Tender online / publication availability
The tender is available online from 08.07.2026 at 11.00 A.M.; this is the latest document-stated online publication/availability date after Corrigendum 1.
Loading…
RD road to Tandiguda_Road_Jungle clearance, Retaining Wall Left Side 100m _0.200 to 0.300
CE RW I · Mohana, Odisha2026_CERWI_134739_1
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
8 Jul 2026
17 Jul 2026
₹6.8 L
₹6,800
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
The tender is available online from 08.07.2026 at 11.00 A.M.; this is the latest document-stated online publication/availability date after Corrigendum 1.
14.07.2026 up to 5.00 P.M.
17.07.2026 up to 5.00 P.M., being the end of the amended online bidding window.
18.07.2026 at 11.00 A.M. (Price Bid).
90 days from the date of opening of tenders; it may be extended by mutual agreement. The NIT also says 90 days from the last date of receipt, creating a one-day trigger conflict recorded under contradictions.
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
The NIT states Rs.6.78 lakh; the detailed BOQ totals INR 677,210.83.
Rs.4,000, payable online.
Rs.6,800 is stated for this work. The NIT and Clause 1.4 call for online payment, but the same DTCN also lists pledged NSC/POTD/POSB/KVP/scheduled-bank deposit receipt and its checklist asks for a Bid Security Declaration. No separate EMD validity or claim period is stated; obtain portal clarification before submission.
Within 10 days of acceptance, the successful bidder must add initial security so EMD plus initial security equals 2% of the accepted work value and sign the agreement. For low bids, incremental APS applies and must be furnished within seven days of emailed LoA as a pledged term deposit receipt or bank guarantee from a nationalized/scheduled bank, counter-guaranteed by its Bhubaneswar branch.
Bills are submitted monthly; admissible claims are to be adjusted, if possible, within ten days. Interim payments are advances against final payment, and the final bill is to be prepared within one month of the fixed completion date. Security is refundable only 12 calendar months after completion, after final-bill payment and defect rectification.
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
This work is open to D and C Class contractors. Odisha contractors must hold valid registration with CDMS 8-digit unique code; equivalent-class contractors registered with other State Governments, MES, Railways or CPWD may bid but must register under Odisha State PWD before agreement/award.
Valid PAN and GSTIN certificates are mandatory. The bidder must submit CA-certified Annual Turnover information in Schedule-C, financial-year-wise for civil engineering works with updated values and the CA's UDIN. No minimum turnover, net-worth threshold or quantified completed-work experience threshold is stated in the tender documents.
The bidder must declare by affidavit that it has not abandoned any similar work and that no contract was rescinded during the last five years.
A bidder cannot bid where the bidder's or spouse's near relative is posted in the responsible R.W. Circle/Division in the specified engineering/accounting grades. Any relative who is Assistant Engineer or above in State PWD, or Assistant Secretary or above in Works Department, must be disclosed in a covering letter; otherwise a no-relationship certificate/affidavit is required.
A retired gazetted engineer or gazetted officer formerly employed in engineering/administrative duties in a State Engineering Department cannot contract for two years after retirement without Government permission.
Joint ventures, consortium agreements and MOUs are not allowed to participate.
Breach of bid obligations can cause cancellation of empanelment and suspension/prohibition/debarment/blacklisting for at least 180 days. Canvassing causes rejection and exclusion from other works in the organization. If selected L1 fails to execute the agreement, the code amendment provides three-year debarment and blacklisting action.
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
Special repair to the RD road to Tandiguda for 2026-27, under R.W. Sub-Division, R. Udayagiri.
The percentage BOQ covers 8,040 sqm clearing/grubbing; 53.54 cum hard-soil foundation excavation; 15.6 cum river-sand filling; 14.13 cum PCC 1:3:6; 312 sqm M-40, 80 mm interlocking pavers; 4 km stones; 12 two-hundred-metre stones; 20 direction/place-identification signboards; 51 RCC guard posts; maintenance of 10 Hume-pipe culverts; and 603 cum embankment.
Two calendar months from the written order to commence work.
Work must follow IRC and ISI codes, MOST/MoSRT&H road-and-bridge specifications, Odisha detailed standard specifications, and any other standard prescribed by the stated Rural Works authorities; item-specific BOQ standards include IS 15658:2006, IRC:SP:63-2004, IRC-67 and MoRD Clauses 1701, 1703 and 1908.
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
Submit a percentage-rate bid online through www.tendersodisha.gov.in; the tender is described as single cover.
The bidder must have portal enrolment using its own Digital Signature Certificate. Do not upload the DTCN; accept its conditions online. A bidder disagreeing with the DTCN cannot participate.
