Publication / bid dated
Bid document dated 12-09-2026 (GEM/2026/B/8013829).
- No corrigendum amends this date in the tender pack.
Loading…
Power Amplifier
Bharat Dynamics Limited · Visakhapatanam, Andhra Pradesh9866810
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
12 Sept 2026
24 Sept 2026
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
Bid document dated 12-09-2026 (GEM/2026/B/8013829).
Bid End Date/Time is 21-09-2026 10:00:00.
Bid Opening Date/Time is 22-09-2026 10:00:00.
Bid Offer Validity is 180 days from Bid End Date.
Delivery is 180 days / within 06 months from the date of PO (same timeline stated two ways).
Warranty is 18 months from the date of acceptance of item at BDL.
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
No tender value, estimated cost or BOQ amount is stated in the bid documents.
EMD is not required.
No tender document fee or bid participation fee is charged in this bid.
ePBG/Performance Security is 5.00% of contract value for 21 months; may be furnished as ePBG (Advisory Bank: State Bank of India) or online RTGS/internet banking to BDL’s Union Bank account within 15 days of award.
ATC payment: 95% basic + 100% taxes within 30 days after receipt and acceptance; remaining 5% basic against PBG. Bid header sets overall payment timeline as within 30 days of CRAC (superseding GeM GTC’s default 10 days).
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
Single Tender Applicable: Yes — only ELECTRONIC ENTERPRISES INDIA PRIVATE LIMITED is listed for participation.
Only Class-I and Class-II local suppliers may bid; non-local suppliers are not eligible. Minimum local content: 50% (Class 1) and 20% (Class 2).
MSE Purchase Preference is Yes (upto L1+15% for 25% quantity), but MSE/Startup relaxation for Years of Experience and Turnover is No.
Bidder must provide OEM manufacturing / manufacturer authorisation with the bid; authorised distributors must furnish OEM authorisation with OEM contact details.
Bidder must comply with Annexure-1 technical specifications for Krohn-Hite Model 7500 and accept AS 9100D / quality ATC conditions including no counterfeit parts.
Any bidder from a country sharing a land border with India is eligible only if registered with the Competent Authority; false declaration is ground for immediate termination and legal action.
Vendor must declare any recent demerger/merger; failure to declare entitles BDL to debarment if discovered later.
Seller should have well-established Installation, Commissioning, Training, Troubleshooting and Maintenance Service group in INDIA; service-centre details near consignee destinations to be uploaded with the bid.
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
Supply of 1 set Power Amplifier — Krohn-Hite Model 7500 Wideband Power Amplifier — with specified accessories.
Wideband power amplifier DC to 1 MHz, >75 W continuous power, up to 125 Vrms (to 100 kHz), voltage gain 0–40 dB, low distortion, short-circuit protection — full specs in Annexure-1 datasheet.
Deliver free of cost to BDL Visakhapatnam consignee within 06 months / 180 days; acceptance on CoCs/calibration reports and demonstration at BDL.
18 months warranty from acceptance at BDL; free repair/replace during warranty; OEM warranty certificates at delivery.
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
Online two-packet bid on Government e-Marketplace (GeM); bid number GEM/2026/B/8013829.
Offer is liable to rejection if certificates/documents sought in Bid, ATC and any Corrigendum are not uploaded.
At supply: OEM test certificates, calibration reports, CoCs, warranty certificate, ePBG proof, GST invoice and a checklist of submitted documents; BDL will not acknowledge valid supply until mandatory PO documents are provided.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
The AI found nothing to report for this question.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
Bid Payment Timelines state payment within 30 days of CRAC (superseding GTC 10-day 100% payment), while ATC clause 10 withholds 5% basic until PBG is submitted.
BDL ATC LD is 0.5%/week capped at 10% of delayed stores’ price; GeM GTC LD is 0.5%/week of delayed quantity value, generally capped at 5% of total contract value (10% only if delay is inordinate >25% of completion period).
ATC requires PBG valid till warranty + 3 months claim; GeM GTC states Performance Security valid for 2 months beyond completion of all contractual obligations including warranty. Bid ePBG duration is 21 months (fits 18-month warranty + 3 months).
Bid is Single Tender limited to ELECTRONIC ENTERPRISES INDIA PRIVATE LIMITED for Krohn-Hite-7500, while MII clauses bar non-local suppliers and require min 50%/20% local content for Class 1/2.
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Ask BDL to confirm whether only ELECTRONIC ENTERPRISES INDIA PVT LTD may bid, and how Class-1/Class-2 local-content thresholds apply to this foreign-OEM Model 7500 supply.
Request confirmation that ATC clause 10 (95% basic + 100% taxes, 5% against PBG) overrides the bid-header ‘within 30 days of CRAC’ wording and GTC 10-day 100% default.
Ask whether BDL ATC max 10% LD or GeM GTC 5%/10%-inordinate-delay framework will be enforced.
Seek a definitive checklist mapping the GeM mandatory document fields to named ATC certificates to avoid technical rejection.
Request unmasked consignee address/contact and scope of ‘demonstration of item at BDL’ (on-site power, interfaces, pass criteria, who bears demo cost/time).
Confirm whether only RK519, CAB-018 and CAB-025 are mandatory accessories, or any datasheet options (e.g. remote gain 011, extended warranty EW7500, other cables) are also required.
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
Delivery within 06 months/180 days is of the essence; LD 0.5%/week up to 10% under ATC; tax increases during delay extension not borne by BDL if vendor-caused.
5% ePBG for 21 months plus ATC 5% basic retention against PBG; GTC makes payments due only after PBG receipt/verification — working-capital risk.
18-month warranty with free repair/replace; seller expected to maintain India service group and upload nearby service-centre details — ongoing support liability for an imported instrument.
Stringent quality clauses: no non-conforming or counterfeit parts; notify process/provider changes; BDL/customer/regulator right of access across supply chain; retain records 3 years; ISO 14001:2015 EMS compliance.
Single-tender restriction plus Class-1/2-only MII rule and land-border registration create high bid-rejection and false-declaration termination risk if classifications are wrong.
Bid lists Arbitration Clause: No and Mediation Clause: No — dispute-resolution path is less favourable than multi-tier ADR and defaults to whatever GeM GTC/legal remedies remain.
Bidders must self-check GST; reimbursement limited to actuals or applicable rates, whichever lower, and not above quoted GST % — under/over-quoting GST hurts margin or competitiveness.
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
Ministry of Defence — Department of Defence Production — Bharat Dynamics Limited (BDL).
Buyer Email: [email protected]; HOD grievance redressal Email: [email protected].
Performance security beneficiary: Manager-IMM, Gunuru Venkata Satish, Bharat Dynamics Limited Hyderabad.
Consignee/Reporting Officer and full address are masked; delivery location is Visakhapatnam (quantity 1).