Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Clarification
Clarification# 105: 5. Software, Server, and Licensing Requirements- Please confirm whether the system shall be hosted on a local server or cloud platform and whether all software licenses, STS key management, database, and system integration costs must be included in the bid price.- Please also clarify whether any recurring annual license, subscription, or per-meter fees are permitted.Response: The bidder shall include in its proposal all necessary software, licenses, STS key management systems, databases, system integration, and any other associated components and services required to ensure the complete and proper operation of the Smart Metering System.The proposed solution shall be fully functional and operational, with all associated costs clearly identified and included in the bid price. ion.Clarification# 106: 6. Integration with the Power Plant Control SystemPlease confirm whether the Smart Metering System is required to interface with the plant SCADA/EMS or other control systems. If so, kindly specify the required communication protocols, interfaces, and data exchange requirements.Response: We confirm that the Smart Metering System must interface with the plant SCADA/EMSClarification# 107: 7. Installation and Commissioning Scope- Regarding the smart metering system, there is a communication option superior to LoRa or PLC which is LoRaWAN. Would you like us to submit a proposal based on the options outlined in the tender documents, or would you prefer the better alternative?- Please clarify whether BOQ Item 12 includes the physical installation of all 2,200 meters at customer premises, communication infrastructure, system commissioning, testing, and end-user training, or whether the scope is limited to supply and configuration.Response: LoRa refers to the physical Radio Frequency (RF) modulation technology; therefore, LoRaWAN is not considered an alternative communication technology but rather a network protocol operating over the LoRa physical layer.Accordingly, the proposed LoRaWAN solution may be considered under the RF communication option specified in the tender documents. Bidders shall ensure full compliance with the applicable technical requirements and the provisions of the Electrical BoQ, particularly Items 12.1.1.1, 12.1.1.2, and 12.1.1.3, which specify PLC/RF communication options.
Clarification
Clarification# 96: the manufacturer wants to focus on the BESS and PCS skid. the manufacturer will provide his standard high-capacity 5MWh DC block and PCS skid are designed for medium-voltage (MV) coupling (e.g., 11kV or 33kV) to reduce current levels and maximize efficiency.Would the Husswain accept a medium-voltage coupling architecture for the BESS (e.g., PCS step-up to 11kV directly to the RMU) instead of the mandated 800V LV bus? If acceptable, the integration with the PV inverters (which output 800V) would require the PV side to step up independently.Response: The required BESS and PCS specifications shall be maintained as stated in the tender documents, comprising a battery energy storage system with a nominal capacity of 3.8 MWh and a PCS rated at 1.9 MW. All bidders are required to comply with these specified capacity requirements and the system configuration indicated in the tender documents. Any proposed alternative coupling architecture, including medium-voltage coupling, shall not be considered a basis for deviating from the specified requirements.Clarification# 97: If the manufacturer intends to offer a standard 5MWh container BESS, we want to know if the 3.8 MWh EOL requirement applies to the DC block before PCS/Transformer losses, or must it be measured at the AC side after the PCS step-up? We need to confirm the measurement boundary to ensure our 5MWh DC block guarantees the 3.8 MWh AC output at Year 10. ?Response: The BESS is 3.8 MWh nominal capacity as revised in all related documents mentioned below:"REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications)."In addition, the BESS system includes (battery storage 3.8 MWh nominal capacity and PCS 1.9 MW) and bidders are required to meet this requirement.Clarification# 98: The manufacturer noticed that in the existing system electrical design is using 10 energy storage cabinets with 190KW/373KWh of each for the BESS and PCS part. Theoretically, the initial storage capacity is only 1.9MW/3.73MWh, which doesn't meet the requirement of at least 3.8MWh EOL capacity.However, the manufacturer's solution uses a 5MWh battery container with 5MW PCS, which can meet the relevant requirements even considering the EOL after 10 years. Can you accept it?Response: 1. BESS is 3.8 MWh nominal capacity as revised in all related documents mentioned below:"REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications)."2. The BESS system includes (battery storage 3.8 MWh and PCS 1.9 MW) and bidders are required to meet this requirement.Clarification# 99: Q 1- Item 1.2.1 (Civil BoQ): You mentioned this "The steel used will be galvanized with a minimum galvanized thickness as per iso coating standard for M4 corrosion category and medium life span using polyethylene/ zinc rich or equivalent materials." The question is can we use polyethylene-coated steel profiles for bridge and column structures?Response: No. Polyethylene-coated steel profiles are not acceptable for bridge and column structures. The steel members shall comply with the specified galvanization requirements and applicable ISO coating standards for the M4 corrosion category and medium durability.Clarification# 100: Q 2- What is the system nameplate nominal capacity as the mentioned capacity at end of life?Response: BESS is 3.8 MWh nominal capacity as revised in all related documents mentioned below:"REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications)."Clarification# 101: Q 3- Item 12 (Ele. BoQ): Smart Metering System.To ensure full technical compliance and accurate pricing for BOQ Item 12 Smart Metering System, we kindly request clarification on the following points:1. Customer Interface Unit (CIU)The BOQ specifies 2,100 single-phase meters and 100 three-phase meters, while the CIU quantity is indicated as "1 System."Please clarify whether a separate CIU is required for each of the 2,200 meters or whether the stated quantity refers to one centralized system.Response: Dedicated 1-to-1 Deployment (No Centralized Architecture):The CIU will be a separate physical unit for each individual customer meter, covering all 2,200 meters (2,100 single-phase and 100 three-phase).No centralized or shared CIU architecture will be used. Because the meters utilize a split-meter configuration (with the measuring unit installed externally on poles or boundary enclosures), every consumer premise requires its own dedicated indoor CIU keypad for token entry and monitoring. The BoQ line item listing "12.1.1.3" represents the overall metering package header and requires pricing for 2,200 individual CIU unitsClarification# 102: 2. Scope of the Complete Smart Metering SystemPlease confirm whether the contractor shall supply a complete AMI/prepayment solution, including HES, MDMS, STS Vending System, key management, servers, software licenses, communication gateways, and all necessary accessories, or whether any of these components will be provided by the Employer.Response: The Contractor shall supply and deliver all components, equipment, software, licenses, and accessories explicitly specified in the BoQ. This includes the complete AMI/prepayment system components listed therein, such as HES, MDMS, STS Vending System, key management system, servers, software licenses, communication gateways, and all associated accessories, as applicable. Any items specified in the BoQ are within the Contractor's scope of supply and shall be delivered in accordance with the tender requirements.Clarification# 103: 3. Communication TechnologyThe specifications mention GPRS/4G, NB-IoT, and RF-Mesh communication options.Please confirm whether a specific communication technology is mandatory or whether any of these technologies is acceptable, provided that the complete system operates reliably and meets the technical requirements.Response: We confirm that the specific communication technology is mandatory.Clarification# 104: 4. Meter ConfigurationPlease clarify the required rated voltage, maximum current (80A or 100A), and connection type for both single-phase and three-phase meters, particularly whether the three-phase meters shall be direct-connected or CT-operated.Response: The rated voltage of both single-phase and three-phase meters shall be compatible with the applicable system voltage. The maximum current rating shall be proposed by the bidder based on the selected meter model and the manufacturer's specifications, ensuring suitability for the intended application.Regarding three-phase meters, either direct-connected or CT-operated configurations may be proposed, subject to the manufacturer's recommendations and the technical requirements of the installation.
Clarification
Clarification# 87: Could you please extend the tender deadlineResponse: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.Clarification# 88: We kindly request an extension of the tender closing date by further ten days, as some of the manufacturers are still in the process of reviewing the required technical specifications and prepare their offersResponse: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.Clarification# 89: Regarding Point 2: String Inverters with Mounting Support and Concrete Foundation, kindly clarify whether the required inverters should be conventional on-grid string inverters or hybrid inverters.Section B) Hybrid System Interoperability mentions hybrid compatibility, which has caused some confusion.Should we propose on-grid string inverters or hybrid inverters ?Response: Conventional on-grid string inverters are required. Hybrid inverters are not required under this item. The reference to hybrid compatibility in SectionB) concerns system interoperability and does not change the specified inverter type. Bidders are required to meet this requirement.Clarification# 90: Q1: Regarding the item 5.2 (0.8 kV LV Switchgear) the details and capacity of the circuit breakers are NOT MATCH with the [drawing no E1-08 - page 11 - Annex 5B in switchgear box], shall the contractor put price consideration according to the drawing or BoQ specifications.IN ADDITION, the 0.8kV side of the Auxiliary transformer 25kVA shown in the drawing is protected by an MCCB rated by 6300A which is not logic. Please confirm the MCCB capacity.Response: The technical specifications required for each type of circuit breaker and the requirements necessary to ensure proper system protection is reflected in the Electrical BoQ Item No. 5.2 "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities" which has been revised to match Single Line Diagram (SLD) drawing E1-08 and as follows:a. Incoming Circuit Breakers: (15 x 400 A, 4-pole MCCBs) and (10 x 250 A, 4-pole MCCBs)b. Outgoing Circuit Breakers: (1 x 6300 A ACB) and (1 x 63 A MCCB)For Auxiliary transformers 25kVA is protected by 63 A MCCB capacity as mentioned above.Clarification# 91: Q2: There are differences in the specifications in Annex 2 and BoQ. For example, the DC Bus voltage in batteries [Annex 2 – Title 4.2 – state DC Bus Operating Range 1040V to 1512V] but in the BoQ [item 3.5 – state Rated DC voltage: ≥ 1500VDC]. Please confirm.Response: The DC bus operating voltage range specified in Annex 2, Section 4.2 (1,040–1,512 VDC) represents the battery system's operational voltage range, while the voltage specified in BoQ Item 3.5 (≥1,500 VDC) refers to the required rated DC voltage of the battery system. Bidders shall ensure that the proposed system satisfies both requirements.Clarification# 92: Q3: Regarding the inverters Item 2.1, the required limit of the THD < 1% at rated power, whereas in the Annex 2 [Title 3.5 – 𝑇𝐻Di < 3% at rated power]. Please confirm.Response: THD above 1% is not accepted.Clarification# 93: Q4: Regarding the Optical Ground Wire (OPGW) item 6.1, it is not stated to install electrical poles, and they did not exist now. How to install it?Response: The overhead transmission line installation activities are excluded from the contractor’s scope of work and shall be carried out by the relevant authorities in Al-Mahrah (PEC).The contractor’s responsibilities are strictly limited to the supply of the complete Optical Ground Wire (OPGW) fiber-optic conductor, supervision of its installation by PEC, and subsequent testing and commissioning.Accordingly, the scope of work has been revised to clearly distinguish the contractor’s obligations from PEC’s installation responsibilities, ensuring a clear definition of the contractual division of responsibilities and avoiding any potential ambiguity during implementation. "REV 1 - Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station"Clarification# 94: Q5: Regarding Smart Prepayment Meter item 12.1.1, it is not mentioned to install this item, shall the contractor supply them only? IN ADDITION, is calibration of the Smart Prepayment Meter enough in the manufacture?Response: The Contractor's scope includes the supply and installation of the part smart prepayment meters, as well as providing the necessary capacity-building and training for the relevant authorities to ensure proper installation for the remaining meters, operation and management of the meters.Furthermore, all supplied smart meters shall be accompanied by valid manufacturer-issued calibration certificates. Calibration at the manufacturing stage is acceptable, provided that the corresponding certificates are submitted with the meters.Clarification# 95: Regarding the subject, could we please have answers to the queries below?1. The quantity for the Base-Course in the BOQ item number 1.1.2 is showing 700 cubic meters, and I believe the quantity is more than that.2. The electrical SOW and BOQ, item number 6.1, state that 3 km of 11 kV OHL should be supplied and installed, but there is no drawing showing the line's route or specification for the poles and foundations. This is critical work with a high cost, and the missing information will affect the tender price.3. Regarding the implementation period, five months is a short duration given the project's location and the unstable situation in the Middle East. These issues are likely to affect the project deadline, so we ask that you consider allowing more time.4. Could you extend the clarification period by one week and move the submission date for this RFQ from 22 November 2026 to 06 December 2026?Response: 1. The quantities indicated in the BoQ are based on the current site conditions and the assessed requirements at the time of preparation. Should additional quantities be required during implementation due to actual site conditions, such variations shall be assessed, verified, and addressed in accordance with the applicable provisions and procedures of the Contract.2. The required OPGW cable length is 2 km for the overhead transmission line to be implemented by PEC to connect the solar power plant to the existing generation station. The OPGW cable shall have 24 fiber-optic cores, in accordance with the revised "Rev 1- Annex 4 – Husswain Mini-Grid Solar Power Station Bill of Quantities", Item No. 6.1.3. Please note that the work plan has been amended from 5 months to 8 months. The document REV 1 - RFQ-2026-65288- Solicitation, Sections II, III, IV, V has been amended to reflect this accordingly.4. Please be advised that the clarification deadline has been extended to 17-November-2026 @ 12:00 AM.
Clarification
Clarification# 76: With reference to Annex 2 – Electrical Technical Specifications, Section 7.7 (Optical Ground Wire (OPGW) & Fiber Optic Infrastructure), we note that the tender documents do not specify the required Overall Diameter or Rated Tensile Strength (RTS) of the OPGW cable.In this regard, we kindly request UNOPS to clarify the following:Overall Diameter: Kindly confirm the required overall diameter of the OPGW cable.Rated Tensile Strength (RTS): Kindly confirm the required minimum RTS of the OPGW cable.Response: The required OPGW cable shall have 24 fibre-optic cores as mention in tender document (BoQ, Electrical Specifications). The overall diameter and Rated Tensile Strength (RTS) shall be determined by the manufacturer based on the proposed cable design, ensuring compliance with the applicable technical standards and project requirements.Accordingly, bidders shall propose an OPGW cable with 24 fibre-optic cores for 11kV transmission line and clearly indicate its overall diameter and RTS in their technical submissions.Clarification# 77: 1. Extension of the Clarification PeriodExtend the clarification period by at least 10 calendar days, allowing bidders and manufacturers sufficient time to assess the requirements and submit additional technical questions.Response: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.Clarification# 78: 2. Extension of the Tender Submission DeadlineExtend the current deadline of 22 November 2026 by at least 21 calendar days, to 13 December 2026, allowing bidders to incorporate UNOPS clarifications and finalize their proposals.Response: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.Clarification# 79: 3. Extension of the Project Implementation Period from 5 to 8 MonthsWe request that the implementation period be extended to 8 months, consistent with the timeframe referenced in the project's Environmental and Social Management Plan (ESMP).The current five-month period presents significant practical challenges, particularly considering:International banking delays: Wire transfers from Yemen can take approximately one week due to Central Bank review procedures. Additional sanctions-related compliance checks and enhanced due diligence by Chinese receiving banks can extend payment processing to approximately one month in some cases.Uncertain maritime shipping schedules: Ongoing instability affecting regional shipping routes has increased uncertainty in vessel availability, transit times, and delivery schedules.Equipment manufacturing and integration: Major components, particularly BESS, PCS, transformers, switchgear, and microgrid controllers, require manufacturing, factory testing, shipping, installation, and integrated commissioning.Response: Please note that the work plan has been amended from 5 months to 8 months. The document REV 1 - RFQ-2026-65288- Solicitation, Sections II, III, IV, V has been amended to reflect this accordingly.Clarification# 80: Regarding this tender, we would appreciate your clarification on the following points:Item 3.2 (Ele. BoQ): Please specify the total required quantity of container, as the text mentions both two 20HQ containers and one 40HQ container.Response: Only one container 20 HQ is required for BESS and all related documents already revised. (REv 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities, REV 1 - Annex 6 - Technical specifications for Goods and REV 1- Comparative Data Table and Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications)Clarification# 81: Item 6.1 (Ele. BoQ): Please confirm whether the supply and installation of wooden poles are included under this item in accordance with the technical specifications.Response: The overhead transmission line installation activities are excluded from the contractor’s scope of work and shall be carried out by the relevant authorities in Al-Mahrah (PEC).The contractor’s responsibilities are strictly limited to the supply of the complete Optical Ground Wire (OPGW) fiber-optic conductor, supervision of its installation by PEC, and subsequent testing and commissioning.Accordingly, the scope of work has been revised to clearly distinguish the contractor’s obligations from PEC’s installation responsibilities, ensuring a clear definition of the contractual division of responsibilities and avoiding any potential ambiguity during implementation. "REV 1 - Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station"Clarification# 82: Deadline Extension: Given the scope and technical depth of this tender, we respectfully request an extension of the submission deadline to finalize our bid accurately.Response: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.Clarification# 83: Regarding Item 3.4, could you please confirm whether the PCS output voltage must be exactly 800V, or whether we can offer a different voltage (e.g., 400V) with a suitable step-up transformer to achieve the required 800V mini-grid voltage?Response: The proposed modification will not be accepted. The specified system voltage of 800 VAC shall be maintained without any deviation. Introducing a 400 VAC PCS would require additional equipment, including an isolation/coupling transformer, which would alter the approved system configuration and introduce unnecessary complexity. Furthermore, PCS equipment compatible with the specified 800 VAC system voltage is commercially available in the market.Clarification# 84: We kindly request an additional extension of at least ten (35) days beyond the current submission deadline to allow sufficient time to complete and submit a comprehensive and competitive proposal.Response: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.Clarification# 85: Regarding the BESS system, in the technical questionnaire the configuration was mentioned as 3.8MWH battery & 1.9MWH PCS as one set, whereas on the drawings it was mentioned something else. The configuration on the drawings was described as 10 sets of batteries 380KWH connected to 190KW PCS, does this mean you are flexible with any configurationResponse: The BESS system includes (battery storage 3.8 MWh and PCS 1.9 MW) and bidders are required to meet this requirement.Clarification# 86: We kindly request an extension of the deadline for this bidResponse: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.