The successful bidder must produce originals of uploaded documents when called, before agreement. Separately, an SC/ST bidder claiming 50% EMD exemption/price preference must deliver attested caste certificate and application to the Superintending Engineer, R.W. Division, Mohana by the amended opening time, 18.07.2026 at 11.00 A.M.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
Corrigendum 1 extends the online bidding window from 24.06.2026–03.07.2026 to 08.07.2026–17.07.2026, moves clarification from 01.07.2026 to 14.07.2026, and moves price-bid opening from 04.07.2026 to 18.07.2026; all times remain 11.00 A.M. for start/opening and 5.00 P.M. for deadlines. Bidder action: use only the amended dates.
Online availability/submission: 08.07.2026 11.00 A.M. to 17.07.2026 5.00 P.M.; clarification: 14.07.2026 5.00 P.M.; price-bid opening: 18.07.2026 11.00 A.M. All other tender terms remain unchanged.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
The original NIT closes bidding on 03.07.2026, clarification on 01.07.2026 and opens on 04.07.2026; Corrigendum 1 changes these to 17.07.2026, 14.07.2026 and 18.07.2026 respectively. Corrigendum 1 prevails.
The NIT says 90 days from the last date of receipt, while DTCN Clause 2.17 says 90 days from tender opening. Use the more specific Clause 2.17 trigger—90 days from opening—but seek confirmation because this changes expiry by one day.
For the same Rs.6,800 security, the NIT/DTCN require online payment, Clause 1.4 also names pledged savings/deposit instruments, and the checklist asks for a Bid Security Declaration. No amendment resolves whether the declaration replaces or supplements EMD. The tender-specific online-payment direction is the safer operational reading, but portal clarification is essential.
The tender-specific NIT/DTCN notice says the amount and bidder's rate exclude 18% GST and applicable GST is paid over the bill, but generic DTCN clauses say rates cover GST and the contractor bears GST. The repeated tender-specific Clause 13 should prevail for pricing, subject to written confirmation.
A 2026 office memorandum abolishes the 14.99% negative-bid cap and adopts incremental APS, but the DTCN also reproduces an older Annexure-III clause rejecting bids below 15%. The later 03.01.2026 memorandum and the tender-specific APS clauses prevail; bidders may quote lower subject to APS and abnormal-low-bid scrutiny.
Clause 1.5 says EMD plus initial security equals 2% of accepted value, Clause 1.4 refers to 2% or 3% as applicable, and payment Clause 6 refers to a 10% security balance with deductions up to 5%. The initial deposit should follow the specific 2% post-award clause, but total retention/security needs written confirmation.
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Please confirm whether the bidder must pay Rs.6,800 EMD online, upload only a Bid Security Declaration, or do both, and confirm whether any pledged physical instrument is accepted. This is pass/fail and the DTCN gives all three directions.
Please confirm that percentage rates must exclude GST and that applicable GST will be paid over certified bills, notwithstanding Clauses 1.10 and 30 saying rates include/contractor bears GST.
Please state the exact initial security, total performance/security deposit and bill-retention percentages for this D/C-class work, because the DTCN separately states 2%, 2% or 3%, and a 10% balance with deductions up to 5%.
Please confirm whether the 90-day validity runs from amended bid submission (17.07.2026) or opening (18.07.2026), because the NIT and Clause 2.17 use different triggers.
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
Completion is only two calendar months from the commencement order. Delay compensation is 0.5% of estimated cost per day for uncommenced/unfinished work; missed progress milestones attract one-third percent per day, with total compensation capped at 10%. Rescission can additionally recover 20% of leftover-work value as penalty.
The department disclaims BOQ quantity completeness and may add, omit or reduce items to any extent without invalidating rates or paying extra compensation. Dewatering, benchmarks, traffic arrangements, temporary cross-drainage, shoulders, maintenance and debris clearance are treated as incidental with no extra claim.
Bid submission deems the bidder to have inspected the site and priced availability of materials, labour, leads/lifts and all difficulties; no extra payment follows a later misjudgment. The contractor must arrange materials, plant, machinery, clean water and night lighting at its own cost.
Interim certificates are only advances, security deductions may reach 5% to make up a stated 10% balance, and security remains locked until 12 months after completion, final-bill payment and defect rectification. Completion is not certified until defects are rectified to the Executive Engineer's satisfaction.
A low bid can require incremental APS and detailed price justification. Failure to demonstrate capability permits rejection; failure to furnish APS within seven days of LoA cancels the bid and initiates blacklisting.
Assignment or subletting requires written Executive Engineer approval; breach may cause rescission and forfeiture of security deposit.
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
Executive Engineer, Rural Works Division, Mohana, acting on behalf of the Governor of Odisha. Email: [email protected]. No named individual, street address or phone number is stated in the supplied tender documents.