Providing 1.00 MLD Water Supply Scheme to SIPCOT Jeyankondam
Providing 1.00 MLD of Water Supply to SIPCOT at Jeyankondam in Ariyalur District
TWAD · Ariyalur, Tamil Nadu·2026_TWAD_682765_2
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
Published
25 Jul 2026
Closes
31 Jul 2026
Estimated value
₹12.9 Cr
EMD
₹9.7 L
Key dates
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
7
Publication / download window
IFB dated 17.06.2026; tender documents downloadable free from https://tntenders.gov.in from 25.06.2026 to 24.07.2026 up to 15:00 (server time) as stated in the IFB table.
IFB No. 01 /F.WSS to SIPCOT- Jeyankondam /SDO/CE-TNJ/2026/Dt.17.06.2026.
Cover and ITB Clause 21.1 fix bid submission on 31.07.2026, which is after the IFB download end date of 24.07.2026 — see contradictions.
Tendernotice_1.pdf is only a digital-signature stamp dated 25.06.2026 IST and carries no schedule text.
Site visit
Facilitated site visit on 06.07.2026 at 11:00 AM for bidders to understand site conditions ahead of the pre-bid meeting.
Site visit is bidder-facilitated by the Tender Inviting Authority; costs and risk remain with the bidder.
Pre-bid meeting
Pre-bid meeting on 09.07.2026 at 11:00 hours at the Office of the Chief Engineer, TWAD Board, Thanjavur; attendance is not mandatory.
Bidders are requested to submit questions in writing/cable to reach the Employer not later than one week before the meeting.
Online clarifications via the e-procurement system are answered if received earlier than 10 days prior to the bid submission deadline.
Addenda may be issued up to 48 hours before the deadline for submission / technical bid opening.
Bid submission deadline
Online bid submission deadline is 31.07.2026 up to 15:00 (3:00 P.M.) server time via https://tntenders.gov.in, as stated on the cover page and ITB Clause 21.1.
IFB table instead states Bid Submission 24.07.2026 upto 15:00 hours — conflict recorded under contradictions; cover page and Clause 21.1 are the detailed operative submission clauses.
Late bids cannot be submitted after due date/time as per server time.
If the specified date is a holiday for the Employer, bids are received up to the appointed time on the next working day.
Bid opening
IFB states Part-I/technical bid opening on 27.07.2026 at 15:30 hours online at the office of the Tender Invitee; this date conflicts with the 31.07.2026 submission deadline elsewhere.
Bids open online and can be viewed online by bidders.
After Part I evaluation, there is a 5-working-day complaint window before Part II (price bid) opening of qualified bidders.
Price-bid opening date/time is intimated to Part-I qualified bidders if changed.
Bid validity
Bids remain valid for not less than 120 days from the date of opening of the Technical Bid; shorter validity is non-responsive.
Employer may request extension in writing; refusal does not forfeit bid security, but agreement to extend requires extending bid security for the extension period.
Contract / completion timeline after award
Performance security and agreement within 28 days of Letter of Acceptance; contract start is the 28th day from work order; construction 12 months, trial run 3 months, then paid maintenance 12 months.
Financial milestones during construction: 30% by 3 months, 50% by 6 months, 70% by 9 months, 100% by 12 months.
Activity Chart to be submitted within 7 days of signing agreement.
Registered JV agreement (if JV) within 28 days of LoA or before concluding agreement, whichever earlier.
Financials
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
7
Estimated / approximate tender value
Approximate value including 18% GST is Rs.12.86 Crore; available bid capacity must exceed Rs.12.86 Crore.
Item-rate / two-cover e-tender; bidders quote rates in the BOQ on https://tntenders.gov.in.
Prices entirely in Indian Rupees.
Bid security (EMD)
Bid security Rs.9.65 Lakh (Rupees nine lakh sixty five thousand only) only through ONLINE and e-BG Mode on https://tntenders.gov.in; missing/stipulated form is non-responsive.
Unsuccessful bidders: returned promptly, not later than 30 days after bid validity expiry or bid finalisation, whichever is later.
Successful bidder: returned after performance security furnished and agreement signed; no interest payable.
Forfeited for withdrawal/modification during validity, non-acceptance of bid-price corrections, failure to furnish performance security or sign agreement in time, or severing conditions after acceptance.
IFB also states EMD payable Online Mode or eBG through the e-tendering website.
