Tender download start
Tender document download starts on 28.07.2026 at 1500 HRS.
- NIT is dated 28.07.2026.
- No corrigendum in the tender pack amends this date.
Loading…
Tender for Construction of Vertical Extension on the Existing Library Buildingat Palamuru University Campus Bandameediapally Mahabubnagarand Construction of Boys Hostel and Girls Hostel Buildings at PG Center Wanaparthy in Telangana on EPC basis.
Engineering Projects (India) Ltd. · Mahabubnagar, Wanaparthy, Telangana2026_EPI_285731_1
Written by TenderKart AI from the documents published when it was generated. Check the tender for later corrigenda before you bid.
28 Jul 2026
7 Aug 2026
₹20.9 Cr
₹30.9 L
All important dates as they stand after corrigenda: publication, pre-bid/clarification deadline, bid submission deadline, bid opening, and bid validity period.
Tender document download starts on 28.07.2026 at 1500 HRS.
No last date for pre-bid queries is filled in the tender schedule.
Online tender submission closes on 07.08.2026 at 1500 HRS.
Online technical bid opening is on 10.08.2026 at 1500 HRS.
Physical/offline EMD (if not paid online) is due by 10.08.2026 at 1500 HRS.
Bid remains open for acceptance for 150 days from the last date of tender submission.
Completion period is 15 months including design period, reckoned from the 10th day of LOA/Letter of Acceptance.
Tender value or estimated cost, EMD/bid security (amount, acceptable forms, validity), tender document fees, performance security, and key payment terms.
Estimated cost put to tender is Rs. 20,89,40,980/- excluding GST.
Non-refundable tender fee is Rs. 11,800/- inclusive of GST @18%, payable online to EPI.
EMD is Rs. 30,89,500/-; acceptable as online payment, DD/Bankers Cheque in favour of Engineering Projects (India) Limited, Bank Guarantee, or Insurance Surety Bond.
Security Deposit cum Performance Guarantee is 2.50% of Contract Value, to be submitted within 21 days of LOA/LOI.
If L1 quotes below estimate, Additional Performance Security is payable on a stepped scale and must be furnished within 60 days of LOI (or SDPBG timeline), else LOI withdrawn and EMD forfeited.
Retention Money is 7.5% of each RA bill gross value: 5% refunded with final bill after successful completion; 2.5% after defect liability period.
No mobilization or secured advance; prices are firm with no escalation; contractor payment is back-to-back after EPI receives payment from Palamuru University.
Every pass/fail eligibility and qualification requirement: experience and past performance, turnover/net worth, registrations and certifications, consortium/JV rules, and debarment or blacklisting conditions.
In last 7 years ending last day of month previous to tender invitation: 3 similar works ≥40% ECPT, OR 2 ≥50%, OR 1 ≥80%.
Average annual turnover on works in last 3 FYs ending 31.03.2025 ≥50% of ECPT; no losses in more than two consecutive years in last five FYs; and either Banker’s Certificate =40% ECPT (not older than 3 months before bid due date) OR Net Worth ≥10% ECPT as on 31.03.2025.
Joint Venture / Consortium is not eligible to bid.
Bidder must not be currently ineligible/suspended/blacklisted/banned/debarred by EPIL or any Central/State Govt Department/PSU at bid submission; border-sharing country procurement restrictions apply with Annexure-VIII undertaking.
All bidders must declare local content; Class-I (≥50%) gets purchase preference within L1+20% margin if L1 is not Class-I; Class-II (≥20%) gets no purchase preference.
Integrity Pact on Rs.100 stamp paper is mandatory (tender ≥ Rs.10 Cr); bids without signed IP are liable to rejection. Site visit self-declaration with EPIL site-visit certificate (Annexure-IX) is required with the bid.
Valid PF & ESI registration, PAN and GST registration are required with the bid; Class-III digital signature is required to submit on CPP portal.
What is being procured: the work, supplies or services, deliverables and quantities, locations, phases, completion or delivery timelines, applicable standards, and notable exclusions.
EPC package for (i) vertical extension of existing Library Building (plinth area 21,980 sqft) at Palamuru University Campus, Bandameediapally, Mahabubnagar Dist, and (ii) Boys Hostel (G+2, 16,500 sqft, 150 students) and Girls Hostel (G+2, 21,000 sqft, 200 students) at PG Center, Wanaparthy Dist, Telangana.
Scope covers civil & structural works, architectural consultancy, all MEP services, materials, tools, labour and related building services as per bid documents, drawings and Engineer-in-Charge directions.
Overall completion 15 months including design; financial milestone targets: Month 1 – 10%; Months 2–5 – 30%; Months 6–12 – 50%; Months 13–15 – 10%.