Clarification
Clarification# 66: Q08 [CRITICAL] Annex 2 requires grid-following PV inverters and grid-forming BESS; Annex 6 appears to require grid-f…Tender reference: Annex 2 §3.4 p.9; Annex 6 String Inverter Item 2Please confirm that the 15 solar string inverters are required to operate in GRID-FOLLOWING mode and that grid-forming, virtual inertia and black start are PCS/BESS functions, not mandatory native PV-inverter functions.Response: - The 15 solar PV string inverters are required to operate strictly in standard Grid-Following (GFL) mode (current source, P/Q control, synchronized to the grid/microgrid reference).- Advanced network-forming attributes—specifically Grid-Forming (GFM) voltage-source control, virtual/synthetic inertia, and Black Start capability—are system-level functions allocated exclusively to the Battery Energy Storage System (BESS) Power Conversion System (PCS), and are not mandatory native requirements for the PV string inverters.Clarification# 67: Q09 [CRITICAL] ESMP expressly assigns the 0.9km 11kV power line (17 poles and phase conductor) to PEC and excludes i…Tender reference: Annex 7A ESMP §2.4.1 pp.6–8; Electrical BoQ 6.1; E1-08 SLD; Annex 1Clarification requested Please issue a definitive split-of-scope matrix confirming whether the 0.9km 11kV power line, 17 wooden poles, AAAC phase conductors, insulators, poles, foundations, erection, OPGW and fibre terminations belong to PEC or the EPC Contractor.Response: The overhead transmission line installation activities are excluded from the contractor’s scope of work and shall be carried out by the relevant authorities in Al-Mahrah (PEC).The contractor’s responsibilities are strictly limited to the supply of the complete Optical Ground Wire (OPGW) fiber-optic conductor, supervision of its installation by PEC, and subsequent testing and commissioning.Accordingly, the scope of work has been revised to clearly distinguish the contractor’s obligations from PEC’s installation responsibilities, ensuring a clear definition of the contractual division of responsibilities and avoiding any potential ambiguity during implementation. "Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station"Clarification# 68: Q10 [CRITICAL] OPGW quantity 3km versus PEC line length ~0.9km; 12-core communications mentioned elsewhere versus 24…Tender reference: Electrical BoQ 6.1; Annex 2 §§5.9, 7.7; Annex 7A §2.4.1Clarification requested Please confirm final OPGW length, 24- versus 12-fibre design, route, splice/ODF termination points, existing poles/tower mechanical data and whether the 3km includes spare/slack lengths or another network segment.Response: The required OPGW cable length is 2 km for the overhead transmission line to be implemented by PEC to connect the solar power plant to the existing generation station. The OPGW cable shall have 24 fiber-optic cores, in accordance with the revised Annex 4 – Husswain Mini-Grid Solar Power Station Bill of Quantities, Item No. 6.1Clarification# 69: Q11 [CRITICAL] Quantities for 3×1C×300 and 3×1C×630 cables use linear meter units with unclear measurement per phase/…Tender reference: Electrical BoQ 8.2.2–8.2.7; E1-08 SLDClarification requested Do BoQ lengths (e.g., 3330m for 3×1C×300 and 720m for 3×1C×630) represent route length per complete 3-phase set, or total aggregate conductor length? Please provide a cable schedule with route length, number of parallel sets and cable metres per core.Response: The quantities specified in the BoQ represent the total aggregate length of the conductors, not the length of an individual conductor.Clarification# 70: Q12 [CRITICAL] Single-core AC and MV cables specify steel tape armour (STA), which could induce excessive losses/hea…Tender reference: Electrical BoQ 8.2.2–8.2.7Clarification requested Please confirm that single-core AC/MV power cables may use compliant non-magnetic armour (e.g. aluminium wire armour / equivalent) and approved screening/bonding, instead of ferromagnetic steel tape armour.Response: The specified AC cables shall be copper conductors, and the proposed alternative cable types or materials will not be accepted. Bidders shall strictly comply with the cable specifications and requirements stated in the Electrical BoQ, with no deviations permitted.Clarification# 71: Could you please let us know the technical details of the existing genset plant that is already equipped with controllers ?Response: All details already included in the drawing SLD sheet No. E1-08 in "REV 1 - Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing " and DEIF controllers currently exist as controllers.Clarification# 72: Pls clarify the following:End-of-Life (EOL) Capacity:Discrepancy: Annex 2 states a requirement of at least 70% remaining capacity at 6,000 cycles. However, the Bill of Quantities (BoQ) and Annex 6 state a requirement of 80%.Clarification needed: Which of these target percentages should we follow for our compliance and pricing?Response: Please refer to the amended document "REV 1- Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications" and 80% capacity is requiredClarification# 73: Container Size:Discrepancy: The BoQ specifies 2 × 20 ft containers, whereas Annex 2 mentions a 40 ft container.Clarification needed: Could you please confirm the required container configuration and size?Response: Only one container 20 HQ is required for BESS and all related documents already revised. (REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities, REV 1 - Annex 6 - Technical specifications for Goods and Comparative Data Table and REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications)Clarification# 74: Energy Basis (Nominal vs. EOL):Discrepancy: Annex 4 specifies 3.8 MWh nominal capacity, while Annex 2 specifies 3.8 MWh EOL (End of Life) capacity. An EOL requirement of 3.8 MWh implies that the system must maintain this capacity after 10 years of operation, which would necessitate a higher initial nominal capacity (approximately 4.5 to 5 MWh).Clarification needed: Please clarify whether the 3.8 MWh figure refers to the initial nominal capacity or the guaranteed EOL capacity.Response: The nominal energy capacity is 3.8 MWh as per the revised BoQ and drawings "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities and REV 1 - Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing No. E1-09."Clarification# 75: We are writing to formally request two weeks extension for the tender submission deadline to ensure we can deliver a highly competitive and comprehensive proposal that fully aligns with your requirementsResponse: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.
Clarification
Clarification# 60: Q02 [CRITICAL] No advance; monthly certified work; Schedule V shows plant/materials delivered to site under monthly …Tender reference: Section IV Schedule 1, PDF pp.10–11; Section V 3.4, PDF p.24; Contract GCC 10.3–10.4Clarification requested Will certified major imported equipment (PV modules, PCS/BESS, transformer, RMU) be payable upon delivery and inspection at site, prior to installation? If not, specify payment milestones or a measurable payment schedule for manufacturing and equipment delivery.Response: In accordance with the contract payment modality, payments shall be made based on the actual activities completed and duly certified by UNOPS, as specified in the Contract. Accordingly, payment eligibility shall be determined by the achievement and certification of the applicable contractual milestones. Delivery of equipment to the site, in itself, does not constitute an independent basis for payment unless expressly provided for in the Contract.Clarification# 61: Q03 [CRITICAL] Annex 2 requires 3.8 MWh usable AC energy at YEAR 10, whereas Annex 6 / BoQ state >=3.8 MWh nominal D…Tender reference: Annex 2 §4.1 & §17, PDF pp.13,52; Annex 6 Item 3.1; Electrical BoQ 3.3 / 3.15Clarification requested Please confirm the binding battery acceptance criterion is ≥3.8 MWh NOMINAL DC at beginning of life (BOL), with degradation/warranty stated separately. Please issue a formal amendment removing the contradictory 3.8 MWh usable AC at end-of-life wording.Response: BESS is 3.8 MWh nominal capacity as revised in all related documents mentioned below:REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications).Clarification# 62: Q04 [CRITICAL] PCS >=1.9 MW continuous grid forming at 800 VAC; 800 V PCS availability may be constrained.Tender reference: Annex 2 §§4.1–4.3, PDF pp.13–15; Annex 6 3.2; updated electrical SLD E1-08Clarification requested Will UNOPS accept a grid-forming PCS at 690 VAC connected to the specified 800 VAC common bus through a suitably sized isolation/coupling transformer (including losses, protection and black start), with 1.9 MW net continuous output at the point of interconnection? If yes, define approval/submittal requirements.Response: The proposed modification will not be accepted. The specified system voltage of 800 VAC shall be maintained without any deviation. Introducing a 690 VAC PCS would require additional equipment, including an isolation/coupling transformer, which would alter the approved system configuration and introduce unnecessary complexity. Furthermore, PCS equipment compatible with the specified 800 VAC system voltage is commercially available in the market.Accordingly, bidders shall comply fully with the specified 800 VAC requirement and submit a compliant grid-forming PCS solution without introducing any changes to the specified system voltage.Clarification# 63: Q05 [CRITICAL] Supplier requests clarification whether seamless switching is physical transfer within 20ms or sampli…Tender reference: Annex 2 §§4.3–4.7, pp.14–17; Electrical BoQ 3.4–3.6Clarification requested Please distinguish the required switching transitions (GFM PCS↔diesel-forming, PCS GFM↔GFL, utility↔island), and state any mandatory zero-break/≤20ms load-transfer performance, acceptable interruption duration and FAT/SAT measurement points.Response: The switching and transition methodology for the BESS requires seamless, zero-break coordination across multiple operational states. When the BESS transitions from its primary Grid-Forming (GFM) mode to a Grid-Following (GFL) and dynamic droop mode upon the startup and synchronization of the 1,250 kVA diesel generators, or when shifting between utility and islanded states, the control architecture maintains voltage stability within ±0.1 Hz steady-state precision. Critical performance metrics include an end-to-end control loop latency of ≤100 ms, a sampling rate of ≤20 ms for voltage and frequency, and an active power Fast Frequency Response (FFR) injection burst within ≤50 ms during major frequency deviations. Acceptable interruption duration is strictly zeroed for automated synchronizations, while a communication watchdog timeout exceeding 500 ms forces the BESS into an autonomous local frequency-watt droop fail-safe mode. Verification of these capabilities during Factory Acceptance Testing (SAT/FAT) requires measurement points across the 800 VDC battery racks, 800 VAC PCS terminals, 11 kV transformer and OHL distribution interfaces, and OPGW communication heartbeat loops. All above clarification already mentioned in REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications section 4.3 to 4.7Clarification# 64: Q06 [CRITICAL] Black start of 7 MVA step-up transformer and 11kV OHL is required from 1.9 MW PCS; transient/inrush a…Tender reference: Annex 2 §4.3–4.7, pp.14–17; E1-08 SLD; 7 MVA transformerClarification requested Please provide transformer inrush/magnetization and fault-level study, or confirm whether controlled pre-insertion, transformer energization device or staged energization may be incorporated; specify acceptable voltage/frequency limits and witness tests.Response: The BESS should utilize a firmware-driven controlled voltage ramp-up strategy, soft-ramping output AC voltage from 0 V to 800 V over a configurable time window to eliminate transient inrush spikes. This is executed through a strict staged energization sequence that powers the local 0.8 kV switchgear, ramps the 7 MVA transformer to 11 kV, and energizes the 11 kV OHL up to the RMU terminal before synchronization. Throughout these procedures, the system maintains strict operational limits, keeping steady-state frequency precision within ±0.1 Hz, steady-state voltage within ±2% and restricting transient dips. Compliance and performance are validated via mandatory witness tests during FAT and SAT, specifically verifying the transformer soft-ramp energization profile, end-to-end black-start isolation sequences, and response latencies against system fault levels. All above clarification already mentioned in REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications section 4.3 to 4.7Clarification# 65: Q07 [CRITICAL] Annex 2 THD ≤1% at nominal, but weak-grid section permits THDi <3%; commercial 350kW inverter measure…Tender reference: Annex 2 §3.3 p.9 & §3.5 p.10; Annex 6 String InverterClarification requested Please confirm whether the binding inverter THDi limit is <1% or <3% at specified rated conditions; clarify testing conditions (P, PF, grid impedance/SCR, background THD, load percentage) and update all relevant clauses consistently.Response: The required THD is ≤ 1%. and all testing conditions are as mentioned in REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications section 3.4 and no updates required.
Clarification
Clarification# 50: 5. There are discrepancies between the BOQ Item No. 5.2 and the Single Line Diagram (SLD) regarding the number, type, and ratings of circuit breakers for the 0.8 kV LV Switchgear, as detailed below:a. Incoming Circuit Breakers:i. Drawings: (15 x 400 A, 4-pole MCCBs) and (10 x 250 A, 4-pole MCCBs)ii. BOQ: (24 x 300 A, 4-pole ACBs)b. Outgoing Circuit Breakers:i. Drawings: (1 x 6300 A ACB) and (1 x 6300 A MCCB)ii. BOQ: (1 x 6000 A ACB) and (1 x 1000 A ACB). Please clarify.Response: Electrical BoQ Item No. 5.2 "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities" has been revised to match Single Line Diagram (SLD) drawing E1-08The correction is as follows:a. Incoming Circuit Breakers: (15 x 400 A, 4-pole MCCBs) and (10 x 250 A, 4-pole MCCBs)b. Outgoing Circuit Breakers: (1 x 6300 A ACB) and (1 x 63 A MCCB)Clarification# 51: 6. In BOQ Item No. 10.1 (Earthing System), the note states that the existing earth pits are excluded from the item, and the contractor shall connect to the existing earth pits and provide additional earth pits as required. Kindly indicate the locations of the existing earth pits and provide the relevant layout drawings, if available.Response: bidder shall strictly adhere to the quantities specified in the Material Schedule Table under Section 9.6 of the Technical Specifications (REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications), specifically electrical BoQ Items 10.1 and 11.1 in REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities, covering the earthing and lightning protection systems, respectively. The BoQ explicitly refers bidders to the Technical Specifications for these requirements; therefore, the specified quantities shall be considered mandatory.Clarification# 52: 7. In BOQ Item No. 11.1, the lightning arrester length is specified as 1 meter, whereas Detail Drawing No. D-06 (Lightning Protection System Installation) indicates a length of 50 cm. Kindly clarify the required lightning arrester length .Response: Please refer to the updated BoQ (REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities) as the requirement is ESE and not air terminal arrester.Clarification# 53: We would like to inform you that we are dealing with Saba Bank to receive our financial payments transferred by UNOPS. We would also like to confirm that the bank continues to maintain a good liquidity position and has the ability to meet its financial obligations. We have not encountered any significant difficulties in receiving our payments through the bank.Based on our direct experience and ongoing dealings with Saba Bank, we consider it a suitable banking institution that continues to provide its banking services satisfactorily.However, should you have any concerns or reservations regarding dealing with Saba Bank, or if the bank is not approved by UNOPS, we kindly request that you inform us accordingly so that we may consider the matter and take the necessary steps.Response: Bidders are required to submit any financial documents issued from certified banks and banks that are not under any kind of sanctions.Clarification# 54: Regarding Point 2 – String Inverters, kindly clarify the following:a. THD: The tender requires THD below <1% at rated load. Would inverters with THD below <3% be acceptable?b. SPD: Would DC Type II and AC Type II SPDs be acceptable as an alternative to the specified integrated Class I+II (Type 1+2) protection?Response: a. THD above 1% is not accepted.b. Any alternative arrangement may be considered acceptable, provided that it delivers equivalent protection functionality and meets the required technical performance, safety standards, and applicable specifications.This has been revised under the following documents:REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 55: Regarding Annex 6 – Technical Specifications for Goods and Comparative Data Table, kindly confirm whether we are required to submit datasheets only for the items specifically mentioned in Annex 6, rather than for all items listed in the BOQ.Response: The technical evaluation will be on the items mentioned in the technical questionnaire and the bidders should ensure attaching all required supporting documents, however, if a bidder wish to provide the catalogs/datasheets for the BoQ items there is no problem as long as they fulfill the TQ supporting documents.Clarification# 56: Regarding Point 3 – Battery Energy Storage System (BESS), kindly clarify whether the required container configuration is 20HQ or 40HQ.Would a single 40HQ container or two 20HQ containers be acceptable?Response: The requirements is only one container 20 HQ for the BESS. The documents have been revised to reflect this and are as follows:REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 57: Regarding Point 3 – BattEnergy Storage System (BESS), kindly clarify whether the required the manufacturer shall be tier 1 or any good manufacturing have the same requirements certificateResponse: It should be tier 1 and grade A as mentioned in the documents:REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 58: As per our meeting, you informed us that we are required to submit datasheets only for the items listed in the Technical Form Table, and not for all items included in the BOQ. Kindly please confirm usResponse: The technical evaluation will be on the items mentioned in the technical questionnaire and the bidders should ensure attaching all required supporting documents, however, if a bidder wish to provide the catalogs/datasheets for the BoQ items there is no problem as long as they fulfill the TQ supporting documents.Clarification# 59: Could you please let us know the technical details of the existing genset plant that is already equipped with controllers ?Response: All details are already included in the drawing SLD sheet No. E1-08 in "REV 1 - Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing " and DEIF controllers currently exist as controllers.