Tender document fee
No cost towards bid document is payable for forms downloaded from the designated website.
Performance security
Within 28 days of LoA, performance security as NSC/Post Office Savings Deposit (TN, pledged to EE, TWAD Board, RWS Division, Ariyalur) OR unconditional irrevocable BG from a Nationalised/Scheduled Bank branch in Tamil Nadu in prescribed format, scaled by bid percentage vs departmental value.
a) Any plus percentage and up to minus 5% of department value — 2% of contract value.
b) Minus 5% up to minus 15% — 4% of contract value.
c) More than minus 15% — 5% of contract value.
Also deliver non-judicial stamp paper for Rs.100 for executing the agreement.
Performance security released after Defect Liability Period; liable to forfeiture for failure leading to termination.
Successful non-registered contractors must get registered in TWAD Board.
Retention / withheld amounts and DLP securities
Staged payments retain final 5% against 2-year BG; for water-retaining structures 40% of each bill may be withheld for water-tightness (or indemnity bond in lieu); after DLP a fresh 5% BG on water-retaining structure value for further 3 years is required.
Civil works: up to 95% of measured/check-measured quantity; 2.5% on commissioning of the scheme; 2.5% on commissioning of entire scheme against unconditional irrevocable BG for 2 years.
Pipes: 65% after supply at site; 85% after laying/jointing/testing; 95% after trial run/commissioning of main; 100% after entire scheme commissioning against 5% BG for 2 years.
Mechanical items: 75% supply / 90% erection / 95% commissioning / 100% after entire scheme against 5% BG for 2 years.
100% construction payment may be made on commissioning / pre-final against 5% BG on construction works for 2-year Defect Liability Period; final bill after maintenance period.
Indemnity bond in prescribed form on Rs.100 stamp paper may replace the 40% water-tightness withholding for reservoirs/sumps; 24-month water-tightness guarantee from completion and commissioning.
Mobilisation advance
Mobilisation advance up to 10% of agreed construction contract value, interest-bearing at the rate notified by Government, against irrevocable bank guarantee.
Recovery starts in the next Payment Certificate after certified interim payments (excluding advance and retention) exceed 30% of Contract value (Construction Period Section I) less Provisional Sums.
Amortization at 20% of each Payment Certificate until 80% of Contract amount received or agreement period ends, whichever earlier.
Taxes, recoveries and price adjustment
GST TDS from every payment; Income Tax TDS at prevailing rates; 1% construction-worker welfare fund paid by Employer to the welfare board; price adjustment applies (works ≥ Rs.100 lakhs) per specified GOs for cement, steel, labour etc.
Price adjustment applies only when rates change by 3% or more vs estimated rates (RBI index); calculated on departmental estimated cost (for minus tenders, value of work done).
Price adjustment ceases for work beyond agreement period (with stated exceptions for official suspension/EOT causes).
Bills monthly in M.Book format; EE to scrutinise and pay within 6 weeks of bill submission.
Accepted Contract Amount covers entire works including design, install, test, commission, trial operation (Section I) and O&M (Section II).
Eligibility
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
9
Who may bid / registration
Open invitation; IFB eligibility is Registered Class I Contractors (Civil). Successful non-TWAD-registered contractors must register in TWAD Board after award.
Bidder must not be/have been associated with the design consultant or supervision consultant/affiliates.
One bid per bidder for the whole scheme; participating in more than one bid (other than as subcontractor) disqualifies.
Bids by individuals, proprietorships, partnerships and limited companies allowed with prescribed signing/PoA evidence.
Financial qualification
In any one of last five FYs (2020-21 to 2024-25): annual turnover ≥ Rs.9.65 Cr (75% of BOQ); and minimum annual turnover in any two of those years ≥ Rs.4.24 Cr (33% of BOQ); minimum cash flow Rs.3.22 Cr (= 3 months × BOQ / period).
Audited balance sheets for last five FYs and CA-certified turnover in Annexure-II required.
Total monetary value of civil works for past five years in Annexure-I.
Credit-line / access to finance evidence in Annexure-VIII (bank certificate).
Similar work experience
100% completed and commissioned Water Supply Scheme in last five years of value not less than Rs.5.14 Cr under a single agreement (40% of BOQ) OR Rs.7.72 Cr under two agreements (60% of BOQ).