Works to follow tender technical specifications, APSS/TSSOR 2025-26, AP state technical specifications/building data, BIS, and directions of Engineer-in-Charge; price bid is single lump-sum EPC quote against estimated Rs.20,89,40,980.
The complete checklist of documents to submit — mandatory vs conditional, with any prescribed formats, proformas or annexures — plus how to submit: portal and mode, envelope/cover structure, digital signature requirements, signing and attestation rules, and physical originals with their deadline.
Only online submission on CPP eProcurement portal is accepted; Class-III DSC required.
Physical original EMD (DD/BG/Insurance Surety Bond) must reach EPI inviting authority by 10.08.2026 1500 HRS; other originals on demand.
Every corrigendum/addendum in order — what changed (original vs amended value), its impact, and the action for the bidder — ending with the values that finally apply.
The downloaded tender documents contain no corrigendum or addendum file; all dates, amounts and conditions stand as originally published in the NIT dated 28.07.2026.
Genuine conflicts within and across the documents (original vs corrigenda, clause vs annexure, tender document vs BOQ): both sides with citations, and which value prevails.
Clause 5 states EMD valid for minimum 180 days but immediately glosses it as “(one hundred fifty days)”; bid validity elsewhere is 150 days.
Tender schedule fixes offline EMD by 10.08.2026 1500 HRS, while Cl.12 item 2 says physical original EMD within last date of bid submission (07.08.2026) or extended time.
Memorandum reckons start/completion from 10th day of LOA, while ACC Cl.4 reckons actual start from 10th day of signing of agreement/work order.
Tender drawings are labelled for hostel blocks for Law/Engineering buildings, while NIT scope is Library vertical extension at Mahabubnagar and Boys/Girls hostels at PG Center Wanaparthy.
NIT mandates online-only bid submission, but Annexure-I still says Letter of Undertaking is “TO BE ENCLOSED IN ENVELOPE-1 ALONG WITH EMD”.
Only critical, tender-specific pre-bid queries that could materially change bid/no-bid, pricing, eligibility or contractual risk. Skip generic or obvious questions the documents already answer clearly.
Schedule leaves Last Date of Submission of Pre-bid Queries blank; ask EPI to notify the cut-off and any meeting date/mode.
Ask EPI to confirm whether EMD instrument must be valid 180 days or 150 days from bid due date.
Seek written confirmation that physical EMD may arrive by 10.08.2026 1500 HRS (not 07.08.2026), delivery address at Contracts Division CO, and exact SFMS beneficiary bank identifiers.
Request issue of project-specific drawings/area statements matching the NIT scope, because Volume II drawings appear labelled for Law/Engineering hostel blocks.
Ask whether any maximum payment timeline applies if Palamuru University delays paying EPI, and whether milestone RA billing percentages are defined beyond financial targets in ACC Cl.4.
Clarify whether the 15-month completion clock and LD run from 10th day of LOA or from 10th day of agreement signing/work order.
Commercial, legal and execution risks a bidder should weigh: liquidated damages and penalties, unusual or one-sided clauses, tight timelines, and payment or security risks.
No mobilization/secured advance; RA payments only after EPI receives funds from Palamuru University; contractor gets no interest/compensation for client-side payment delay.
Compensation for delay is 0.5% of awarded contract value per week, capped at 10% of tendered value (excl. GST); intermediate financial milestones can trigger automatic withholding.
Rates firm for entire/extended period with no escalation; 7.5% retention plus 2.5% PBG and possible additional below-estimate security lock substantial cash.
Work includes vertical extension on an existing library plus new hostels at a second campus; tender drawings appear mislabelled, increasing design, interface and rework risk on EPC lump-sum.
False credentials, Integrity Pact breach, cartelisation or unsatisfactory progress on existing EPI works can lead to rejection, EMD forfeiture and debarment up to three years; LOA collapses if PBG/additional APS not timely furnished.
Mandatory key staff recoveries if not deployed (PM Rs.50,000/PM; Engineers Rs.30,000/PM; Supervisor Rs.20,000/PM); CAR/EAR, WC and 5% third-party insurance required, with PBG forfeiture risk if policies not placed.
The inviting authority and relevant contacts: office, person, designation, address, phone and email — and which address receives physical submissions, if any.
Group General Manager, Contracts Division (Corporate Office), Engineering Projects (India) Ltd., receives tender-related correspondence by post/in person.
Sri R Narayan Naik, AGM (Tech), EPI Palamuru University Site Office is the site-visit and site-query contact.
IEMs for this tender are Shri Ganganna Satish and Shri Rajendra Kalla.
Work is invited by EPI on behalf of owner Palamuru University, Mahabubnagar.