Clarification
Clarification# 39: Can you support us with the following questions for this tender1. THDi: Annex 2 specifies THDi below 1% in some sections but below 3% in its weak-grid stability discussion. Which limit governs acceptance? Can less than 3% THDi accepted ?Response: THD above 1% is not accepted.Clarification# 40: 2. Grid-forming: Annex 6 requires grid-forming and black-start capability from the PV inverters, whereas Annex 2 describes them as grid-following. Can UNOPS confirm that:- Grid-forming and black-start functions are provided by the BESS PCS- Grid-following PV inverters are acceptable?Response: String inverters must be Grid Following operation as slaves to the BESS Grid Forming PCS or Diesel generators.Clarification# 41: 3. Surge protection: Can the SPD arrangement in Annex 2, Section 3.8, be accepted instead of the integrated Type I+II requirement in Annex 6, provided the complete installation has coordinated surge protection?Response: Any alternative arrangement may be considered acceptable, provided that it delivers equivalent protection functionality and meets the required technical performance, safety standards, and applicable specifications.This has been revised under the following documents:REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitisREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 42: 4. AFCI: Is certified DC AFCI mandatory for the utility-scale string inverters, or can alternative string-fault detection, thermal monitoring and DC isolation protection be accepted?Response: Yes, if explicitly stipulated in the Employer's Requirements / Technical Specifications (typically referencing IEC 63027 or UL 1699B). In utility-scale installations, DC Arc-Fault Circuit Interruption (AFCI) has become a standard requirement by off-takers, lenders, and technical advisors (e.g., DNV, Fichtner) to mitigate thermal runaway and catastrophic fire risks across large DC string arrays.Clarification# 43: In item no.7 we review the SLD, the drawing said the new RMU will be 2 LBS and 1 VCB which is CCV configuration. but in the bill of quantity file, it said 2 VCB incomer and 1 VCB feeder. please comfirm which is correct.Response: The insultion voltage rating for the SC cables has been amended to read between 1.2 to 3 kV as per manufacturer recommendation of string inverters and other related equipment. Kindly refer to the revised electrical BoQ "REV 1- Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis" item No. 8.2.Clarification# 44: Regarding the BoQ an AC cable insulation rating of 1 kV. However, since the output voltage from the On-grid Inverters and PCS is 800 V AC, a 1 kV rating (U_0/U = 1/0.6 kV) does not provide an adequate safety margin for continuous operation and voltage transients.Could you please confirm the recommended insulation voltage rating for these AC cables?Response: The insulation voltage rating for the SC cables has been amended to read between 1.2 to 3 kV as per manufacturer recommendation of string inverters and other related equipment. Kindly refer to the revised electrical BoQ "REV 1- Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities" item No. 8.2.Clarification# 45: Regarding the Smart Transformer Station specifications for the 7 MW solar plant, the tender documents specify a low-voltage side of 800 V AC.However, according to standard international manufacturing practices, step-up transformers in this category are standardly rated at 1 kV on the low-voltage side to deliver an operational output of 800 V AC. To strictly meet the 800 V AC operational output under standard manufacturing block sizes, selecting a slightly larger capacity transformer station is often required.Could you please clarify if we are permitted to select the next standard available larger transformer capacity to ensure full compliance with international standards and optimal system matching?Response: There is flexibility with 30% extra as already revised in related documents:REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 46: With reference to the tender documents issued for the above-mentioned project, and following our thorough review of the Bill of Quantities (BOQ), Technical Specifications, and engineering drawings, we kindly request your clarification on the technical queries and discrepancies observed below to enable us to prepare our proposal accurately:1. In BOQ Item No. 7.2, the air conditioner capacity is specified as 1 Ton, whereas in BOQ Item No. 7.4, it is specified as 2 Tons. Kindly clarify the required capacity.Response: The required air conditioner capacity is 1 Ton as revised in electrical BoQ Item 7.4 (REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities)Clarification# 47: 2. There is a discrepancy between the Technical Specifications and the BOQ Item No.6.1 regarding the number of cores required for the OPGW – Optical Ground Wire. Kindly clarify the required number of cores?Response: The technical specifications and the BoQ both mention the required number of cores for the OPGW which is 24 fiber cores. Kindly refer to these documents.Clarification# 48: 3. Regarding Section 9.6 – Material Schedule for Earthing & Lightning Protection Systems (Material Schedule Table) in Electrical Technical Specification, should we follow the quantities specified in the provided schedule for both the earthing and lightning protection systems?Response: Yes, the bidder shall strictly adhere to the quantities specified in the Material Schedule Table under Section 9.6 of the Technical Specifications, specifically electrical BoQ Items 10.1 and 11.1 in REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities, covering the earthing and lightning protection systems, respectively. The BoQ explicitly refers bidders to the Technical Specifications for these requirements; therefore, the specified quantities shall be considered mandatory.Clarification# 49: 4. In BOQ Item No. 5.2, the total rated current of the circuit breakers exceeds the current-carrying capacity of the busbar. Please ClarifyResponse: Please refer to the revised documents REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsThe correction includes:The busbar must be sized as 1.25 x rated capacity
Clarification
Clarification# 35: Part threeFollowing our review of the tender documents, drawings, BOQ, and technical specifications we kindly request clarification on the following technical points:5. Earthing System – Earth ResistanceAs per Tender BOQ – Annex 4:Supply, install, test and commission a complete earthing grid and bonding system for PV arrays, string inverters, BESS containers, 7 MVA Transformer station with 0.8 kV LV Switchgear, and 11 kV OHL, as per specifications and drawings.Minimum requirements:Earthing Grid Copper Conductor of minimum size 50 mm².Earthing Grid Depth: 0.5 Meter as per the specification and drawing.Earthing Grid Area: L: 166 m × W: 87 m.Earth electrodes/pits, copper conductors, bonding, clamps and couplers to all metallic parts.Target earth resistance: ≤ 1 Ohm (or lower if required by Employer).Exothermic welding or approved clamps; test links.Compliance: IEC 60364-5-54 / BS 7671 / IEEE80.Includes earth testing with calibrated tester and reports.Earth resistance should be tested in the presence of the UNOPS representative by a calibrated earth tester, and the earth resistance should not be more than 5 Ohm.Note: The item does not include the existing earthing pit, only connection to the existing pits and adding any additional earthing pits required.As per Annex 2:Resistance Limit: The main grid resistance must be ≤ 1.0 Ω (Calculated at 0.20 Ω).Request for Clarification:Please clarify the required earth resistance limit: ≤ 1 Ohm or 5 Ohm.Response: The earth resistance ≤ 1 Ohm as corrected in tender document "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis"Clarification# 36: 6. Lightning Protection System – Type of Lightning RodsAs per Tender BOQ – Annex 4:Supply, install, test and commission an ESE lightning protection system for the PV Area, BESS containers, 7 MVA Transformer Station with 0.8 kV LV Switchgear, and 11 kV Overhead Line, as per specifications and drawings.Minimum requirements:Design per IEC 62305, NFC 17-102 (2011); ESE Lightning Rods with Efficiency (ΔT): 60 μs.Down conductors, test joints, and earth termination.Bonding with earthing system; separation distance maintained.Includes risk assessment assumptions and as-built test records.Lightning protection materials per IEC 62305.Includes air terminals, down conductors (copper 50 mm² with saddles/clamps), test joints, and earth termination.Air terminals (Franklin rods) SS/Cu, 1 m height with base and fixings.Down conductor copper 50 mm² with saddles/clamps, test joints and bonding accessories.As per Annex 2:Quantity: 4 ESE Lightning Rods.Efficiency (ΔT): 60 μs (Model PDC 6.4 or equivalent).Mounting: 6 m elevation masts above the highest equipment point.Protection Radius (Rp): ≈86.7 m at Level II.Request for Clarification:Please clarify the required lightning protection rod type, considering that the BOQ refers to both ESE lightning rods and Franklin rods.Response: The required lightning protection rod type is ESE as corrected in tender document " REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis"Clarification# 37: 7. Lightning Protection System – Shadow EffectAs per Annex 2, the lightning rods shall be mounted on 6 m elevation masts above the highest equipment point.Request for Clarification:Has the shadow effect created by these 6 m elevation masts on the PV modules been considered in the project design?Response: All shading-related calculations and assessments have already been considered during the design stage. Accordingly, the bidder shall strictly comply with the minimum technical requirements specified in the tender documents, with no deviations permitted.Clarification# 38: In order to ensure the submission of a highly comprehensive, fully compliant, and competitive technical and financial proposal that meets the strict standards and detailed requirements of UNOPS, we kindly request a deadline extension of at least one (1) week.Due to the complex technical specifications and the coordination required with international manufacturers to assemble an integrated offer, this additional time is essential for us to finalize a high-quality submission.Response: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.
Clarification
Clarification# 33: Part Two Following our review of the tender documents, drawings, BOQ, and technical specifications we kindly request clarification on the following technical points:3. 7 MVA Step-Up Transformer – Short-Circuit Impedance (Z%)As per Tender Drawing – Annex 5 and Tender BOQ – Annex 4:Rating: 7.0 MVA (Continuous Maximum Rating).Voltage Ratio: 11 kV / 0.8 kV.Cooling and Type: Oil-immersed with ONAN/ONAF cooling.Vector Group: Dyn11.Winding Material: High-grade electrolytic copper with Class A (105°C) insulation.Impedance: 6% at 75°C.Core: High-grade, grain-oriented silicon steel with mitred joints for low noise and minimal no-load losses.Tap Changer: Off-Circuit Tap Changer (OCTC) with a range of ±2 × 2.5%.Protection Devices: Buchholz relay (double-float), Magnetic Oil Level Gauge (MOG), Pressure Relief Device (PRD), and DGPT (Detection of Gas, Pressure, and Temperature).Conservator: Sized for expansion from -5°C to +100°C; includes a silica gel breather and sump for sludge.Valves: Tinned brass or stainless steel; includes drain, filter, and oil sampling valves.Winding: Electrolytic copper, paper-insulated, designed for high short-circuit strength.Bushings: Outdoor porcelain or resin-molded; 12 kV (MV) and 1.1 kV (LV) ratings.As per Standard Specification after Calculations:The same specifications are stated, except:Short Circuit Impedance at Rated Current Z%: 8% at 75°C as IEC 60076-5.Notes:Z%: 8% as IEC 60076-5.If they connect this system with the Public Grid, the transformer short-circuit current = 63.15 kA/1 sec at the 0.8 kV side, whereas it was 84.2 kA/1 sec at 0.8 kV and Z% = 6%.Request for Clarification:Please clarify and confirm the required Short Circuit Impedance at Rated Current Z% value, considering the above discrepancy between 6% and 8%.Response: Short Circuit Impedance at Rated Current 7% as revised in BoQ and drawing "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis and REV 1 - Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing No. E1-08."Clarification# 34: 4. 0.8 kV LV Switchgear – Circuit Breaker SpecificationsAs per Tender Drawing – Annex 5:Rating: 0.8 kV, 6300A, 50Hz, IP55.Busbars: Tinned high-conductivity copper, rated for 6300A continuous.Circuit Breakers: Low-Voltage Air Circuit Breaker (ACB), 4 or 3-Pole, withdrawable type, with motorized spring-charging mechanism with shunt trip and under-voltage release, rated continuous current: 1 × 6300A.Minimum 15 Pieces of 4-Pole, 300A Circuit Breakers (MCCBs).Minimum 10 Pieces of 4-Pole, 200A Circuit Breakers (MCCBs).Multifunction Meter: Digital device that measures, monitors, and displays multiple electrical parameters, such as voltage, current, power, energy, and frequency.Safety: Internal arc classification and mechanical interlocks to prevent breaker movement while in the "ON" position.SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB.As per Tender BOQ – Annex 4:Rating: 0.8 kV, 6300A, 50Hz, IP55.Busbars: Tinned high-conductivity copper, rated for 6300A continuous and 50kA (1 sec) short circuit, dimension 5 × (100 mm × 10 mm).Circuit Breakers: Vacuum (VCB)/Air withdrawable Circuit Breakers (ACB) with motorized mechanisms (1 × 6000A, 1 × 1000A ACBs), Minimum 24 Pieces of 4-Pole, 300A Air Circuit Breakers (ACB), Draw-out type.Mechanism: Motorized spring-charged with shunt trip and under-voltage release.Protection: Integrated microprocessor trip units with LSIG (Long-time, Short-time, Instantaneous, Ground fault) functionality.Multifunction Meter: Digital device that measures, monitors, and displays multiple electrical parameters, such as voltage, current, power, energy, and frequency.Safety: Internal arc classification and mechanical interlocks to prevent breaker movement while in the "ON" position.SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB/VCB.As per Annex 2:Circuit Breakers: One Vacuum (VCB)/Air Circuit Breaker (ACB) with motorized mechanisms, Minimum 25 Pieces of 4-Pole Air Circuit Breakers (ACB), Draw-out type.Mechanism: Motorized spring-charged with shunt trip and under-voltage release.Protection: Integrated microprocessor trip units with LSIG (Long-time, Short-time, Instantaneous, Ground fault) functionality.Safety: Internal arc classification and mechanical interlocks to prevent breaker movement while in the "ON" position.SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main VCB/ACB.Feeder Recommendations:Main Transformer Outgoing: 6,300 A Air Circuit Breaker (ACB).Solar Inverters (15 units): 250 A MCCB or ACB.BESS Modules (10 units): 180 A MCCB or ACB.Auxiliary Transformer: 63 A MCCB.As per Standard Specification after Calculations:Rating: 0.8 kV, 6300A, 50Hz, IP55.Busbars: Tinned high-conductivity copper, rated for 6300A (50kA) continuous.Circuit Breakers: Low-Voltage Air Circuit Breaker (ACB), 4 or 3-Pole, withdrawable type, with motorized spring-charging mechanism with shunt trip and under-voltage release, rated continuous current: 1 × 6300A + 1 × 1000A.Minimum 15 Pieces of 4-Pole, 300A Circuit Breakers, 25kA (MCCBs).Minimum 10 Pieces of 4-Pole, 200A Circuit Breakers, 25kA (MCCBs).Multifunction Meter: Digital device that measures, monitors, and displays multiple electrical parameters, such as voltage, current, power, energy, and frequency.Safety: Internal arc classification and mechanical interlocks to prevent breaker movement while in the "ON" position.SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB.Notes:VCB only at MV.In the current network configuration, there is no problem in terms of short-circuit current. However, in the future, if they connect this system with the Public Grid, the short-circuit current will increase to (Isc): 84.2 kA at (0.8 kV & Z% = 6%) main busbar.Request for Clarification:Please provide the exact technical specifications required for each type of circuit breaker and the requirements necessary to ensure proper system protection.Response: The technical specifications required for each type of circuit breaker and the requirements necessary to ensure proper system protection is reflected in the Electrical BoQ Item No. 5.2 "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis" which has been revised to match Single Line Diagram (SLD) drawing E1-08 and as follows:a. Incoming Circuit Breakers: (15 x 400 A, 4-pole MCCBs) and (10 x 250 A, 4-pole MCCBs)b. Outgoing Circuit Breakers: (1 x 6300 A ACB) and (1 x 63 A MCCB)
Clarification
Clarification# 30: Regarding Item No. 12 – Smart Metering System, we would like to seek your clarification on the communication technology.The tender specifications mention LoRa and PLC communication options. However, we would like to propose LoRaWAN, which offers an alternative communication solution with advantages in scalability, network management, and long-range connectivity.Could you please confirm whether we should submit our proposal strictly based on the communication options specified in the tender documents (LoRa or PLC), or whether UNOPS would accept an alternative proposal based on LoRaWAN, subject to meeting or exceeding the required technical specifications?Response: LoRa refers to the physical Radio Frequency (RF) modulation technology; therefore, LoRaWAN is not considered an alternative communication technology but rather a network protocol operating over the LoRa physical layer.Accordingly, the proposed LoRaWAN solution may be considered under the RF communication option specified in the tender documents. Bidders shall ensure full compliance with the applicable technical requirements and the provisions of the Electrical BoQ, particularly Items 12.1.1.1, 12.1.1.2, and 12.1.1.3, which specify PLC/RF communication options.Clarification# 31: Part one Following our review of the tender documents, drawings, BOQ, and technical specifications we kindly request clarification on the following technical points:1. HV Lithium Battery Energy Storage Unit (BESS)As per Tender Drawing – Annex 5:· Chemistry: LFP (Lithium Iron Phosphate) preferred.· Total Nominal Energy: Minimum (10 × 373 kWh = 3.73 MWh).· Nominal system voltage: Compatible with inverter HV battery range.· Built-in rack BMS with cell monitoring (V, T), balancing, alarms, and communication to master BMS.· Cycle life: ≥ 6,000 cycles @ 80% DoD (or better) with third-party report.· Operating temperature: -10°C to +50°C (with derating policy), storage -20°C to +55°C.· Safety: UL9540/IEC 62619 (or equivalent), integrated fuses/contactors, insulation monitoring.· Warranty: ≥ 10 years.· Includes racks, internal busbars, power and communication cables, and all accessories.As per Tender BOQ – Annex 4:The same requirements are specified, except:· Total Nominal Energy: Minimum 3.8 MWh.Request for Clarification:Please clarify the required minimum total nominal energy capacity: 3.73 MWh or 3.8 MWh.Response: The nominal energy capacity is 3.8 MWh as per the revised BoQ and drawings "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis and REV 1 - Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing No. E1-09."Clarification# 32: 2. Power Conversion System (PCS)As per Tender Drawing – Annex 5:· Bi-directional (10 × 190 kW) inverters system with native microgrid intelligence.· Grid-Forming (GFM / Virtual Synchronous Machine) Mode (Primary Mode): Serves as the primary voltage and frequency reference (800 V, 50 Hz) for the isolated mini-grid when operating without diesel generators.· Grid-Following (GFL) & Dynamic Droop Mode (Parallel/Charging State): When one or both 1,250 kVA diesel generators are running and master the 11 kV/0.8 kV bus, the PCS seamlessly switches or operates in dynamic P-f/Q-U droop mode to share real and reactive load or absorb surplus solar energy.· Controlled Soft-Start & Transformer Energization: Capable of black-starting the local 7 MVA (0.8/11 kV) step-up transformer and 11 kV OHL feeder from a de-energized state.· Voltage Ramp Control: Soft-ramps output AC voltage from 0 V to 800 V over a configurable window (1–10 seconds) to eliminate transformer magnetizing inrush currents and prevent over-current trips.· Hardware Reverse Power Protection: Coordinates with MGC control logic to enforce active power flow limits at the 0.8 kV switchgear, preventing unauthorized reverse power flow into running diesel generator sets (protecting directional power relays, ANSI 32).· Reverse Power Inhibition: Prevents exporting power to the 11 kV bus when the Diesel Generator is the sole grid-forming source.· SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB.As per Tender BOQ – Annex 4:· Bi-directional 1.9 MW inverter system with native microgrid intelligence.· The remaining operating mode and protection requirements are specified as described above.As per Annex 2 – Section 4.3:The Power Conversion System (PCS) shall be a bi-directional, utility-grade 1.9 MW, 800 VAC inverter system with native grid-forming (GFM) and grid-following (GFL) control modes, optimized for seamless transition and parallel operation with synchronous diesel generators.Additional requirements include:· Virtual Synchronous Machine (VSM) algorithms with programmable virtual inertia (H = 1.0–5.0 s) and synthetic damping.· Overload capability: ≥ 110% continuous for 10 minutes, and ≥ 150% for 10 seconds.· Grid-Following (GFL) and Dynamic Droop Mode when one or both 1,250 kVA diesel generators are running and mastering the 11 kV/0.8 kV bus.· Controlled soft-start and transformer energization, including black-start capability for the local 7 MVA (0.8/11 kV) step-up transformer and 11 kV OHL feeder.· Voltage ramp control from 0 V to 800 V over a configurable window of 1–10 seconds.· Hardware reverse power protection coordinating with MGC control logic to prevent unauthorized reverse power flow into running diesel generator sets (ANSI 32).Note:It is preferable to write in the BOQ:"Bi-directional (10 Units × 190 kW) inverters system with native microgrid intelligence."Request for Clarification:- Please clarify and confirm the required PCS configuration- Whether the BOQ should specify 10 units × 190 kW instead of only stating 1.9 MW.Response: - The PCS must be Grid Forming operation.- The requirement in BoQ specifies 10 units x 190 kW PCS and bidders must follow this requirement.