Experience from Central/State Govt Depts/Quasi-Govt/Govt Undertakings or Private Organisations accepted with prescribed certificate standards.
Govt certificates must be by officer not below Executive Engineer; private org certificates need photos, GM-rank certificate countersigned by AEE-rank Govt engineer and notarised, plus IT/TDS/GST financial transaction proof.
Subcontractor experience not counted toward main contractor eligibility unless prior approved subcontract with EE-rank certified copy, subcontract agreement and financial proofs.
Performance certificates must be Notary-attested copies and contain specified scheme/contract/performance component details.
Physical work experience (aggregate last five years)
Minimum aggregates: 1 No. collection/infiltration/intake/jack well (40% of 1 No.); PVC/HDPE/OPVC pipeline 8.032 km (30% of 26.774 km) including 1.338 km of 125 mm dia or higher (min 5% on 50% of higher-dia 250 mm pipe length); pumping machinery 20.142 kW aggregate with at least 1 No. of 16.785 kW or higher; RCC water-retaining structures 0.195 LL aggregate with at least 1 No. sump/SR of 0.33 LL or higher.
Pumping machinery: 30% of total requirement 67.14 kW → 20.142 kW; and min 1 No. of 50% of highest pump capacity 33.57 kW → 16.785 kW or higher.
RCC WRS: 30% of 0.65 LL → 0.195 LL; and min 1 No. of 50% of highest capacity 0.65 LL → 0.33 LL or higher.
Manufacturer experience also required for pumps (5 years production; min 50 units/year sold — specified brands/equivalent), valves above 200 mm (5 years; 200 units/year), and DI pipes (200% of total length required).
Bid capacity
Assessed Available Bid Capacity = A×N×1.5 − B must be more than the total bid value / Rs.12.86 Crore; N = 1 year; A and B updated to 2025-26 price level @ 6% p.a.
A = max value of civil engineering works executed in any one year during last five FYs (completed + in progress).
B = value of existing commitments and ongoing works to be completed during next 12 months.
Joint Venture rules
JV accepted. For works > Rs.1 Cr up to Rs.20 Cr: lead + one partner (1+1). Lead meets ≥50% and each other partner ≥25% of financial/bid-capacity criteria; all partners collectively 100%. Physical criteria may be met collectively; similar-work criterion may be met by any one partner.
JV partners should separately satisfy financial qualification for their participation and collectively satisfy physical qualification.
JV may be permitted for value not less than 25% of work put to tender; below 25%, subcontracting may be permitted.
Lead partner authorised via PoA of all partners; Employer corresponds only with lead; all partners jointly and severally liable.
Copy of JV Agreement with bid; registered JV Agreement within 28 days of LoA or before concluding agreement, whichever earlier.
Bid and agreement must be legally binding on all partners.
Subcontracting limits
Any single subcontract ≤15% of contract value; total subcontracted work ≤60%. EE written notice if a subcontract exceeds 10%; no reply in 15 days permits appointment. Subcontractors need two similar completed & commissioned works in last 5 years and cannot further sub-subcontract.
Assignment/transfer of contract not permitted; any subletting only with written consent of Engineer in charge.
Documentary evidence of proper subcontractor agreement to be furnished with bid (Annexure-XI).
Debarment / blacklisting and other disqualifiers
Bidders blacklisted/banned/debarred by any Central/State/UT Department/Undertaking/Organisation as on application date are disqualified; poor performance, false statements or litigation history in last 5 years also disqualify.
Annexure-X declaration of non-blacklisting mandatory.
Litigation details in Annexure-IX (notarised).
Disqualification for misleading/false representation; abandoning work; rescission attributable to non-performance; inordinate delays; consistent litigation against applicant; bankruptcy/financial failure.
Key personnel / technical staff obligation
For works up to Rs.50 Cr, mandatory deployment: 1 Project Manager (BE Civil, 15 yrs), 1 Deputy PM (BE Civil, 10 yrs), 2 Resident Engineers (BE Civil/Mech/Elec, 5 yrs), with monthly non-employment penalties of Rs.25,000 / 15,000 / 10,000 per person.
Key personnel proposal in Annexure-VII; technical staff undertaking in Annexure-XII.
Scope of work
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
4
Work overview
Procurement-and-construction contract for Providing 1.00 MLD Water Supply Scheme to SIPCOT Industrial Park at Jeyankondam / Jayankondam, Ariyalur District (Deposit work), including supply/installation of materials and machinery to BIS/TNBP/bid specs, commissioning, trial run and paid maintenance.
