/printer/consumables/hardware kits; totals for 62 labs include 124 workstations and 1,116 AIOs.
Labs are at Government ITI institutes across Uttar Pradesh (Appendix-1 list); consignee address on GeM is UPDESCO, Lucknow; site-wise delivery contacts issued after PDI.
Complete delivery, installation and commissioning at ITI level within 90 days from GeM Contract/work order; PDI mandatory before dispatch; final acceptance after installation.
3-year comprehensive onsite warranty from site acceptance/installation, with 24-hour response and 48-hour resolution SLAs, standby replacement, helpdesk and genuine spares.
Buyer may increase/decrease quantity or duration up to 25% under GeM/option clause; for lumpsum service contracts, scope/value may increase up to 25% with service provider consent.
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
Two-packet e-bid on GeM Portal (https://gem.gov.in / bidplus); technical and financial packets as per GeM two-packet process, with Reverse Auction after technical qualification.
Bid signed by duly authorized person; scanned EMD with e-bid and original EMD to Tendering Authority office within 5 days of technical bid opening; successful bidder signs Format-1 contract within 7 days of GeM notification.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
The AI found nothing to report for this question.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
GeM bid includes standard EMD exemption language, but buyer ATC and bid-specific text expressly bar any EMD exemption and mandate rejection without EMD; ATC prevails.
GeM standard past-experience clause uses 40%/50%/80% of estimated cost over current+last three FYs, while ATC Clause 7 sets ₹14 Cr / ₹8.75 Cr / ₹7 Cr over four FYs from 01.04.2022 with a defined similar-work definition; ATC overrides.
GeM Bid Details state Contract Period 1 Year(s), but ATC requires 36-month comprehensive warranty, 38-month initial PBG and SLA through warranty; long-term support obligations outlast the stated 1-year contract period.
GeM states payment within 45 days of SDAC/online bills, while ATC makes payment contingent on UPDESCO receiving corresponding funds from IndiaAI and uses 80/20 milestones; ATC also disclaims interest for funding delays.
GeM bid ATC text highlights NEFT/RTGS and says EMD also acceptable as surety bond, while ATC Clause 5 details BG or RTGS/IMPS/NEFT; follow ATC Clause 5 instruments and still meet any GeM upload fields.
Scope and Appendix consistently refer to ITI institutes, but Formats 7 and 8 text say “IITs”; treat ITI/Appendix-1 locations as operative.
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Ask buyer to confirm in writing that ATC Clause 7 (₹14/8.75/7 Cr) supersedes GeM 40/50/80% similar-services clause for technical evaluation.
Seek clarity whether the 45-day GeM SDAC payment clock still applies if IndiaAI funds are delayed, and whether any provisional payment/interest protection exists.
Request confirmation whether the single order of minimum 3,500 AIOs can be cumulative across amendments/extensions of one contract, and what proof (completion vs supply) is accepted.
Ask when final ITI-wise addresses/contacts will be frozen, how site-not-ready delays are certified, and whether such delays are excluded from the 90-day LD clock and 80% milestone.
Clarify what constitutes “inauguration”/operationalization for the final 20%, who schedules it, and maximum time from SITC to Milestone-2 if inauguration is delayed by buyer/institute.
Ask which parties sign the tripartite agreement (UPDESCO/IndiaAI/Institute/Supplier), and confirm ATC Format-1 conditions prevail over the GeM-generated contract as stated.
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
Payments depend on UPDESCO receiving IndiaAI funds; no advance/LC and no interest/compensation for delayed government funding.
SITC across 62 ITIs within 90 days; LD 0.1% per day of undelivered/late quantity, capped at 10% of order value for a particular district, then possible termination and PBG forfeiture.
₹200/day response delay and ₹500/day resolution delay per incident; total SLA penalty capped at 10% of contract value; max penalty/repeated failure can lead to termination, PBG forfeiture and debarment.
Buyer may terminate for convenience with 15 days’ notice; default cure only 7 days; sole arbitrator nominated by ACS/PS IT & Electronics after mutual consent; Lucknow jurisdiction.
₹70 Cr OEM turnover, embossed logo, factory OS/DPK, and especially 3,500-unit single AIO order create supply-chain concentration and compliance risk; only one make/model per equipment type for dealers.
5% PBG locked ~38 months plus 3 months after warranty; subletting prohibited; option clause can change quantity/duration up to 25%.
Misrepresentation, common interests across bidders, or false land-border/local-content declarations can cause rejection, termination, PBG forfeiture, debarment and legal action.
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
U.P. Development Systems Corporation Ltd. (UPDESCO), under Information Technology And Electronics Department, Uttar Pradesh.
Pre-bid queries to [email protected]; GeM HOD grievance email [email protected]; Buyer email [email protected].
Original Bid Security/EMD must reach the office of the Tendering Authority (Managing Director, UPDESCO, II Floor, Uptron Building, Near Gomti Barrage, Gomti Nagar, Lucknow - 226010) within 5 days of technical bid opening.