Clarification
Clarification# 22: 10. Transformer winding material and voltage ratio wordingWith reference to the following items of tender documents:-• Electrical BoQ 5.1 / Tech Questionnaire 5.1: “Winding Material: High-grade electrolytic copper…” (repeated); Voltage Ratio stated as “11 kV (MV) / 0.8 kV (LV)” while plant LV bus is 0.8 kV stepping up to 11 kV.• No aluminium-winding option appears in the Questionnaire (copper mandatory), which is clear; ambiguity is mainly LV/MV order and CMR 7.0 MVA vs plant inverter AC ≈4.5 MVA + PCS 1.9 MW.Clarification question: Please confirm that- Copper windings are mandatory (aluminum not accepted),- That the transformer is 0.8/11 kV Dyn11 7.0 MVA CMR and whether the 7 MVA rating (vs ~6.4 MVA connected generation) is intentional for future expansion.Response: - The transforemer winding must be copper and aluminium is not accepted.- The 7 MVA can be raised with maximum flexcibilty of 30% extra to meet site conditions as amended in specifications in the documents:REV 1 -1 Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitisREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableREV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 23: 11. String inverter GFM requirement vs BESS as GFM masterWith reference to the following items of tender documents:-• Tech Questionnaire / BOQ. 2.1: string inverters require “Grid-forming capability: voltage/frequency regulation, black start, droop control” AND hybrid interoperability as high-speed slave under BESS GFM master.• BESS PCS (3.2): primary GFM / VSM at 800 V, 50 Hz when operating without diesel.Clarification question: Please clarify whether string inverters must themselves provide native GFM/black-start capability, or whether GFL operation as slaves to the BESS GFM PCS (and/or diesel) fully satisfies the technical criteria.Response: String inverters must be Grid Following operation as slaves to the BESS Grid Forming PCS or Diesel generators.Clarificartion# 24: 12. Missing / mis-numbered BOQ spare items and cleaning-robot sparesWith reference to the following items of tender documents:-• Electrical BOQ. spares jump from 23.2 (inverter spares) to 24.3 (transformer spares); items 24.1 / 24.2 appear missing (numbering).• Robots: main item 22.1 = 105 pcs; spare set 24.9.1 = 10 Sets — Which unit of measuring to be considered and what’s different?.• CCTV items 19.2 / 19.3 titles are “8MP” while description are “6MP”.Clarification question: Please issue a corrected BOQ spare-parts schedule (restoring any missing lines if any), and confirm the req. CCTVResponse: (a) The BoQ has been revised to correct the typographical error in the item numbering.(b) Additionally, Item 23.9.1 represents the spare parts associated with the main item 22.1.(c) CCTV items 19.2 and 19.3 have been revised accordingly. The required camera specification is 8 MP resolution.The amendment is under REV 1 -1 Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitisClarification# 25: 13. Kindly include the quantities of the stone Retaining wall as per drawing D-11- Annex 5CResponse: Please note that is is included in the BoQ "REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis item" under the Civil Work BoQ items# 1.4.2.2 and 1.4.2.3.Clarification# 26: 14. Please Specify and describe the responsibility and works / items to be done by beneficiary (end user) during implementation period of the project .Response: As per the UNOPS contract , the end user responsibility is to volunteerly facilitate the work of the contractor. Any requirements should be requested, it must be through the UNOPS assigned engineer.Clarification# 27: we kindly ask you to provide the actual load information of the existing Hasswain Mini-Grid, including:- Actual daily load profile (preferably at 15-minute intervals).- Maximum and average load demand (kW/kVA).- Daily energy consumption (kWh).- Daytime and nighttime load demand.to assess the mini-grid load requirements and evaluate the capability of the proposed BESS system to support the network.Response: The requested information is not relevant to the contractor's scope of work, as the contractor is not responsible for designing or determining the load requirements.The contractor's obligation is to execute and deliver the works strictly in accordance with the scope, specifications, and technical requirements set out in the tender documents. Accordingly, the requested load information does not constitute a basis for modifying or deviating from the specified contractual requirements.Clarification# 28: We kindly request clarification on the following items regarding the Load Information:- Peak load power (kW): Could you please clarify this requirement?- Percentage of inductive load (%): Could you please clarify this requirement?- Inductive load list: Could you please clarify this requirement?- Average load power (kW): Could you please clarify this requirement?- Load duration hour (h): Could you please clarify this requirement?- Motor type and Qty if applicable: Could you please clarify this requirement?Response: The requested information is not relevant to the contractor's scope of work, as the contractor is not responsible for designing or determining the load requirements.The contractor's obligation is to execute and deliver the works strictly in accordance with the scope, specifications, and technical requirements set out in the tender documents. Accordingly, the requested load information does not constitute a basis for modifying or deviating from the specified contractual requirements.Clarification# 29: We kindly request a 7-day extension of the bid submission deadline, until 29 November 2026.This additional time is needed to finalize supplier quotations and complete the technical proposalResponse: Please be advised that the submission deadline has been extended to 29-November-2026 @ 09:00 AM. Kindly ensure preparing your submissions ahead of this date to avoid any last minute submissions.
Clarification
Clarification# 18: 6. BESS energyWith reference to the following items of tender documents:-• Annex 5B drawing E1-09 (SCADA Interface Schematic): 10 BESS units (BESS 01 … BESS 10) of about 373 kWh each ≈ 3.73 MWh total.• Annex 5B drawing E1-08 (Overall SLD): 10 PCS units PCS(1)…PCS(10) of 190 kW, 800 V (= 1.9 MW).• Electrical BOQ item 3.1 / Tech Questionnaire 3.1: nominal energy ≥3.8 MWh DC BOL.• No Annex 5B drawing states the number of BESS containers; E1-02 notes refer to a single “BESS Container” (weather station mounting), while BOQ 3.2 says “2x 20HQ” / “ISO 40HQ”.Clarification question: Please confirm(a) the minimum BESS energy (≥3.8 MWh DC BOL per BOQ, or 10 × 373 kWh ≈ 3.73 MWh per drawing E1-09), and whether it is nominal or usable;(b) whether the 10-unit / 10 × 190 kW PCS topology on E1-08/E1-09 is mandatory or indicative;(c) the required number and size of BESS containers, which no drawing shows.Response: (a) The BESS nominal energy capacity is 3.8 MWh as specified in REV 1 – Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing No. E1-09.(b) The relevant drawing has been revised accordingly under REV 1 – Annex 5-B: Electrical Drawings – Husswain Mini-Grid Power Station, Drawing No. E1-09.(c) The BESS installation comprises one container only. Therefore, there is no need to separately indicate the number of containers on the drawings, as this requirement is already clearly specified in the BoQ, technical questionnaires, and civil works.Clarification# 19: 7. BESS chemistry – LFP mandatory vs “preferred”With reference to the following items of tender documents:-• Technical Questionnaire / Comparative Data Table item 3.1: “Chemistry: Lithium Iron Phosphate (LFP), new and unused cells.”• Annex 1 Scope of Work Page 23 : “3.8 MWh Lithium Iron Phosphate (LiFePO4) BESS”.• Electrical BOQ item 3.3: “Chemistry: LFP (Lithium Iron Phosphate) preferred.”Clarification question: Please confirm whether LFP chemistry is mandatory (pass/fail) or only preferred, and whether any non-LFP chemistry would be accepted.Response: The required battery type is Lithium Iron Phosphate any other type is not accepted. all realted documents are revised. (REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis, REV 1- Annex 6 - Technical specifications for Goods and Comparative Data Table and REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications)Clarification# 20: 8. String inverter peak / rated powerWith reference to the following items of tender documents:-• Electrical BOQ item 2.1: “min Max. output power 330 (kW), Rated power 300 (kW)” and “parallel operation of 8 units”; quantity = 15 pcs.• Technical Questionnaire item 2: “Rated output power not less than 300 kW”; “Parallel operation of at least 8 units” — no explicit 330 kW peak requirement.• Annex 1 Scope of Work Page 23: “Fifteen (15) 300 kW” inverters; “each inverter manages exactly 21 strings.”• Drawing D-02 (DC Wiring SLD): “INVERTER RATING: 300 kW”; “TOTAL NOS. OF MPPT'S PER INVERTER: 15”; shows 21 strings per inverter.• Annex 5B drawings E1-03 (Inverters and String Zones), E1-04 (PV Array Layout & String Configuration) and E1-08 (Overall SLD: 15 × 300 kW inverters, “21 STRING / 24 PV per String Inverter, 504 MODULES”) , not state any MPPT count; the 15-MPPT figure appears only on Annex 5C typical drawing D-02.• Annex 5C drawing D-02 (DC Wiring SLD), notes 1–4: PV module 720 W; inverter 300 kW; 24 modules in series per string; “TOTAL NOS. OF MPPT'S PER INVERTER: 15”; 21 strings per inverter (String-1…String-21) — i.e. 15 MPPT confirmed on D-02, vs ≥6 MPPT minimum in Questionnaire/BOQ 2.1.Clarification question: Please confirm(a) whether a 330 kW maximum/peak output is mandatory in addition to 300 kW rated;(b) whether all 15 inverters must be capable of paralleling together (or only ≥8);(c) whether ≥6 MPPTs (questionnaire/BoQ) or 15 MPPTs (Annex 5C drawing D-02; not stated on Annex 5B E1-03/E1-04/E1-08) is the binding requirement.Response: (a) The string inverter specifications have been amended to read: "the maximum output power is 330 kW, while the rated output power is 300 kW" in the documents REV 1 - Annex 6 - Technical specifications for Goods and Comparative Data Table and REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications and Item 2.1 in REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis has been revised accordingly.(b) The string inverters shall be equipped with parallel operation capability, as required by the technical specifications. However, the actual paralleling connection and associated works are excluded from the current scope of work.(c) REV 1- Annex 5C - Typical Drawing - D-02- DC Wiring Single Line Diagram has been revised to reflect ≥6 MPPTs.Clarification# 21: 9. BESS usable energy / DoD / C-rate / EMS SoC windowWith reference to the following items of tender documents:-• Tech Questionnaire 3.1 / BOQ. 3.3: Nominal ≥3.8 MWh DC BOL; “usable energy at ≥90% DoD shall be declared”; cycle life ≥6,000 @ 80% DoD.• EMS (BOQ 3.6 / Questionnaire 3.4): nighttime discharge to 20% SoC; daytime charge to 90% SoC (70% usable window in operation).• PCS ≥1.9 MW with 3.8 MWh implies ~0.5C / ~2-hour duration, but no explicit C-rate or discharge-duration guarantee is stated as a pass/fail criterion.Clarification question: Please confirm- The guaranteed usable energy (MWh) and DoD basis for acceptance testing,- Whether EMS SoC limits (20–90%) override the ≥90% DoD declaration,- Whether any minimum discharge duration or C-rate is req.Response: - The BESS shall have a guaranteed nominal energy capacity of 3.8 MWh with a minimum Depth of Discharge (DoD) of 90%.- The EMS State of Charge (SoC) operating limits (20–90%) are defined by the control philosophy and do not supersede or modify the specified DoD requirement.- The BESS technical specifications explicitly emphasize the requirement for a C-rated battery.
Clarification
Clarification# 15: 3. Diesel generators – 6 sets on drawing E1-08 vs 2×1250 kVA in BOQ linesWith reference to the following items of tender documents:-• Annex 5B drawing E1-08 (Overall Single Line Diagram), “HUSWAIN GENERATION STATION” / existing generation station block: 6 Cummins canopy diesel sets, 0.415 V 50 Hz – 2 × 1000 kVA + 4 × 1250 kVA (≈7,000 kVA total), all six labelled “GENERATOR-1”, with three 3 MVA Dyn11 step-up transformers.• Electrical BOQ items of BESS/PCS/EMS repeatedly requiring coordination with “one or both 1250 kVA diesel generators”, reverse-power ANSI 32, wet-stacking protection, and OPGW start signal to powerhouse 400 V breakers (i.e. 2 × 1250 kVA).• Annex 5B drawing E1-09 (SCADA Interface Schematic) also shows generator/MGC interface.• Annex 1 Scope of work – Page 24- MGC: coordinate “backup Diesel Generator”.• No diesel generator supply/install or interface items shown in the Husswain Electrical or Civil BOQ.Clarification question: Please confirm :(a) the number and rating of diesel generators the MGC/EMS must coordinate with (6 sets of 2×1000 + 4×1250 kVA per drawing E1-08, or 2×1250 kVA per cite in Electrical BOQ), and correct the meaning of “GENERATOR-1” in drawing of all generators; (b) Are all generators, their 0.415 kV switchgear and the 3 MVA step-up transformers are existing / Employer furnished;& (c) Kindly specify the Contractor’s exact interface scope to be quoted (point of connection, protection relays (ANSI 32 etc.), control/start signals, OPGW termination & Cables at the powerhouse, and any retrofit of existing generator controllers).Response: a- The Micro-Grid Controller (MGC)/Energy Management System (EMS) shall coordinate the operation of two existing diesel generators, each rated at 1,250 kVA (2 × 1,250 kVA), located in the existing power house. Refer to Clause 5, Micro-Grid Controller (MGC) & Energy Management System (EMS), of the document named "REV 1- Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications".b- All generation units, step-up transformers, and 11 kV RMUs indicated in the Single-Line Diagram (SLD) are existing equipment installed in the respective power houses.c- The communication requirements, network architecture, and interface configurations are comprehensively detailed in Clause 5.1, Communication System & Network Topology, of the document named "REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications"Clarification# 16: 4. PV plant ,size of mounting steel structureWith reference to the following items of tender documents:-• Annex 1 Scope of Work Page 24: Lightning Protection: ESE system “covering the 1,728-module field and BESS containers”. 1,728 modules would be only ≈1.24 MWp at 720 Wp — inconsistent with 5.44 MWp plant sizing required.• Annex 5D drawing S-11 (Solar Panels Distribution Plan- Mayfa city ?): the dimensions of each steel structure of each solar panels group (2x36=72 solar panels) are 9X5.4 m – 48.6 m length by 4.25 m width• Annex 5A drawing A-6 (Architecture Plan): Site area ≈ 277.3 × 256.8 m; shown dimensions ≈ 47.5 m long at 4.8 m width with 4.0 m spacing (vs 48.6 m x 4.25m on S-11).Clarification question:- Kindly confirm which length is correct 47.5 m or 48.6 m- The drawings of Annex 5D of Mayfa is valid to be used for Husswain area ?- Is the overall dimension of site will not effect due that confliction of length of each steel structure of each solar panels group- Clarify about the “1,728-module” and “36 PV Modules” references if erroneous.Response: - The typical drawings shows the maximum spacing that can be used between the solar panels to have the overall maximum width for the group that can be used in this typical to give maximum 48.6m. The width of solar are based on the offer and the total width of group will be based on the selected PVs type. The minimum spacing is 15-20mm- Yes, the drawing of Annex 5D is valid to be used for Husswain area.- The general drawings shows the overall dimensions using the minimum spacing of 19mm.- As per the contract scope and the contractual terms, the contractor is required to prepare shopdrawings prior the start of work and submit for approval and this will be based on the contractor PV offered brand.Clarification# 17: 5. BESS container size – 2×20HQ vs ISO 40HQ vs 6.06×2.4 m foundationsWith reference to the following items of tender documents:-• Electrical BOQ. item 3.2 title: “2x 20HQ container modified for BESS…”.• Same item 3.2 minimum requirements: “ISO 40HQ container, CSC plate…”.• Item 3.1 / 3.15: “all in one or two” containers.• Annex 1 Scope of Work Page 12: container foundations “(6.06 × 2.4 m containers for BESS)” (=20 ft footprint), not 40 ft.• Annex 5C drawing D-09 / CF-1 (Foundation of the Steel Container): one ring footing CF1 0.60 m × 0.30 m around a 6.7 × 3.0 m plan, i.e. a 20 ft footprint; no quantity stated.• Civil BOQ 2.0 Containers Foundations: the quantities — which equals roughly ONE Container Foundation CF1 as per drawing D-09, while the plant needs BESS (2 × 20HQ or 1 × 40HQ), LV switchgear container and RMU containers , therefore quantities are not enough.Clarification question:- Please clarify the mandatory BESS enclosure configuration (number of containers and 20HQ vs 40HQ)- Confirm how many container foundations (D-09 CF1, 6.7 × 3.0 m) are to be built and measured for BESS, LV switchgear and RMU containers with updating quantities of Civil BOQ , since Civil BOQ 2.0 quantities (RC 3 m³) cover only about one foundation; if 40HQ is required, please issue the corresponding foundation drawing.Response: - The required BESS container is 20HQ and all realted documents has been revised."REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis, Electrical Work BoQ Item No. 3.2 "- Yes, we confirm that all foundations shall be constructed for the BESS, LV switchgear, and transformer (excluding the RMU), as specified in the Civil Work BoQ. The quantities shall be based on the requirements for two (2) 20-foot HQ containers.