Two-cover item-rate e-tender under TWAD Board, Chief Engineer/Thanjavur.
IFB/Contract No.: 01 /F.WSS to SIPCOT- Jeyankondam /SDO/CE-TNJ/2026/Dt.17.06.2026.
BOQ header row once states "PROVIDING 1.10 MLD" while work name everywhere else is 1.00 MLD — see contradictions.
Key components and quantities
Salient components: Infiltration Well 4.50 m dia × 12 m depth – 1 No. at Thenkachiperumalnatham; DI connecting main (250 mm D/F lengths); 250 mm OPVC 12.5 KSC pumping main 27,000 m plus 20 m DI; Control Room 3 m × 4 m – 1 No.; RCC sump 65,000 litre – 1 No.
Connecting main DI: 250 mm D/F (3 m)–114 Nos; (2 m)–3 Nos; (1 m)–2 Nos.
Physical eligibility basis cites total pipeline length 26.774 km and pump requirement 67.14 kW / highest 33.57 kW; sump 0.65 LL — slight length variance vs 27,000 m OPVC in salient details.
BOQ includes infiltration well in River Coleroon near Thenkachiperumalnatham, pumping main materials & civil, open-well submersible pumpsets, valves, chambers, flowmeters and allied works.
Location
SIPCOT Industrial Park at Jeyankondam/Jayankondam in Ariyalur District, Tamil Nadu; infiltration well near Thenkachiperumalnatham / River Coleroon.
Section I construction 12 months from start (28th day from work order) with quarterly financial milestones, then 3-month trial run/commissioning/guarantee performance; Section II paid maintenance 12 months.
If satisfactory trial run completed within three months, contractor maintenance can commence on completion of trial run with minimum continuous designed supply for one month.
During construction and trial run, EB power cost borne by bidder; during Section II O&M, electricity for normal O&M borne by Employer.
Standards: relevant BIS, TNBP, bid documents; water-tightness testing per IS 3370 (Part-I) 1965 as amended.
Required documents & submission
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
32
Submission mode and portal
Electronic two-cover submission only on https://tntenders.gov.in; Part I Technical Bid and Part II Price Bid as separate online files; all documents digitally signed.
Bidder needs portal enrolment/registration and valid DSC (smart card/e-token) from authorised CA (e.g. Safescrypt, e-MudhraCA).
After online submission the system generates a unique time-stamped bid ID as acknowledgement.
No rates/prices in technical bid/first cover; Part II contains Price Bid alone.
Bid documents non-transferable; conditional tenders liable for rejection; alternative proposals not considered.
Language: English (supporting docs may be other languages with accurate English/Tamil translation).
Bids may be modified online any number of times before deadline; withdrawal after submission not allowed; modification after deadline may forfeit bid security.
Signing, attestation and physical originals
Online digital signing is primary; many identity/experience documents require Notary attestation. Bid security is online/e-BG only. Clause 24.2 also refers to original EMD at opening (conflicts with online-only EMD).
Proprietor/partner/authorised-signatory signatures to be Notary-attested as applicable (Clauses 2.2–2.4).
Registered Power of Attorney for bid signatory (7.1.2).
No separate general requirement for physical submission of technical envelopes is stated beyond online e-submission; agreement stamp paper Rs.100 after award.
Certificate that no correction/alteration was made to downloaded bid document and bidder will abide by all terms.
Corrigendum analysis
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
1
No corrigendum / addendum found in the tender pack
The supplied documents contain only Tendernotice_1.pdf, BidDocument.pdf and BOQ_827814.xls. No corrigendum, addendum or pre-bid reply document is present, so original document values apply as written (subject to internal conflicts noted under contradictions).
Bid document contemplates addenda/corrigenda via the portal (latest corrigendum on tntenders.gov.in) but none are included in this workspace pack.
Finally applying key values remain those stated in BidDocument/BOQ: approx value Rs.12.86 Cr; EMD Rs.9.65 Lakh; submission 31.07.2026 15:00 per cover/Cl.21.1; pre-bid 09.07.2026 11:00; validity 120 days from technical bid opening.
Contradictions
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
6
Bid submission deadline: 31.07.2026 vs 24.07.2026
Cover page and ITB Clause 21.1 fix online submission at 31.07.2026 15:00, while the IFB summary table states Bid Submission 24.07.2026 upto 15:00 and download end 24.07.2026.
