Publication / issue
Tender Notice digitally signed and issued on 10.08.2026 (eProcure).
- Tendernotice_1.pdf digital signature timestamp: 2026.08.10 17:00:13 IST.
Loading…
Non-Comprehensive Operation and Maintenance Contract for the Shore Power Supply facility at Coal Berth 1 and 2 at Kamarajar Port
Ennore Port Limited · Thiruvallur, Tamil Nadu2026_MoS_921462_1
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
10 Aug 2026
7 Sept 2026
₹46.6 L
₹93,120
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
Tender Notice digitally signed and issued on 10.08.2026 (eProcure).
Written pre-bid queries due by 17:00 hrs on 19.08.2026.
Pre-bid meeting at 11:00 hrs on 20.08.2026 at Port Administrative Office, Vallur Post, Chennai-600 120.
Online bid submission closes at 15:00 hrs on 07.09.2026 on www.eprocure.gov.in / eprocure.gov.in.
Technical bid (Cover-1) opens at 15:30 hrs on 08.09.2026 at Kamarajar Port Limited, Vallur Post, Chennai-600 120 (e-Procurement mode).
Offer validity is 90 days; documents conflict on whether the 90 days run from submission deadline or from tender opening.
O&M contract period is 12 months from Work Order/LoA commencement date; performance security and agreement due within 14 days of award documents.
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
Estimated cost Rs.46,56,000/- plus applicable GST.
EMD Rs.93,120/- by DD or bank guarantee; NSIC/MSME firms exempt; physical instrument must reach KPL before bid closing.
No tender document fee is stated in the tender documents.
Successful bidder must furnish security deposit cum Performance Guarantee of 10% of total contract price within 14 days of work order.
Quote basic unit rates inclusive of all taxes except GST; GST reimbursed after ITC reflection; monthly payments against GST-compliant invoices; rates fixed for contract duration.
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
Bidder must have a valid GST number.
Minimum valid contractor’s licence Grade A (Form EA) issued by Tamil Nadu Government Electrical Licensing Board is mandatory.
Average annual financial turnover over last three years ending 31 March of previous financial year must be at least Rs.13.97 Lakh (30% of estimated cost).
In any one of the last seven years (ending last day of month previous to invitation), at least 50% of the bidder’s annual value of work (CA-certified, escalated at 7% p.a. to bid/tender opening) must be from Electrical maintenance/Construction (Project) work.
Successfully completed similar works in last 7 years meeting 3×40% / 2×50% / 1×80% of estimated cost (excluding GST).
False representations, poor performance history, and post-award default can disqualify or debar bidders; KPL suspension/banning policy forms part of the tender.
No consortium, joint-venture, or multi-bidder association rules are prescribed in the tender documents.
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
Non-Comprehensive Operation and Maintenance (O&M) of the Shore Power Supply facility at Coal Berth-1 & 2, Kamarajar Port, Vallur, Chennai.
Scope covers shore-power operations, routine/preventive and breakdown maintenance, documentation, safety, and coordination—not major equipment supply.
Deploy minimum 1 Site In-charge/Manager and 3 Technicians every day throughout the contract, including holidays/Sundays and extended vessel operations as directed.
12-month O&M service quantity (12 months in BOQ); major spares/equipment by KPL; no housing of contractor employees on KPL premises.
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
Bids only through e-procurement two-cover system on www.eprocure.gov.in / eprocure.gov.in by 15:00 hrs on 07.09.2026.
Cover-1 Technical Bid opens first; Price Bid of only technically eligible bidders opens online later.
EMD DD/BG must physically reach KPL before bid closing; modification/withdrawal language mixes e-procurement with sealed envelope marking.
Technical/financial proofs need CA certification and notarised/self-attestation as specified; Form of Tender signed & sealed; PoA on stamp paper.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
The AI found nothing to report for this question.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
Clause 1.4 measures 90-day validity from last submission date, while Clause 3.7 and Form of Tender measure it from tender opening—about a one-day gap here, but material if openings slip.
GCC starts the 12-month tenure from Work Order/LoA date, while Form of Tender ties the 12 months to execution of the Contract.
Clause 3.8 cites due date as '1500Hrs, xx.xx.2026' and simultaneously requires e-Procurement only and sealed physical envelopes for modification notices.
Annexures I–II and Form 2A footers still read 'Comprehensive Annual Maintenance Contract for maintaining the Airconditioners at Kamarajar Port' while body text is for Shore Power O&M.
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Ask KPL to state the exact minimum 'annual value of work' rupee figure required under clause 3.1, and which years/documents prove the ≥50% electrical share.
Confirm process, timeline and acceptable evidence for TN Electrical Licensing Board endorsement/verification of other-State/UT Grade A licences before bid due date.
Confirm exact receiving office/desk, acceptable delivery mode (hand/courier), and whether scanned EMD upload is also required online.
Seek a written list of minor consumables contractor must supply versus major spares/equipment KPL supplies, and whether specialised testing/OEM call-outs are reimbursable.
Ask which 90-day validity start date prevails and whether LOA, Work Order and 'contract' are the same instrument for the 14-day PS/agreement clocks and 12-month start.
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
Any failure to carry out scope to KPL’s satisfaction may lead to forfeiture of Performance Security and termination; KPL may also hire third-party cover at contractor’s cost.
Fixed minimum crew (1+3) must cover holidays/Sundays and extended vessel operations, with 30-minute breakdown response—labour cost and absenteeism risk is significant on a non-comprehensive monthly rate.
Rates are fixed for the contract with no adjustment; GST is reimbursed only after ITC reflection on KPL’s portal—cash-flow lag and statutory-cost risk sit with contractor until reimbursement evidence path is met.
10% performance security for contract period +60 days is heavy for a 12-month O&M; KPL may further increase PS if bid is seriously unbalanced.
Contractor solely bears injury/damage, labour-law compliance (Minimum Wages, PF, ESI, Workmen’s Compensation) and must keep personnel insured for full contract term; KPL may recover from dues/PS.
Non-TN licence without endorsement is summary rejection; private-client experience needs Form 26AS/TDS/UDIN audit trails—qualification risk is documentation-heavy.
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
Kamarajar Port Limited (A Company of Chennai Port Authority), Port Administrative Office, Vallur Post, Chennai – 600 120.
Deputy General Manager (C), Kamarajar Port Limited, Port Administrative Office, Vallur Post, Chennai-600 120; Tel 044-27950029 / 044-2795 0029.
Manager (Elect.) mobile 9600162167; Deputy Manager (Elect.) mobile 9597088338.
For CPPP/e-procure technical queries: [email protected] or phone 1-800-233-7315.
Pre-bid meeting and technical bid opening attendance venue is Kamarajar Port Limited, Port/Administrative Office, Vallur Post, Chennai-600 120.