Clarification
Clarification# 10: Item 3.8: The tender specifications specify a water/glycol cooling system for the Battery Energy Storage System (BESS).Question? Would UNOPS accept an alternative, advanced technology such as an immersion liquid cooling system?Response: No alternative cooling system shall be accepted under any circumstances. The bidder must comply with the specified cooling system requirements as per technical specifications.Clarification# 11: Is it acceptable for the lead company to take on less than 50% of the project responsibilities?Response: There is no limit on the percentage of the JV membership. JV members should fill the returnable form schedule 0.3 Joint Venture Partner Information and according to the instructions.Clarification# 12: I have joined the pre-bid meeting but had unstable internet connection, will the meeting link be shared and the Q&A with us?Response: The pre-bi meeting minutes have been shared under amendment# 2. Please go to the "Documents" section and you will find the document named "Minutes for Pre-bid Meeting RFQ-2026-65288" for your reference.Clarification# 13: 1. (11) kV OHL scope missing from BOQ (conductors, poles) vs Scope / OPGW-only in BOQWith reference to the following items of tender documents:-• Annex 2 Scope of Work - Item NO. (7) Regarding 11KV Overhead Lines: requires 11 kV OHL with conductors size 150 mm² (e.g. ACSR “Wolf”), 11 m treated poles/structures, C5-M cross-arms, insulators, and 12 kV gapless surge arresters.• Electrical BOQ item 6.0/6.1: only “Optical Ground Wire (OPGW)… Minimum 24 fibers… Qty 3.0 km” —items for ACSR phase conductors, poles, cross-arms, insulators, or surge arresters for the OHL are not mentioned or required for quotation ??• Annex 1 Scope of Work Scope of works – Page 33 regarding: 11kV overhead Line Pre-Commissioning and Commissioning• Electrical BOQ Item No. 24.6 list OHL insulator/arrester/hardware spares Parts , implying an OHL exists, but main OHL construction items are not included in BOQ.Clarification question: Please confirm whether the 11 kV overhead line (poles, 150 mm² ACSR phase conductors, hardware and arresters) is part of this Tender ? and, if so, Please provide BOQ line items and quantities; or confirm that only 3 km of OPGW (shield wire/comms) is required and phase conductors/poles are Employer (End User) -furnished / out of scope.Response: The overhead transmission line (OHL) installation activities are not part of the contractor’s scope of work and shall be carried out by the relevant authorities in Al-Mahrah Public Electricity Corporation (PEC).The contractor’s responsibilities are limited to the supply of the complete Optical Ground Wire (OPGW) fiber-optic conductor, supervision of its installation by PEC, and subsequent testing and commissioning.Accordingly, the scope of work has been revised to clearly distinguish the contractor’s responsibilities from PEC’s installation responsibilities, ensuring a clear definition of the contractual division of responsibilities and avoiding any potential ambiguity during implementation. "REV 1 - Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station"Clarification# 14: 2. (11) kV OHL phase conductor type – AAAC (E1-08) vs ACSR (Scope)With reference to the following items of tender documents:-• Annex 5B drawing E1-08 (Overall Single Line Diagram): “11kV OHL - AAAC (150 mm²)” between the plant RMU and the existing generation station.• Annex 2 Scope of Work - Item NO. (7.3) Regarding 11KV Overhead Lines: “Conductors size 150mm2 (e.g., ACSR “Wolf””)”.• Neither conductor mentioned the quantities in BOQ .Clarification question: Please confirm 11 kV OHL phase-conductor type and size (AAAC 150 mm² per drawing E108 or ACSR 150 mm² “) and is in Scope of works or not , also, illustrate the route length, and the applicable standard (IEC 61089 / EN 50182), so that conductor, fittings and OPGW sag-tension coordination can be priced consistently.Response: The overhead transmission line (OHL) installation activities are not part of the contractor’s scope of work and shall be carried out by the relevant authorities in Al-Mahrah Public Electricity Corporation (PEC).The contractor’s responsibilities are limited to the supply of the complete Optical Ground Wire (OPGW) fiber-optic conductor, supervision of its installation by PEC, and subsequent testing and commissioning.Accordingly, the scope of work has been revised to clearly distinguish the contractor’s responsibilities from PEC’s installation responsibilities, ensuring a clear definition of the contractual division of responsibilities and avoiding any potential ambiguity during implementation. "REV 1 - Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station"
Clarification
Clarification# 6: Can you clarify:- The requirements related to Joint Venture submissions between a local and an International company? Does the International Company need to be registered in the UNGM or is the registration of the local company is sufficient to be eligible?- Previous Experience Requirements: If one of the companies (the international company for example) meets the requirements in the same field, is it enough to have this as a JV or does both companies require to have independent previous similar experience to meet this criteria?Response: Please note: - The eligibility crteria states: The bidder is eligible as defined in Section I: Instructions to Bidders, Article 4 [Bidder Eligibility].In case of Joint Venture (JV) each joint venture member must meet the requirement. To establish this criteria by a bidder and his JV partner, they both need to be registered in the UNGM as suppliers and cleared from the UNGM ineligibility lists.- The previous experience criteria states: In case of Joint Venture (JV), all joint venture members combined must meet it. Thus, this criteria can be fulfilled either by merging the previous experiences of both the bidder and the JV partner or if one partner can provide all the required project experience.Clarification# 7: With reference to Annex 4 – Bill of Quantities, Item 12.1.1.3 (Customer Interface Unit – CIU), and the related requirements under Annex 2 – Electrical Technical Specifications, we kindly request clarification regarding the required quantity and configuration of the CIU system.The Bill of Quantities indicates the CIU quantity as “1 System”, while the project includes a total of 2,200 smart meters (2,100 single-phase and 100 three-phase).In this regard, we would appreciate UNOPS's clarification on the following:a. Is one CIU required for each individual customer meter, meaning a total of 2,200 CIUs, or is the requirement for one centralized/shared CIU system serving all customers?b. If individual CIUs are required, should each CIU be supplied as a separate unit and paired with its corresponding smart meter?c. If a centralized or alternative configuration is intended, kindly provide the expected system architecture and the required quantity of CIUs.d. Please confirm whether the CIU communication interface with the corresponding smart meter may utilize either RF or PLC communication, as indicated in the relevant BOQ requirements.Response: (a, b and c) Dedicated 1-to-1 Deployment (No Centralized Architecture): The CIU will be a separate physical unit for each individual customer meter, covering all 2,200 meters (2,100 single-phase and 100 three-phase). No centralized or shared CIU architecture will be used. Because the meters utilize a split-meter configuration (with the measuring unit installed externally on poles or boundary enclosures), every consumer premise requires its own dedicated indoor CIU keypad for token entry and monitoring. The BoQ line item listing "12.1.1.3" represents the overall metering package header and requires pricing for 2,200 individual CIU units.Programming, Binding, & Configuration: A dedicated CIU will be specified for each meter. Each CIU must be either pre-programmed at the factory or programmed/paired on-site to establish a secure, 1-to-1 logical binding with its assigned split meter before commissioning.(d) Communication Interface (PLC Primary with RF Option):Local communication between the indoor CIU and the outdoor smart meter shall be primarily via Power Line Communication (PLC), with the availability of an RF (Radio Frequency) option to accommodate varying site conditions, structural wall barriers, or localized electrical noise across the distribution grid.System Security & Authentication: The system must implement robust security and authentication protocols across the entire metering loop.All 20-digit STS (Standard Transfer Specification) tokens generated by the cloud platform (or local failover server) must be cryptographically secured using a Hardware Security Module (HSM) or equivalent software module. Mutual authentication between the CIU and its paired meter ensures that token transmission is protected against tampering, interception, or cross-meter credit transfer attempts.Clarification# 8: With reference to RFQ-2026-65288 – Provision of a Mini-Grid Solar Power Plant System for Husswain, Al-Mahrah Governorate, Republic of Yemen.During our technical review, we identified a number of differences and inconsistencies between the documents that require clarification to ensure that our proposed solution fully complies with UNOPS requirements.We would appreciate your clarification on the following points:1. BESS Energy Capacity – Nominal DC Capacity vs. Usable AC CapacityThe tender documents specify the BESS energy capacity differently:• Annex 2 requires a minimum usable energy capacity of 3.8 MWh AC-side at End of Life (EOL).• Annex 6, Item 3.1, specifies a minimum nominal energy capacity of 3.8 MWh DC at Beginning of Life (BOL), with usable energy at 90% DoD to be declared.• The updated electrical drawings (Annex 5B, Drawing E1-08) indicate 10 battery units, each rated at approximately 373 kWh, resulting in a total nominal capacity of approximately 3.73 MWh.Could you please confirm the governing BESS capacity requirement and clarify whether the minimum required capacity is 3.8 MWh usable AC-side at EOL, or 3.8 MWh nominal DC at BOL?Response: 1- BESS capacity requirement is 3.8 MWh nominal capacity. As revised in REV 1- Annex 2 - Electrical - Husswain Mini-Grid Technical SpecificationsClarification# 9: 2. BESS Cycle Life and Remaining Capacity at EOLWe also noted a difference in the required battery capacity retention:- Annex 2 specifies a minimum cycle life of 6,000 cycles at 80% DoD, with the remaining capacity at EOL specified as 70%.- Annex 6, Item 3.1, specifies at least 6,000 cycles at 80% DoD, with at least 80% remaining capacity under the specified test conditions, or equivalent warranted lifetime energy throughput.Please confirm the applicable minimum remaining capacity requirement at EOL and whether the 70% or 80% capacity retention requirement shall govern.Response: Please refer to the amended documents "REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications" and 80% capacity is required
Amendment #2
Dear Bidders,This purpose of this amendment is to:Add the prebid meeting minutes to the eSourcing document tab The document RFQ-2026-65288- Solicitation, Sections II, III, IV, V is amended toExtend the implementation period from 5 months to 8 months as highlighted in yellow.The document Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station is amended toExclude the 11 kV OHL from the contractor’s scope of workThe document Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications is amended toUpdate the battery capacity in page# 13: Section 4: Part 4.1: System overview and rating (BESS Capacity) as highlighted in yellow.Update the busbar rating in page# 27: Section 6.3: 0.8 kV LV Switchgear Specification as highlighted in yellow.The document Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantities is amended toUpdate the technical specifications for items# 2.1 - 3.2 - 3.3 - 5.1 - 5.2 - 6.1 - 7.4 - 8.2.1 - 10.1 - 11.1 - 19.2 - 19.3 as highlighted in orange.Correct the numbering from items# 23.3 to 23.10 as highlighted in orange.The document Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station is amended to Update the drawing in sheets# E1-8 and E1-9.The document Annex 5C- Typical Drawings - D-02-DC Wiring Single Line Diagram is amended toUpdate the number of MPPTs from 15 to >/= 6.The document Annex 6 - Technical specifications for Goods and Comparative Data Table is amended toUpdate the technical specifications for items# 3.1 - 5.1 - 5.2 as highlighted in orange.eSourcing general tab is amended as followExtending the submission deadline from 22 November 2026 @ 10:00 AM to 29 November 2026 @ 10:00 AMExtending the clarifications deadline from 12 November 2026 @ 12:00 PM to 17 November 2026 @ 12:00 PMeSourcing particular is amended as follows Extending the expected contract award date from 22 December-2026 to 29 December-2026 (The contract award date is only anticipated and not binding)eSourcing Criteria tab under Technical Criteria section is amended as followsThe work plan criteria is extended from 5 months to 8 monthseSourcing Questionnaire tab is amended as followsQuestion 11 is amended according to the 8 months work plan.Therefore;eSourcing Document Tab is amended to add the following documents: Minutes for Pre-bid Meeting RFQ-2026-65288REV 1 - RFQ-2026-65288- Solicitation, Sections II, III, IV, VREV 1 - Annex 1 - Scope of Work Husswain Mini-Grid Solar Power StationREV 2 - Annex 1 - Electrical - Husswain Mini-Grid Technical SpecificationsREV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of QuantitiesREV 1 - Annex 5B - Electrical Drawings - Husswain Mini-Grid Power StationREV 1 - Annex 5C- Typical Drawings - D-02-DC Wiring Single Line DiagramREV 1 - Annex 6 - Technical specifications for Goods and Comparative Data TableeSourcing General tab under description is updated to: Extending the submission deadline to read 29 November 2026 @ 10:00 AMExtending the clarifications deadline to read 17 November 2026 @ 12:00 PMeSourcing Particulars tab under scope of quotation is updated to:Extending the expected contract award date to read 29 December-2026 (The contract award date is only anticipated and not binding)eSourcing Criteria tab is amended to update the work plan criteria to 8 monthseSourcing Questionnaire tab Question 11 is amended to reflect the 8 months work planALL OTHER TERMS & CONDITIONS UNDER THIS TENDER REMAINS THE SAME ....
Clarification
Happening now: The pre-bid meeting is held virtually now via the following link: (https://meet.google.com/fnj-zmfg-pbh). ALL interested suppliers are encouraged to attend the pre-bid meeting.
Clarification
Clarification# 4: Please share the pre bid meeting link Response: Please note that the pre-bid meeting has been extended under amendment# 1 to read as below:The pre-bid meeting will be held on 05-November-2026 @11:00 am Sana'a, Yemen time virtually via the following link: (https://meet.google.com/fnj-zmfg-pbh).
Clarification
Clarification# 5: Appendix 5B of the electrical drawings remains damaged as is, and no modifications have been made. Response: Ammendment# 1 has been published to replace the corrupted document named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station" with a correct version named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station - Updated". Kindly check the documents tab for the corrected document.
Amendment #1
Dear Bidders,This purpose of this amendment is to:The document "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station" is corrupted and is replaced with the corrected version.eSourcing Particulars tab is amended as follows:Extending the pre-bid meeting date from 01 November 2026 @ 11:00 AM to 05 November 2026 @ 11:00 AMTherefore1. eSourcing Document Tab is amended to add the following documents: Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station - Updated2. eSourcing Particulars tab under description is updated to: Extending the pre-bid meeting date to read 05 November 2026 @ 11:00 AMALL OTHER TERMS & CONDITIONS UNDER THIS TENDER REMAINS THE SAME ....
Clarification
Clarification# 1: We would like to inform you that the file "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station.pdf" appears to be corrupted and cannot be opened or viewed. We would appreciate it if you could kindly resend the file or provide an alternative download link at your earliest convenience to enable us to review the electrical drawings and proceed with our proposal preparation.Response: Ammendment# 1 has been published to replace the corrupted document named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station" with a correct version named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station - Updated". Kindly check the documents tab for the corrected document.Clarificaion# 2: Regarding the electrical drawing details, we would like to inform you that the electrical drawings for the mini-grid solar station are corrupted. Specifically, the words, legends, and figures appear distorted and have turned into random numbers and unreadable symbols/signs.Response: Ammendment# 1 has been published to replace the corrupted document named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station" with a correct version named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station - Updated". Kindly check the documents tab for the corrected document.Clarification# 3: With reference to the attached document “Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station.pdf,” we have noticed some typographical errors and unclear text in the drawings. We kindly request you to review the attached document and provide a corrected and clearer version, if applicable.Response: Ammendment# 1 has been published to replace the corrupted document named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station" with a correct version named "Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station - Updated". Kindly check the documents tab for the corrected document.
Tender Value
Refer Docs
Bid Security (EMD)
Refer Docs
Closing Date
29 Nov 2026, 07:00 (UTC)7d left29 Nov 2026, 12:30 pm IST
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Provision of a Mini-Grid Power Station with Battery Energy Storage for Husswain – Al-Mahrah ----------------------------- IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides Interested in improving your knowledge of what UNOPS procures, how we procure and how to become a vendor to supply to our organization? Learn more about our free online course on “Doing business with UNOPS” here
320100
RFQ/2026/65288
Request for quotation
Yemen
RFQ
UTC
21 Nov 2026
28 Oct 2026
Number of Male Employee
Number of Female Employee
BoQ Item related description.
Lump sum.
Millimeter.
Centimeter.
Linear meter.
Square meter.
Cubic meter.
Number.
Piece.
Package.
Groups of related Items.
Kilogram.
Metric Ton.
Reference.
System.
Groups of related Items.
Kilogram.
Metric Ton.
Reference.
System.