Operative detailed clause for deadline is Clause 21.1 (and cover page) stating 31.07.2026 3:00 P.M.
IFB download window ending 24.07.2026 is inconsistent with a 31.07.2026 submission date unless later amended on the portal.
Bidders should confirm the live portal critical dates on https://tntenders.gov.in before bidding.
Bid opening date earlier than detailed submission deadline
IFB states bid opening 27.07.2026 at 15:30, which is before the 31.07.2026 submission deadline in Clause 21.1/cover — impossible without amendment.
No other explicit bid-opening calendar date is printed in Clauses 24.x (only procedure).
Until a corrigendum reconciles dates, treat portal critical dates as essential confirmation; document conflict remains unresolved in the pack.
EMD form: online/e-BG only vs original EMD at opening
Clauses 16.1 and IFB require Bid Security only via ONLINE and e-BG, but Clause 24.2 says bids without original EMD/EMD exemption document at opening will be rejected and technical bids not opened.
Practical compliance path stated for bidders is online/e-BG on tntenders.gov.in; the 'original EMD' wording appears residual and creates rejection risk if interpreted literally.
Seek clarification/pre-bid confirmation whether any physical EMD instrument is still expected.
Scheme capacity: 1.00 MLD vs BOQ line '1.10 MLD'
Bid document title/IFB/salient details consistently state 1.00 MLD, but one BOQ item description heading reads PROVIDING 1.10 MLD WATER SUPPLY SCHEME.
BOQ work-name header elsewhere still says 1.00 MLD; treat 1.00 MLD as the scheme requirement unless BOQ quantities clearly implement 1.10 MLD.
Clarify with Employer which capacity governs design/guarantee.
Pumping main length: 27,000 m vs 26.774 km eligibility base
Salient details specify 250 mm OPVC 12.5 KSC pipe 27,000 m, while physical experience criteria use total length 26.774 km for the 30%/higher-dia thresholds.
Difference is about 226 m; eligibility percentages are computed on 26.774 km in the qualification table.
BOQ quantities should be checked item-wise for the payable length; qualification table values are fixed as printed (8.032 km / 1.338 km).
GCC starting page vs Annexure pagination
Index lists General Conditions of Contract from page 69, but pages 61–72 are Annexures I–XII and GCC definitions appear later; use clause titles rather than index page map alone.
Does not change commercial terms but can mislead navigation.
Pre-bid queries
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
6
Reconcile critical dates on portal vs IFB vs Clause 21.1
Please confirm the final download end date, bid submission deadline and technical/financial bid opening dates/times on https://tntenders.gov.in, given IFB (24/27 Jul 2026) conflicts with cover/Clause 21.1 (submission 31.07.2026 15:00).
Ask whether any corrigendum has been or will be issued to supersede the IFB table.
Confirm holiday-shift rule application if 31.07.2026 is a holiday.
Is any physical/original EMD still required at opening?
Clause 16.1 mandates ONLINE/e-BG only, but Clause 24.2 rejects bids without original EMD at opening — please confirm exclusive online/e-BG compliance and whether any hard-copy instrument or exemption certificate must reach the CE office, and by when.
Also confirm e-BG claim period/validity expectation relative to 120-day bid validity.
Confirm governing scheme capacity 1.00 vs 1.10 MLD and pipeline length base
Please confirm whether the scheme guarantee/design capacity is 1.00 MLD or 1.10 MLD (BOQ heading) and whether payable/qualification pipeline length is 27,000 m or 26.774 km.
Affects design duty of pumps, trial-run acceptance and experience calculation thresholds.
Class I registration — which register is mandatory at bid stage?
IFB eligibility line says Registered Class I Contractors (Civil), while Clause 6 opens to any bidder meeting requirements and Clause 33 allows post-award TWAD registration — please confirm whether non-Class-I or non-TWAD-registered firms can bid if financial/physical criteria are met.
Material pass/fail for many potential bidders and JVs.
Paid maintenance scope, staffing, payment and power/consumables risk
Please detail measurable O&M KPIs for the 12-month paid maintenance, payment schedule/BOQ items for maintenance, mandatory O&M staffing/shifts, and exact split of power, chemicals, spares and major repair costs between Employer and Contractor during Section II and DLP.
Special Conditions put normal O&M power on Employer but construction/trial power on bidder; consumables generally on Contractor unless priced.
Need clarity on whether paid maintenance is a separate priced BOQ component or deemed included.
Land, ROW, river permissions and SIPCOT interface risks
Please confirm status of land acquisition/ROW for the ~27 km pumping main, river-bed infiltration well permissions, road/rail/utility crossings, and SIPCOT boundary interface responsibilities, and whether delays for permissions entitle EOT without LD.
Site data disclaimers place investigation risk on bidder; foreclosure clause pays only for executed works with no profit claim.
Risks
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
6
Tight construction programme with milestone LD
12-month construction with aggressive cumulative milestones (30/50/70/100%) plus 3-month trial run; LD at 0.05% of unfinished work per week, capped at 10% of contract value, without prejudice to time-bar termination.
LD imposed via multi-step show-cause (15+7+3 days) and can apply automatically if no reply.
Activity Chart must be approved; Employer may reject updates without prejudice to LD.
Defects correction: attend within 3 days of notice or Employer remedies at contractor risk/cost.
High security stack and long post-completion exposures
EMD Rs.9.65 Lakh; performance security 2–5%; staged retention/5% DLP BG for 2 years; optional/forced water-tightness retention or indemnity; additional 5% BG on water-retaining structures for 3 more years after DLP.
Performance security forfeitable on termination for specification/terms failure.
Bid security forfeitable for validity withdrawal or failure to sign/perform security.
Minus bids sharply increase performance security percentage (up to 5%).
Payment cash-flow and withholding risks
Pipe payments heavily back-ended and consignment-linked; 40% bill withholding risk on water-retaining structures unless indemnity given; Employer payment target 6 weeks after bill submission — working capital intensive on ~27 km pipeline.
Subsequent pipe consignments payable only if prior consignments meet laying/testing thresholds (50% of immediately preceding and 100% of earlier).
Interest-bearing mobilisation advance recoverable quickly (20% of certificates after 30% threshold).
Final bill only after maintenance completion.
One-sided termination / foreclosure and broad Employer rights
Employer may terminate for any reason regarded as breach and recover extra completion cost; foreclosure allows stopping whole/part works with no claim for loss of profit—only eligible amount for executed unusable works as certified by Engineer.
Employer may accept/reject any bid and annul process without liability or assigning reasons.
Not bound to accept lowest bid.
Site / utility / power risk allocation
Bidder bears site investigation risk (soil/levels not guaranteed); must handle notices to telephone/railway/electric utilities; construction and trial-run EB power on contractor; multiple river/road crossings likely on long OPVC main.
Penalty up to 10% of defective work value plus rectification at contractor cost.
Price adjustment stops after agreement period except listed force-majeure/land acquisition/design-change EOT cases.
Qualification documentation severity
Pass/fail hinges on Notary-attested EE-rank certificates with highly specific content; private-work proofs are onerous; outside-State certificates may be re-verified; missing credentials can make bid non-responsive with limited clarification time.
If clarification not provided within stipulated time, bid declared non-responsive.
Internal date/EMD contradictions create administrative rejection risk even for compliant online filings.
Contacts
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
3
Tender invitee / Employer
The Chief Engineer, TWAD Board, Thanjavur — tender invitee and Employer for this bid.
Department context: CE-ER/Thanjavur (from tender framing); work under RWS Division, Ariyalur for performance security pledge.
Office address for pre-bid / correspondence
Office of the Chief Engineer, TWAD Board, Integrated Office Complex, First Floor, No.243/2, Thanjavur–Trichy Main Road, Pillayarpatty, Thanjavur – 613 403.
Pre-bid meeting venue is this office on 09.07.2026 at 11:00 A.M.
Letter of Application is addressed to the Chief Engineer at the same Integrated Office Complex address.
No phone or email contact is printed in the extracted bid pages reviewed; portal for e-tendering is https://tntenders.gov.in.
Division address linked to securities / site administration
Performance security instruments and water-tightness indemnity are in favour of / involve the Executive Engineer, TWAD Board, RWS Division, Ariyalur.
Engineer / Engineer-in-charge means the Executive Engineer or Engineer appointed by Employer.
Contractor bills are submitted to the Executive Engineer or subordinate as directed.
No separate physical bid-submission address is prescribed because bids are e-submitted; any residual original-EMD question should be clarified with the CE office.