Description
EXCAVATION AND EARTH WORK
Site Preparation Works for PV site: Site leveling and preparation: Survey works and Leveling works for the entire PV site by excavating and cutting high areas, Backfilling including compaction, removing obstacles and others, compacting the subgrade layer up to 95% compaction, opening and building a retaining wall as required to hold the soil as well as providing a minimum of 1% drainage slope and do everything necessary to finish the item (The contractor must visit the site before pricing, watches the site and determine the locations of current site, Obstacles to be demolished and removed, any prevent things for construction, evaluate the costs of all required for site preparation. according to specifications, drawings, section levels and instructions of the supervisor engineer). The work include the creartion of deversion line for drainage from the upper streams. The site preperation shall include cut and fill using the same site materials and disposal of dipress. The leveling should be carried out to the level specified levels in the sections
PV Area Backfilling Soil Materials: Backfilling including provison of borrowed subgrade materials for the 10cm finishing ground compacting the subgrade layer up to 95% compaction, opening and building a retaining wall as required to hold the soil as well as providing a minimum of 1% drainage slope and do everything necessary to finish the item. according to specifications, drawings and instructions of the supervisor engineer). The site preperation shall include cut and as described under the specification section 2.4 PV Area Backfilling Soil Materials and 3.6 Subgrade Material The backfilling should be carried out to the levels of finished ground surface
Site Gravel Backfilling : Supply and backfill a layer of Gravel size 0.5 inch to the sourounding area of the transformers and BESS with a thickness not less than 10cm after compacting and leveling the site and layer of 2cm as stips on the lower edges of solar PVs. The price include all required as per the technical requirements and the instruction of UNOPS engineers
Solar PV Mounting structure:
Ground Mounting Structure
The Contractor has to submit Detailed Shop Drawings to be approved by the Engineer before the commencement of the work, and all required materials should be supplied as specified and subject to the Engineer approval. - All works shall be done according to the Engineer's instructions, Drawings, and attached specification. - The Contractor should include in his price the costs of sampling and testing as required and according to technical specifications and a work requirement. - Benchmark and leveling network shall be approved prior to starting next works. - The locations of the building's columns/Beams shall be stakeout by the professional way (such as a total station) as per drawings . - This work prepared to cover 8 solar panels (2384mm x 1303mm) for each span approximately. - Measurement will apply to the outline of panels for top framing plan (level of solar panels),the payable area includes the projected parts of the solar panels
SSECURITY FENCE WORKS FOR THE PV AREA AND FACILITY AREA :
Security Fence Works: Supply and install Chain Link Metal Fence with Barbed wires as per in the drawings and the technical specifications, the work includes the following: • Survey and conduct all site settlement and levelling such as cut and backfill in any type of soil, and clear all planned areas for the work from materials, debris, chairs and disposal of debris to authorized area prior to the commencing of work. • Provide materials and construction of 2.50-meter-high chain Link Fence made from hot dip galvanized coated with pvc coated Post that shall be embedded in concrete footings and pressed at end. The panels width is 3 meter. The chain link comprise 50mmx50mm openings. the work includes installing of three lines of Barbed Wires above. • Provide materials and construction of 3m wide double leaf gate as shown on the drawings and according to the technical specifications and instructions of the supervising Engineer.
Light reinforeced concrete curb Supply and Cast a 20x30cm concrete curb paraemeter using concrete C35 and using wire mesh of to resist the shrinkage cracks as shown on the drawings and according to the technical specifications and instructions of the supervising Engineer. the work include formwork, placing, vibrating, shuttering, curing, cutting, bending and fixing in position and providing all tying wires, spacers. The price includes surface leveling, boulder layer and exavation as well as making sharp soft edges, all surface finishing and painting of exposed surfaces of underground reinforced concrete elements with two coats of water proof painting the strokes of each layer to be opposite to each other according to shop drawings, technical specifications and the instructions of Engineer in charge.
Stone masonry walls Building
EARTH WORK
Stone masonry for the walls and the channels
JOUM STONE. Supply and casting (Joum) concrete consists of ( 60% sound rubbles - 40% concrete, minimum compression strength of 25MPA at 28 days ) under exterior plainth beams. The work and price include providing all required materials of high quality ( cement, sand, aggregate, and whatever), frameworks, workmanship, curing, and doing all it needs and takes to finish the work according to the technical rules, drawings, and the engineer's instructions.
STRIPE STONE WALLS. Supply and Build base black "BASILTE" stone depth under the exteior fence ''where needed ,with cement mortar 1:3 and 1:2:4 concrete filling mix . Texturing shall be in accordance with Engineer’s instructions and approval. Cutting, shaping and building of stone shall be in straight angles (rectangular) , no twisting, distortion or uneven sizes shall be allowed. The price included any work to finish work as per shop drawings, specifications and the instructions of superving Engineer.
JOUM STONE for Ramps and Cutoff wall Supply and casting (Joum) cyclopean concrete consists of ( 30% sound rubbles - 70% concrete, minimum compression strength of 25MPA at 28 days ) under exterior gate ramps and end of RipRap channel. The work and price include providing all required materials of high quality ( cement, sand, aggregate, and whatever), frameworks, workmanship, curing, and doing all it needs and takes to finish the work according to the technical rules, drawings, and the engineer's instructions.
Reinforced concrete works for Gates Ramps. Supply and cast reinforced concrete class(C35) including formwork, placing, vibrating, shuttering, curing, complete as directed. The price includes Supplying reinforcement of (Grade 40), size and length as detailed in the drawings, storing on site including cutting, bending and fixing in position and providing all tying wires, spacers. The price includes surface leveling, making good the harmed surfaces and edges, all surface finishing and painting of exposed surfaces of underground reinforced concrete elements with two coats of hot bituminous paint (75/25) the strokes of each layer to be opposite to each other according to shop drawings, technical specifications and the instructions of Engineer in charge.
Stone Masonry Riprap Channel Lining Supply and build stone masonry riprap lining for open drainage channel using approved black basalt stone or equivalent, hard, durable, sound, and free from cracks, seams, and weathering, laid in cement mortar 1:3 first class, on a prepared and approved subgrade/filter layer. Stone size shall be minimum 0.35 m or as per approved design, well graded and clean. Channel geometry shall be bottom width 1.00 m, side slopes 1V:1.732H (150°), total depth 0.35 m. Stones shall be placed and hand-set to true lines and levels, with joints filled with mortar, pointed, and cured. Texturing and finish shall be in accordance with Engineer’s instructions and approval. Cutting, shaping, and building of stone shall be in straight angles; no twisting, distortion, or uneven sizes shall be allowed. the price including placing of 0.15 m thick gravel filter layer beneath the riprap lining, using approved graded gravel, compacted and levelled to the required lines and levels. Any excavated material disposal, dewatering, or temporary works should be covered under the unit price of the items. The price shall include all labour, materials, tools, scaffolding, curing, wastage, overheads, profit, and any work necessary to finish the work as per workmanship recommendations and approved drawings.
CONTAINERS FOUNDATIONS
Excavation Excavation in any any kind of material soft soil and rock to the design level , the price to include backfill, compact and disposal the surplus mterial outsite, in accordance with the technical specification and the engineer approval FOR the containers foundaions. All sites to be occupied by permanent construction or embankments shall be cleared of all logs, trees, roots, brush, tree trimmings, and other objectionable materials and debris. All waste materials shall be removed from the site and disposed of by and at the expense of the Contractor in accordance with technical specification and for the approval of engineer.
Compacted Base coarse Layer supply and place Compacted sub-base gravel/hardcore stons layer of 15 cm thick for site walk as shown in drawings, technical specification and for the approval of engineer.
JOUM STONE. Supply and casting (Joum) Boulder masonry consists of ( 60% sound rubbles - 40% concrete, minimum compression strength of 21MPA at 28 days ) under exterior plainth beams. The work and price include providing all required materials of high quality ( cement, sand, aggregate, and whatever), frameworks, workmanship, curing, and doing all it needs and takes to finish the work according to the technical rules, drawings, and the engineer's instructions.
Plain Concrete works: Supply and place plain concrete class (15) for the containers 10 cm thickness and under foundation, as shown in drawings, specification and for the approval of engineer
Reinforced Concrete works: Supply and place reinforced cast in place concrete (Readymix) Class C35 (with O.P. Cement ), including formwork, steel reinforcement bars grad 40 . as shown in drawings, technical specification and to the aaproval of engineer for the containers foundations
Monitoring ROOM 5.4*7
Strip Joam Stone Works. Supply and Laying, spreading and compacting well graded stone in layers not exceeding 25cm, including spreading in uniform thickness, hand picking, watering and compacting to the required density, leveling, and finish the surface. Payment shall be made for the measurement of the volume of the compacted fill.
Base Stone Works. Supply and Build base black "BASILTE" stone to cover the ground beams with cement mortar 1:3in first class and first. Texturing shall be in accordance with Engineer’s instructions and approval. Cutting, shaping and building of stone shall be in straight angles, no twisting, distortion or uneven sizes shall be allowed. The price included any work to finish work as per workmanship recommendations.
Cement Block Works. Supply and build concrete hollow blocks (40x20x20) cm (Automatic) for external walls with all required works. Prices of block works shall include supply of automatic solid concrete blocks from v. good and approved factory in perfect dimension and build it in good manner, cement sand mortar (1:3). Works shall include all materials, testing, scaffolds, placing of approval blocks, curing, racking out the joints, workmanship, all ducts, sleeves, opening areas, fiber board, protection concrete(B-200) around sleeve sand pipes for electrical tools and anywhere else, needed, all according to drawings, conditions and directed instructions by the Engineer. The price includes installing concrete R.C LINTEL with reinforcement above door and windows. Fcu = 25 Mpa, the length shall extend 15cm on both sides.
CONCRETE WORKs
Isolate foundation and pedestal. item include 10cm plain concrete under RC footing. The work inclueds painting two coats of water proofing bituminous for foundation surfaces.
Ground beams.
Internal room floor slab (must be levelled and smoothed by Troweling Machine). The item inclueds ployethylene sheet under RC floor.
Columns.
Roof solid slab.
INSULATION WORKS. Supply and install roof water proofing membrane of bitumen rolls 4mm thick covered with quartz granules for main roof, parapet walls and primer coat GS at rate 25 kg/m2 installation of 15x15cm angle fillet 474 groove, groove sealant, groove cover, joints over lapping, backing sheets or pieces all around external roof drains, the work include installation of PVC drainage pipes from the roof to the ground and all necessary material to complete the works as shown in the drawings and as per manufacture instructions and codes of practice.
SCREED CONCRETE WORKS Supply and cast concrete screed slab class(C35) 12 cm average thick including formwork, placing, vibrating, shuttering, curing, complete as directed. The price include surface leveling, making good the harmed surfaces and edges and all surface finishing according to workmanship recommendations.
EXTERNAL PLASTERING WORKS Supply and make external plastering 20 mm thick for walls with four faces: the first is the rough nail rendering (mix 1:1) cement: sand, the second is 5mm thick mortar (mix1: 2) cement: sand, the third is the undercoat 13mm (mix 1: 3) cement: sand, the forth is make Finishing Coat, smooth surface with (1:1) cement: sand mortar. and all this is according to drawings and supervisor engineer's instructions
INTERNAL PLASTERING WORKS Supply and make internal plastering 12 mm thick for internal walls and ceiling with two faces: the first is the rough nail rendering (mix 1:1) cement: sand second layer 13mm: Base‐Coat "Rendering" with (1:3) cement: sand mortar. Works include all materials needed to finish the works according to drawings and supervisor engineer's instructions.
PAINTING WORKs
Supply and apply oil paint (High Quality) for internal walls (2 coats). The works include supply and install:_ Substrate preparation, cleaning surfaces of dust, dirt, stuck, ... Etc,, priming, puttying 2 faces and polishing.The rate includes all material, equipments, labor, .etc, and doing every temporary or Permanent necessaries to finish the item as per standards, specifications and instruction of Engineer in charge.
Supply and apply weather resistant Paint (High Quality) for external Plaster (2 coats). The works include supply and install:_ Substrate preparation, cleaning surfaces of dust, dirt, stuck, ... Etc. priming The rate includes all material, equipments, labor, .etc, and doing every temporary or Permanent necessaries to finish the item as per standards, specifications and instruction of Engineer in charge.
Supply and apply water-based paint for ceiling (2 coats) The works include supply and install:_ Substrate preparation, cleaning surfaces of dust, dirt, stuck, ... Etc,, priming, puttying 2 faces and polishing.The rate includes all material, equipments, labor, .etc, and doing every temporary or Permanent necessaries to finish the item as per standards, specifications and instruction of Engineer in charge.
TilingWORKs
Porcelain Floor tiles. Providing and laying porcelain flooring tiles (40x40) ( high quality, approved by the engineer ) for rooms, offices, and the hall. The work and price include, supplying and preparing sand bed ,installing tiles accurately on a layer of cement mortar (1cement: 3sand) not less than 3 cm thick., grouting and finishing properly, and doing all it needs to finish the work according to the technical rules and the engineer's instructions.
Porcelain Skirting. Supply and installation of porcelain skirting for walls , 10 cm height ( high quality, approved by the engineer ). The work and price include, preparing the surface properly, installing tiles accurately on a layer of cement mortar (1cement: 3sand ), grouting and finishing properly, and doing all it takes and needs to finish the work according to the technical rules and the engineer's instructions.
Bathroom walls. Supply and install glazed wall tiles (first class) size 30x45x0.8 cm for bathrooms walls. The tiles shall be laid and fixed to the walls by approved bonding agents. Price includes cost of surface preparation to receive tiles, which shall include two coats of cement plaster (scratch and float coat) and approved adhesive materials, accessories and grounding. Color of the tiles shall be as chosen by the Engineer. All work should be done according to Specifications and instructions of the Engineer.
STEEL, WOOD AND ALUMINUM WORKS
DOOR WORK Supply, fix and install single external steel door size (2x1.2m) made out steel tubes adjoining vertically without space (tube 50x50x1.25 mm), complete with frame (L section 50x50x0.4), item includes all accessories, handles, locks, hinges and all required accessories according to the instructions of supervisor Engineer.
Spiral steel stair. Supply and install spiral steel stair, item include 15cm dia cylinder tube column 6mm thick, HELICOIDAL RAILINGS minimum ∅3cm cylinder tube (RSH) 2mm thick, 2mm steel nail sheet for raisers. The price includes (60x60x60cm) RC footing,30x30cm base plate, pedestal. The work also includes fabricating, welding, painting and all accessories. All according to design drawings, specifications and the instructions of UNOPS Engineer.
Aluminum sliding windows. Supply and install the Wood-Look Aluminum sliding windows for the room, 1.25 mm section thickness. The price includes all accessories ( frames, glass 6mm thick, locks, handles, rubber, fly screen with frames, and etc.), fixing with anti-rust screws, sealing with silicone properly, and doing all it needs and takes to finish the work according to shop drawings, technical rules and the engineer's instructions and satisfaction.
One-leaf Aluminum door. Supply, fix, and install one-leaf Wood-Look Aluminum door for bathrooms door, size (0.8x2.0m), item include Wood-Look Aluminum sheet all accessories, handles, locks, hinges, rubber, fiberglass 4 mm. thick., with all required sealants, accessories and hard ware as per the instructions of supervising Engineer.
PERIMETER SIDE WALK WORKS The Perimeter side walk shall have a minimum width of 100 cm and construct from concrete Curbs 50 cm height with buried 20 cm. filled in layers with good compacting. The top surface of side walk shall cover with plain concrete 10cm thick the surface of concrete must be levelled and smoothed. The price inclueds a layer of crushed stones under the plain concrete. All according to the instructions of the Engineer.
Signboard
Plumping Works
Floor Drain. Supply, install, testing and commissioning of, 4" stainless steel plated threaded 15x15cm cast brass cover, multi inlet adjustable with trap floor drain. Including, floor clean out plug, HDPE/UPCV siphon and necessary accessories, connections with fixtures and main drain pipes. The item includes all drainage piping to manholes (4 in UPVS 5.2 mm thick) as per drawings, specifications and related codes.
Squatting /Arabic Toilet/Pan. Supply, install, testing and commissioning of, floor ceramic arabic toilet pan, white color, siphon, plastic WC cisterns including necessary accessories, 13-lt capacity cistern, S-trap elbow, valves, fittings, 13mm stop angle valves, chrome plated 13mm hose includes all supply piping from the source (PN16 bar CPVC piping and fittings 3/4 in) and drainage piping to manholes (4 in UPVS 5.2 mm thick) as per drawings, specifications and related codes
Hand-held bidet sprayer with faucet. Supply, install, testing and commissioning of faucet and brass hand held bidet spray shattaf with holder (Italian or equivalent) including quick shut-off valves, nipples, nuts, unions, brass fitting adapters. This item shall also include the complete supply line from the water source, consisting of PN16 bar CPVC piping and fittings, 3/4 inch, with a reinforced plastic or galvanized metal UV-resistant protective sheath for all sections exposed to direct sunlight, with a diameter matching the pipe size.
Hand Wash Basin. Supply and install ceramic hand wash basin for bathrooms white color. The item includes all drainage piping (2 in UPVS 3.2 mm thick)to the nearest floor trap. Complete with elbows, fitting, drop trap, flexible connections and necessary drainage connection.
Hot and Cold Hand Wash Basin Mixer Faucet. Supply, install, connect, testing and commissioning of, hot and cold water 3/4" collectors, Inlets/ Outlets quick shut-off valves, record valves, nipples, nuts, unions, brass fitting adapters. This item shall also include the complete supply line from the water source, consisting of PN16 bar CPVC piping and fittings, 3/4 inch, with a reinforced plastic or galvanized metal UV-resistant protective sheath for all sections exposed to direct sunlight, with a diameter matching the pipe size.
Hot and Cold Wall Mounted Bath Shower Mixer Tap & Shower. Supply, install, connect, testing and commissioning of, hot and cold water wall mounted bath shower mixer tap & shower, high quality, quick shut-off valves, record valves, nipples, nuts, unions, brass fitting adapters. This item shall also include the complete supply line from the water source, consisting of PN16 bar CPVC piping and fittings, 3/4 inch, with a reinforced plastic or galvanized metal UV-resistant protective sheath for all sections exposed to direct sunlight, with a diameter matching the pipe size.
Water Tank Storage. Supply and install plastic/fiber glass (three layers) water storage tank, 2.0 m³ capacity, complete with lockable cover, cleaning opening with 3/4" dia. plug, overflow pipe 3/4" dia., and steel base. This item includes all required works and materials for connection pipes to distribution lines using PN16 bar CPVC piping and fittings 3/4 in, to ensure full and healthy operation, in accordance with the specifications and instructions of the Engineer. The item also includes the supply and installation of all necessary connections and accessories for the filling point, including: Non-return valve Isolation valve Suitable filling coupling All related civil and mechanical works according to approved specifications. All CPVC pipes installed on the rooftop and exposed to sunlight shall be protected with UV-resistant plastic or metal sheathing. All hot water lines shall be insulated using closed-cell elastomeric thermal insulation (minimum 13 mm thickness).
Sewerage Manhole. Supply installation & construction of Inspection 60 x 60 cm. manholes with Plain Concrete base and 200 mm thick concrete solid block walls 20x20x40cm and ductile cast iron frame and hinged cover including excavation, disposal of surplus earth, fittings, testing, cement rendering and back filling as per drawings and specification. The price includes connections to the existing network.
UPVC Waste Drainage Pipes. Supply, install, testing and commissioning of the UPVC (5.5mm Thickness) 6-inch waste water drainage including, pipe fittings, connection to drainage system manholes, required sleeves and all necessary accessories as per drawings, specifications and related codes.
UNDERGROUND SEWAGE SOAKAGE TANK
EARTHWORKS
Excavation works. Excavation in any kind of soil and rock, starting at natural ground levels to final excavations level including any necessary protection works to the excavation (if required) stockpiling of suitable backfill materials and removal of unsuitable materials to approved dump area, complete as shown on drawings and as per specifications.
Fill Works: Filling with excavated material and/or imported fill material to achieve the required final levels, after improvement of the soils according to soils report and structural notes, all in layers, watered, rolled and compacted to reach not less than 90% of the dry density, complete in accordance to instructions in drawings and as per Engineers approval.
MASONARY WORKS:
JOUM STONE. Supply and casting (Joum)stone consists of ( 60% sound rubbles - 40% concrete, minimum compression strength of 25MPA at 28 days ) under exterior plainth beams. The work and price include providing all required materials of high quality ( cement, sand, aggregate, and whatever), frameworks, workmanship, curing, and doing all it needs and takes to finish the work according to the technical rules, drawings, and the engineer's instructions.
CONCRETE WORK.
Reinforced concrete roof: Supply, casting and finishing of reinforced cement concrete class(C25) minimum compressive strength of 25Mpa on cylinder test at 28 days, cement content not less than 350kg/m3 with suitable additives, for soakage pit roof using reinforcement of two layers 6ϕ16/m in each direction. The work includes providing all required materials of high quality and approved ( Steel, cement, sand, aggregate, water, etc.). Also, the price includes supply and installation of support pollywood and timbers, providing, all daimension and reinforecement is according to the drawings. the work also include supply and installation all fittings required, and doing all it takes and needs to finish works as per drawings, technical specifications and Engineer's instructions.
Precast Reinforced concrete Ring pipe: Supply, casting and finishing of pre-cast reinforced concrete ring pipes class(C25) minimum compressive strength of 25Mpa on cylinder test at 28 days, cement content not less than 350kg/m3 with suitable additives, for walls with minimum reinforcement of two layers ϕ10 @ 200 mm vertical and hoops of two layers ϕ10 @ 200 mm using Grade 40 steel bars. The work includes providing all required materials of high quality and approved ( Steel, cement, sand, aggregate, water, etc.). Also, the price includes supply and installation of a gravel layer around the ring pipes as per the drawings and casting of 30cm weidth ,10cm thichness of plain concrete under the bottom ring pipe , providing, all daimension and reinforecement is according to the drawings. the work also include supply, transportation and installation all pipes and fittings required, and doing all it takes and needs to finish works as per drawings, technical specifications and Engineer's instructions.
Description
Solar PV Modules:
Supply, install, test and commissioning of PV modules rated not less than 720 Wp, bifacial dual-glass (glass/glass), N-type HJT or N-type TOPCon, suitable for coastal and hot climate, complete with all accessories and as per Employer’s design and drawings. - System voltage: 1500 VDC. - Module efficiency: ≥ 23.0% or highest commercially available for the 720Wp class (supported by manufacturer datasheet). - Bifaciality factor (φPmax): ≥ 80%. - Power tolerance: 0 to +5 W. - Junction box and connectors: IP68 junction box with bypass diodes; Original MC4 or certified equivalent, UV-resistant cables. - Warranties: Product warranty ≥ 15 years., Performance warranty ≥ 30 years (linear) with end-of-warranty power not less than 87%. - Manufacturer: Tier-1 PV module manufacturer, with proven references and traceable serial numbers. - Scope includes: module supply, installation, testing and commissioning, labeling/serial tracking, lifting/handling, module-side connectors/cables, and all module-related accessories as required to deliver a complete working system as per Employer’s design.
String Inverters with Mounting Support and Concrete Foundation:
Supply, install, test, and commissioning of three-phase String inverter/PCS, min 300 kW, 800Vac, 50Hz, IP66, the work include the construction of the inverters mounting structure as per the manufacturer recommendation and not less than the minimum mounting structure requirements. minimum requirements as the following: A) PV input: - Max DC voltage: 1500VDC; Multiple MPPTs (≥ 6), allowing Minimum of 5 inputs per MPPT input as per design, Max. output power 330(kW), Rated power 300 (kW). - Max PV input current per MPPT: suitable for bifacial high-current modules (allowing 24-bifacial module strings). B) HYBRID SYSTEM INTEROPERABILITY: - SCR Compatibility for Weak Grid conditions, execution of Active Power curtailment commands from the MGC, compatible with the BESS "Grid-Forming" reference during the transition from Diesel-Hybrid to BESS-only modes - support high-speed slave unit under command from Microgrid controller to achieve P-f (Frequency-Watt) and Q-U (Volt-VAR) control to allow the BESS to act as the grid-forming master C) AC output: - Grid-forming capability: voltage/frequency regulation, black start, droop control, parallel operation of 8 units. - THD: < 1% at rated load; overload capability as per IEC. D) Protections and compliance: - Over/under voltage, over/under frequency, overcurrent, short-circuit, Fault Ride-Through (FRT) , Inertia Emulation, anti-islanding (where applicable), DC insulation monitoring, RCMU. -Smart String-level Disconnection (SSLD), Smart Connector-level Detection (SCLD) - Standards: IEC 62109, IEC 62477, IEC 61000 (EMC). - DC SPD Type II at each PV String inverter (Ucpv ≥ 1500VDC). - SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB. provided that it delivers equivalent protection functionality and meets the required technical performance, safety standards, and applicable specifications E) Monitoring and communications: HMI display; data logging; Ethernet; Modbus TCP/RTU; dry contacts; remote monitoring. F) Mounting Support: the work include the construction of RC foundation (1.5x1.0x0.2m) with the minimum two layers top and bottom of 5Dia8/m in each direction and installation and provision of 2 steel column of C80x40x3mm and fixing to the foundation using 4x12mm anchorbolts via baseplate 100x100x8mm. all bolts are Dia 12mm A320 or equavelent. The work include fixixng unistrait 40x40x3mm adjustable as per the dimension of the inverter. The wor include the coating of the steel framework as per minimum coating requirements of the steel mounting structure G) Warranty: ≥ 5 years.
Battery Energy Storage System (BESS) - Containerized:
Supply, deliver, install Battery Energy Storage System (BESS) - Containerized,all in one or two, including Lithium battery, containers, cabinet/rack, Power Conversion System (PCS), Energy Management System (EMS), Auxiliary power system, HVAC, Fire detection and alarm system, fire protection system, cabling system, and every things to complete the work. Minimum requirements:
1x 20HQ container modified for BESS application, including certification. Minimum requirements: - ISO 20HQ container, CSC plate, wind/stacking certified. - Anti-corrosion coating suitable for coastal environment (C5-M), internal anti-condensation coating. - Thermal insulation (walls/roof), fire-rated internal lining as applicable. - Raised anti-slip floor, cable entry glands, drainage. - Doors with panic release, access control provisions. - Internal lighting (LED), emergency light, sockets, earthing bar. - Signage, safety labels, emergency stop push buttons (inside/outside). Includes transport, lifting, placement on foundation, and all modifications per design. The work including all Civil works such as: concrete foundations/plinths for containers, with anchor bolts and cable entry sleeves, cable trenching/duct banks, backfilling, compaction, warning tapes.
HV Lithium battery energy storage unit. Minimum requirements: - Chemistry: LFP (Lithium Iron Phosphate). - Total Nominal energy: min 3.8MWh. - Battery Cell: Grade A - Nominal system voltage: compatible with inverter HV battery range. - Built-in rack BMS with cell monitoring (V,T), balancing, alarms; communication to master BMS. - Cycle life: ≥ 6000 cycles @ 80% DoD (or better) with third-party report. - Operating temperature: -10°C to +50°C (with derating policy), storage -20°C to +55°C. - Safety: UL9540/IEC 62619 (or equivalent), integrated fuses/contactors, insulation monitoring. - Warranty: ≥ 10 years. Includes racks, internal busbars, power and communication cables, and all accessories.
Power Conversion System (PCS) - Bi-directional 1.9 MW inverter system with native microgrid intelligence. - Grid-Forming (GFM / Virtual Synchronous Machine) Mode (Primary Mode): Serves as the primary voltage and frequency reference (800 V,50 Hz) for the isolated mini-grid when operating without diesel generators. - Grid-Following (GFL) & Dynamic Droop Mode (Parallel/Charging State): one or both 1250 kVA diesel generators are running and master the 11 kV/0.8 kV bus, the PCS seamlessly switches or operates in dynamic P-f/Q-U droop mode to share real and reactive load or absorb surplus solar energy. - Controlled Soft-Start & Transformer Energization: Capable of black-starting the local 7 MVA (0.8/11 kV) step-up transformer and 11 kV OHL feeder from a de-energized state, voltage Ramp Control: Soft-ramps output AC voltage from 0 V to 800 V over a configurable window (1 s-10 s) to eliminate transformer magnetizing inrush currents and prevent over-current trips. - Hardware Reverse Power Protection: Coordinates with MGC control logic to enforce active power flow limits at the 0.8 kV switchgear, preventing unauthorized reverse power flow into running diesel generator sets (protecting directional power relays, ANSI 32) - Reverse Power Inhibition: Prevents exporting power to the 11kV bus when the Diesel Generator is the sole grid-forming source. - SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB.
Battery HV combiner / DC distribution cabinet. Minimum requirements: - Rated DC voltage: ≥ 1500VDC; rated current as per system design. - DC main disconnect, pre-charge, contactors, fuses, shunt, and isolation monitoring. - Individual battery string protection (if applicable) and measurement points. - Emergency shutdown interface. - DC SPD Type II at each PV String inverter, BESS (Ucpv ≥ 1500VDC). - IP rating suitable for container indoor; arc-flash warning labels. Includes all busbars,cables, terminals, and integration with inverter/PCS.
Energy Management System (EMS) for BESS microgrid operation. Minimum functions: - Modes: SoC and Health Optimization, Active Balancing, Solar Smoothing, Thermal Logic - Microgrid Operational Coordination & Dispatch Logic: - Nighttime Discharge Operational Logic (20% SoC Threshold):During nighttime operation, the BESS operates as the primary Grid-Forming power source, supplying 100% of the mini-grid load demand while the diesel generators remain shut down. When BESS SoC decays to 20%, the MGC initiates a signal over the OPGW link to auto-start, warm up, synchronize, and close the 400 V breakers of one or both 1250 kVA diesel generators at the powerhouse. Once synchronized, load is seamlessly transferred from the BESS to the diesel generators, and the BESS transitions to standby or controlled charging mode. - Daytime Solar Surplus Charge Management: During daytime hours, excess solar energy beyond load demand is automatically routed to charge the BESS up to 90%" SoC" . Charging power ramps dynamically to prevent abrupt load changes on running engines when diesel generators are operating in parallel during cloudy conditions. - Minimum Engine Load Protection (Anti-Wet Stacking): If solar generation causes net demand on running diesel engines to drop below 30% of rated capacity, the BESS increases charging power to absorb excess PV generation, maintaining diesel engine loadings above wet-stacking thresholds. - Fast Frequency Response (FFR): During sudden frequency deviations (>0.5 Hz ), the BESS delivers an active power injection burst within ≤50 ms to arrest frequency decay (df/dt). - Load shedding signals to BMS/building system: critical/non-critical priority commands. - SOC management, battery cycling limits, alarms. - Interfaces: Modbus TCP/RTU, IEC 61850 optional; API/export. - Local HMI and remote monitoring portal. Includes SCADA gateway, network switch, and data logger.
Auxiliary power system for BESS containers including: - AC auxiliary distribution board, breakers, sockets. - DC control power supply/UPS (24/48/110V) to support controls, BMS, EMS, communications for minimum 4 hours. - Battery chargers and power supplies. Includes wiring, labeling, testing.
Container Liquid Cooling System (Water/Glycol) for BESS thermal management. Minimum requirements: - Liquid Cooling System (Water/Glycol): a closed-loop system where a coolant (typically a 50/50 water-ethylene glycol mixture) is circulated through cold plates in direct contact with the battery modules. - N+1 redundancy per container (at least 2 units/container). - Cooling capacity sized for battery + inverter losses and coastal ambient conditions. - Industrial duty, corrosion-protected condenser, high-efficiency filters. - Temperature setpoint control and alarms integrated with EMS/BMS. - Operating ambient: up to 48°C. Includes refrigerant piping, supports, and commissioning.
Ventilation system for BESS containers. Includes fresh air intake, exhaust fans, louvers, motorized dampers, and smoke purge mode. - Fans corrosion-resistant; noise and vibration control. - Interlocked with fire system and EMS.
Fire detection and alarm system for each BESS container. Minimum requirements: - Addressable fire alarm panel (or loop extension from main panel) with battery backup. - Smoke detectors + heat detectors as required; manual call points; sounder/strobe. - Integration: HVAC shutdown, ventilation control, E-stop, alarms to EMS. - Standards: NFPA 72 / EN54 (or equivalent).
Clean agent fire suppression system for each BESS container. Minimum requirements: - Agent: Novec 1230 (FK-5-1-12) or equivalent clean agent suitable for energized equipment. - Automatic release with pre-discharge alarm and abort switch. - Discharge nozzles and cylinders sized for container volume. - Standards: NFPA 2001 / ISO 14520 (or equivalent). Includes cylinder mounting, piping, pressure switches, and testing.
Gas detection system for each BESS container. - Sensors for smoke/thermal runaway gases (e.g., CO, H2, VOC as applicable), with alarms and outputs to EMS and fire system. - Industrial grade, calibrated, with local display and relay outputs.
Complete communication and monitoring cabling system. - Industrial Ethernet network (CAT7A / fiber as required), patch panels, RJ45 connectors. - RS485/Modbus shielded twisted pair for BMS/EMS/combiner communications. - All cables in trays/conduits with labels and ferrules. Includes testing and commissioning.
CABLES: - Inverter to AC combiner panel cable. - Auxiliary power AC cabling inside containers (lighting, sockets, HVAC feeds). - Power and communication cables.
Supply, deliver, install Battery Energy Storage System (BESS) - Containerized, all in one or two, including 3.8 MWh Lithium battery, containers, cabinet/rack, Power Conversion System (PCS), Energy Management System (EMS), Battery Management System (BMS), Auxiliary power system, HVAC, Fire detection and alarm system, fire protection system, cabling system, and every things to complete the work.
Micro-Grid Controller (MGC) and Energy Management System (EMS)
Micro-Grid Controller (MGC) and Energy Management System (EMS): CORE CONTROL FUNCTIONS: - Grid-Monitoring and LV-Coupled Synchronization and Vector Matching - Energy Management : Peak Shaving, Self-Consumption Optimization, Active/Reactive Power Management, Renewable Smoothing - Bidirectional Active Front End (AFE) Control: Active Rectification Management, Generator-to-Battery Charging - Black Start Management: Master Designation, Dynamic Reference Transition - DYNAMIC CHARGE MANAGEMENT (GENERATOR EXPORT LIMITING): Real-Time Throttling, Reverse Power Prevention, Minimum Load Management - Control Logic and String Inverter Management : Dynamic Setpoint Dispatch, Active Rectification Control, Solar Smoothing - TRANSIENT FUNCTIONS: Fast Frequency Response (FFR) and Inertia Emulation, Bidirectional Protection Logic
AUTOMATIC WEATHER STATION (AWS) - Cloud Anticipation: The MGC shall use real-time Global Horizontal Irradiance (GHI) from the Class A Pyranometer to pre-position BESS or DG capacity before a detected cloud bank reduces PV output. - Sensors: The station must include a Thermopile Pyranometer, Ultrasonic Anemometer, and Ambient/Module Temperature Sensors.
SCADA SYSTEM - SCADA System and Human Machine Interface: - HMI: 15-inch touchscreen HMI. The interface must provide a real-time Single Line Diagram (SLD) of the micro-grid and support historical trending , - System Monitoring: provide deep-level monitoring across all assets (String Inverters, BESS, Diesel Generator, MV remote RMU and LV Switchgear) - Remote Access and Telemetry: Connectivity through both GSM and LAN networks, Web Portal access for at least 10 years, accompanied by supporting documentation from the vendor. - Auxiliary Power Supply (UPS)must feature a 1 kWh battery storage capacity and a minimum 1000W power rating.
Communication System Protocol: IEC 61850 (Station Bus) for high-speed protection; Modbus TCP/IP for power metering and BESS monitoring. Topology: Star or Ring Topology using industrial-grade fiber optic switches. MGC to Inverters/BESS: High-speed Ethernet (Fiber). MGC to LV Switchgear/Transformer: Serial RS485 or Ethernet via RTU. Latency: Critical control loops must have a latency of < 20ms. Topology: A Fiber Optic Ring utilizing Rapid Spanning Tree Protocol (RSTP) to ensure zero-millisecond recovery in the event of a cable fault. Protocol Hierarchy: High-speed IEC 61850 (GOOSE) shall be used for FFR and protection commands (< 40ms), while Modbus TCP is used for data logging and AWS monitoring. Redundancy: Dual-redundant managed switches rated for C5-M coastal environments and temperatures up to +70℃.
Supply, Installation, and Commissioning of a high-speed Microgrid Controller (MGC) / Energy Management System (EMS), AUTOMATIC WEATHER STATION (AWS), SCADA System and Human Machine Interface, Auxiliary Power Supply and Communication System. The MGC shall provide centralized coordination of Distributed Energy Resources (DERs) to ensure system stability, power quality, and economic optimization.
Containerized Integrated 7 MVA Transformer Station (TS) and LV Switchgear
7 MVA with flexibility of 30% over Step-Up Transformer : Rating: 7.0 MVA with flexibility of 30% over (Continuous Maximum Rating). Voltage Ratio: 11 kV (Medium Voltage) / 0.8 kV (Low Voltage). Cooling and Type: Oil-immersed with ONAN/ONAF cooling. Vector Group: Dyn11 (Standard for micro-grids to allow neutral grounding on the LV side). Winding Material: High-grade electrolytic copper with Class A (105°C) insulation. Impedance: 7% at 75°C. Core: High-grade, grain-oriented silicon steel with mitred joints for low noise and minimal no-load losses. Tap Changer: Off-Circuit Tap Changer (OCTC) with a range of ±2 × 2.5%. Protection Devices: Buchholz relay (double-float), Magnetic Oil Level Gauge (MOG), Pressure Relief Device (PRD), and DGPT (Detection of Gas, Pressure, and Temperature). Conservator: Sized for expansion from -5 ℃ to +100 ℃; includes a silica gel breather and sump for sludge. Valves: Tinned brass or stainless steel; includes drain, filter, and oil sampling valves. Winding: Electrolytic copper, paper-insulated, designed for high short-circuit strength. Bushings: Outdoor porcelain or resin-molded; 12kV (MV) and 1.1kV (LV) ratings.
0.8 kV LV Switchgear - Rating: 0.8KV, 6300A, 50Hz. - Busbars: Tinned high-conductivity copper, rated for 1.25 of Circuit breaker rated current 6300A continuous and 50kA (1 sec) short circuit. - Circuit Breakers: Breakers: Vacuum (VCB)/Air withdrawable Circuit Breakers (ACB) with motorized mechanisms (1x6300A, ACBs), (1x63A 3-Pole MCCB), (15 x 400 A, 4-pole MCCBs) and (10 x 250 A, 4-pole MCCBs), Draw-out type. - Mechanism: Motorized spring-charged with shunt trip and under-voltage release. - Protection: Integrated microprocessor trip units with LSIG (Long-time, Short-time, Instantaneous, Ground fault) functionality. - Multifunction Meter: digital device that measures, monitors, and displays multiple electrical parameters—such as voltage, current, power, energy, and frequency - Safety: Internal arc classification and mechanical interlocks to prevent breaker movement while in the "ON" position. - SPD: Integrated Class I+II (Type 1+2) Surge Protective Devices located after the main ACB/VCB.
Auxiliary power system for 0.8LV Switchgear containers including: - AC auxiliary distribution board, breakers, sockets. - DC control power supply/UPS (220V) to support controls, protection, communications for minimum 4 hours. - Battery chargers and power supplies. Includes wiring, labeling, testing.
Container 2Ton Air Conditioning units for 0.8LV Switchgear. Minimum requirements: - Cooling capacity sized for Switchgear losses and Coastal ambient conditions. - Industrial duty, corrosion-protected condenser, high-efficiency filters. - Temperature setpoint control and alarms integrated with EMS/BMS. - Operating ambient: up to 48°C. Includes refrigerant piping, supports, and commissioning.
Fire detection and alarm system for 0.8KV LV Switchgear container. Minimum requirements: - Addressable fire alarm panel (or loop extension from main panel) with battery backup. - Smoke detectors + heat detectors as required; manual call points; sounder/strobe. - Integration: HVAC shutdown, ventilation control, E-stop, alarms to EMS. - Standards: NFPA 72 / EN54 (or equivalent).
Complete communication and monitoring cabling system. - Industrial Ethernet network (CAT7A / fiber as required), patch panels, RJ45 connectors. - RS485/Modbus shielded twisted pair for Micro-Grid Controller, Multi-Functioning meters, Protection communications. - All cables in trays/conduits with labels and ferrules. Includes testing and commissioning.
CABLES: - 0.8 LV Switchgear to 7 MVA step-up Transformer. - Auxiliary power AC cabling inside containers (lighting, sockets, Air Conditioning units feeds). - Power and communication cables.
Supply, install, testing and commissioning of a factory-integrated, skid-mounted 7 MVA Transformer Station, Contrainerized 0.8KV LV Switchgear, Auxiliary power system, 2Ton Air Conditioning units, Fire detection and alarm, Complete communication and monitoring cabling system system, 0.8 KV Power Cable, AC Auxiliary power cable and Communication cable the work include all structural and site prepration work for the installation as per the munifacturer recommendation and approval by UNOPS engineer.
11KV Overhead line
11KV RING MAIN UNIT
General Design and Construction Nominal System Voltage 11 kV Nominal rated current 630A Short Circuit Level/Time 25 kA for 1 Second Basic Insulation Level (BIL) 75 kV Power Frequency Withstand 32 kV - Enclosure Type: Indoor, containerized mounted, metal-enclosed, single bus-bar type switchgear. - Environmental Protection: Minimum IP 66 rating per IEC 60529, with mechanisms protected against dust and moisture. - Configuration: Each RMU consists of two ring Vacuum/SF6 circuit breakers for incomers and one SF6 circuit breaker for the outgoing feeder. - Insulation and Interruption: Air-insulated stainless steel chamber for live parts/busbars; Vacuum or SF6 gas for fault interruption. - Climate Control: Panels must include humidity/moisture control elements activated by thermal switches. - Operating Mechanism and Safety: Operator Interface, Interlocks and Padlocking, Gas Monitoring, Withdraw ability (Inserted, Test (Isolated), Disconnected, and Removed) and Safety Shutters. - Operating Mechanism and Safety: Operator Interface,Interlocks and Padlocking, Gas Monitoring Withdraw ability (Inserted, Test (Isolated), Disconnected, and Removed), Safety Shutters. - Control and Protection System Control Supply: Redundant 110V DC supplies with an automatic/manual changeover scheme provided by the supplier. Auxiliary Power: 110V DC battery bank with 4-hour autonomy and integrated charger. Protection Relays: Programmable, microprocessor-based intelligent digital relays with self-diagnostics and LCD interfaces. Instrument Transformers: Standards Compliance with ANSI/IEEE C57.13 or NEMA ST 20, Accuracy of Minimum 1% accuracy for indicating instruments (0.2% for Tie-In Feeders). Design: Multi-wound type allowed; secondary windings must be grounded at a single point through a removable link.
Supply, install, test, and commission 1 Ton Refrigeration split air conditioner inverter type, including alternate operation and temperature control unit with all wiring requirements Two units will be used in duty mode and alternative mode. Rated Power Consumption: (240 – 2200W) · Rated Running Current: (4–12A). - Capacity: 12000 BTU; - Voltage: 220-240; - Frequency: 50 Hz; - Single phase; - Noise level shall not exceed 45 dB; - Star rating 3 stars or above; - Suitable for wall mounting; - The outdoor unit shall be housed inside a painted metal cage made of mild steel.
Fire detection and alarm system for 11KV Ring Main Unit container. Minimum requirements: - Addressable fire alarm panel (or loop extension from main panel) with battery backup. - Smoke detectors + heat detectors as required; manual call points; sounder/strobe. - Integration: HVAC shutdown, ventilation control, E-stop, alarms to EMS. - Standards: NFPA 72 / EN54 (or equivalent).
Supply, install, testing and commissioning of Contrainerized 11KV Ring Main Unit, Auxiliary power system, 1 Ton Air Conditioning units, Fire detection and alarm, Complete communication and monitoring cabling system system, Power Cable, AC Auxiliary power cable and Communication cable the work include all structural and site prepration work for the installation as per the munifacturer recommendation and approval by UNOPS engineer.
DC, AC, Control Cabling and Cable Tray:
DC Cabling:
Supply, install, test, and commissioning of DC cables, glands, trays, and terminations. - Conductor: stranded copper, tinned for marine/coastal environments. - Insulation: UV resistant, halogen-free, flame retardant; PV cables certified to EN 50618 / IEC 62930; 1000VDC. - Marking, identification, and ferrules as per IEC. - Cable trays: perforated galvanized steel (min G90) with covers, bends, tees, couplers and supports. - All terminations with correct lugs, crimping tools, and heat shrink.
PV string cable 1C x 6 mm² (Red & Black), 1500VDC PV cable, UV-resistant.
AC & Control Cabling:
Supply, installation, testing, and commissioning of (1.2 to 3 kV as per manufacturer recommendation of string inverters and other related equipment) single and multi-core armored copper AC power cables. The installation shall include all required corrosion-resistant glands, cleats, supports, and termination kits. All works must comply with the project specifications, site-specific drawings, and international codes of practice, ensuring suitability for continuous operation at 50°C ambient temperature. All of which shall be according to the specifications, drawings, codes of practice and highest prevailing engineering standards, for the following:
3x1Cx 120sqmm - CU/XLPE /STA /PVC + E=70sqmm.
3x1Cx300sqmm - CU/XLPE /STA /PVC + E=185sqmm.
3x 1Cx630sqmm - CU/XLPE /STA /PVC.
3Cx16sqmm - CU/XLPE /STA /PVC.
4Cx35sqmm - CU/XLPE /STA /PVC.
Supply, installation, testing, and commissioning of 11kV armored copper power cables featuring XLPE insulation and metallic screening. The scope includes all necessary MV-rated termination kits, corrosion-resistant supports, non-magnetic glands, and cleats. All works must comply with project specifications and international codes of practice, ensuring full thermal performance at 50°C ambient temperature and resistance to coastal atmospheric conditions. - 3x1Cx240sqmm - CU/XLPE /STA /PVC
Cable Tray:
Cable tray (10cm wide min height 5cm) with cover.
Cable Trench Excavation and backfilling
Type1: 100cmx60cm
Type2 : 60cm x45cm
Type3 : 65cm x 40 cm
Type4 : 40cm x40cm
Cable Trench Manholes
Typ1: 100 cmx100cm
Typ2: 60 cmx40cm
Typ3: 40 cmx40cm
Outdoor Solar Street Light
Supply, install and commission stand-alone solar street lighting all in one with built in battery and charge controller with Lightning poles include all related work as per detailed drawings.with below specification:- - 60W, 18V Mono-crystalline PV Module - 12VDC, more than 30Ah Li/Iron Battery - MPPT Charger, Lighting Controller with Multi-stage operation capability - More than 8000 Lm LED light with the required drive - Ingress protection: (IP65 or equivalent) or higher - Rigid frame and enclosure that withstand worst weather condition - Motion sensor - Product warranty should be at least 2 years.
Earthing System:
Supply, install, test and commissioning of complete earthing grid and bonding system for PV arrays, String inverters, BESS containers, 7MVA Transformer station with 0.8KV LV Switchgear, 11KV OHL. as per secifications and drawings Minimum requirements: - Earthing Grid Copper Conductor of minimum size 50 mm2 - Earthing Grid Depth: 0.5 Meter as per the specification and drawing - Earthing Grid Area: L: 280 m x W: 260 m - Earth electrodes/pits, copper conductors, bonding, clamps and couplers to all metallic parts. - Target earth resistance: ≤ 1 Ohm (or lower if required by Employer). - Exothermic welding or approved clamps; test links. - Compliance: IEC 60364-5-54 / BS 7671 / IEEE80. Includes earth testing with calibrated tester and reports. Earth resistance should be tested in presence of the UNOPS representative by calibrated earth tester, the earth resistance should not be more than 1 Ohm. Note: the item not includ the existing earthing pit, just to connect to them, and add earthing pit what ever you need.
Lightning Protection System:
Supply, install, test and commissioning of ESE lightning protection system for PV Area, BESS containers, 7MVA Transformer Station with 0.8KV LV Switchgear and 11KV Over head Line as per specification and drawings Minimum requirements: - Design per IEC 62305, NFC 17-102 (2011); ESE Lightning Rods with Efficiency (ΔT): 60 μs , down conductors, test joints, and earth termination. - Bonding with earthing system; separation distance maintained. - Includes risk assessment assumptions and as-built test records. - lightning protection materials per IEC 62305. - Down conductor copper 50 mm² with saddles/clamps, Test joints and bonding accessories.
Smart Metering System
Prepaid System: The contractor price include all the requirements include Hardwares/ Softwares of the system to reach complete and functioning system as per the manufacturer recommendations as per the technical specification.
Smart Prepayment Meters
Single Phase Smart Prepayment Meter Single Phase (2-wire) meter built on the Standard Transfer Specification (STS). Robust enough to withstand coastal and desert climate conditions, including high humidity and dust. Features Class 1.0 accuracy (Active Energy), minimum IP54 rating, and an integrated 80A/100A heavy-duty latching relay. Must include plug-and-play communication modules (GPRS/4G, NB-IoT, or RF-Mesh), anti-tamper mechanisms, an LCD with backlight, and a 12-button keypad.
Three Phase Smart Prepayment Meter Three Phase (4-wire) meter built on the Standard Transfer Specification (STS). Robust enough to withstand coastal and desert climate conditions, including high humidity and dust. Features Class 1.0 accuracy (Active Energy), minimum IP54 rating, and an integrated 80A/100A heavy-duty latching relay. Must include plug-and-play communication modules (GPRS/4G, NB-IoT, or RF-Mesh), anti-tamper mechanisms, an LCD with backlight, and a 12-button keypad.
Customer Interface Unit (CIU) keypad for indoor credit entry/monitoring via RF/PLC
Monitoring System and Billing Infrastructure
Data Concentrator Unit (DCU) / Communication Gateway DCUs utilizing RF-Mesh/PLC to bridge the smart meters to the cloud, to be installed at distribution transformer locations. Downlink Communication: Supports RF-Mesh (Sub-GHz) or PLC (Power Line Communication) for local meter connectivity. Uplink Communication: Quad-band 4G/LTE/GPRS with an Ethernet (RJ45) fallback. Capacity: Minimum support for 500 meter nodes per DCU. Memory & Storage: Non-volatile memory capable of storing 6 months of interval data for all connected meters in case of backhaul failure. Power Supply: Wide input range (100V–450V AC) with an internal supercapacitor or battery to provide a "Last Gasp" notification during a power outage. Ingress Protection: IP65 for outdoor pole-mounting.
Vending & Billing Platform Cloud-based (SaaS), STS Token Generation, API for Mobile Money Token Generation: Secure Hardware Security Module (HSM) or software-equivalent for 20-digit STS token generation. Tariff Engine: Support for Step/Block Tariffs (e.g., first 50kWh at a lower rate). Time-of-Use (ToU) capabilities (6 slots per day) to incentivize usage during peak solar production hours. Payment Integration: Open API architecture for seamless integration with Mobile Money and local banking gateways. User Management: Role-Based Access Control (RBAC) for administrators, technicians, and billing agents.
Meter Data Management (MDM) System License/Deployment Web-based Central Management System (CMS) accessible via browser to provide utility managers with real-time visibility into the grid’s health. Energy Auditing: Automated comparison between energy evacuated from the 7MVA Transformer and the sum of consumer consumption to identify line losses or theft. Load Profiling: Real-time data capture of voltage, current, and frequency from any meter for troubleshooting. Remote Control: "Bulk Disconnect" functionality to shed non-essential loads if the BESS State of Charge (SoC) drops below critical levels. Reporting: Automated daily, weekly, and monthly revenue and energy balance reports. Must include an automated SMS/Email alerting engine for low credit, anomalies, and tamper events.
Failover Server Hardware Mirrored local failover server, to be installed at the mini-grid control room to support the primary cloud-hosted software.
Prepaid System Training
Conduct End-to-end training program tailored for all system operators, including Billing Clerks, Technical Engineers, and Administrators. The training must cover the following modules: * Vending and Billing: Generating 20-digit STS tokens , managing API integrations with Mobile Money/banking apps , and configuring Step Tariffs, Time-of-Use (ToU) tariffs, and fixed monthly charges/debt recovery . * Monitoring and MDM: Operating the web-based Central Management System (CMS) , executing remote load management (kW limits) , performing remote disconnects/reconnects , and conducting energy balance audits against the 0.8kV Switchgear Incomer . * Field Operations and Troubleshooting: Installation, Setting , Responding to automated SMS/email alerts for tampers and voltage anomalies , and understanding meter hardware, DCUs, and communication gateways (GPRS/4G, NB-IoT, RF-Mesh, PLC) . * System Administration: Managing Role-Based Access Control (RBAC) , reviewing security audit trails , and understanding the local failover server architecture.
Maintenance Tool Kit
Supply and deliver complete set of maintenance toolkits : - CAT III 1500V Multimeter and Clampmeter - Earth Resistance Tester - Battery Internal Resistance Tester
- Electrical Hand Tools (1000V Insulated) including screwdrivers (slotted and Phillips), pliers (long-nose, diagonal cutters, combination), and open-ended/ring spanners (8mm to 24mm) - Dual-drive insulated wrenches with hex and socket bits
Operation and Maintenance During DNP:
- Provide a full 6 months operation and maintenace for the whole system and provide full On-Job training for the Utility staff during this period . the scope include the provision of the operation and maintenance team including and not limited to electerical engineers and technicans (experianced on PLC , SCADA, off/on- grid solar systems) as well as other engineers based on need.
- Provide technical support and maintenance and preventive visits on the remaining 6 months on bi-monthly basis during the DNP and apply all the preventive maintenace to the system component - Provide monthly reports as per the technical specification.
Work Station PC
Type Desktop PC including Monitor CPU Type:- Min 12 000 point according RAM Memory:- Min 32 GB DDR4 ECC HDD:- (1)x500 GB SSD dhe (2) x 1000 GB HDD Disk Subsystem Controlere :- 7200 RPM SATA 6.0 Gb/s for HDD “Disk Subsystem Controler”: Serial ATA III 6.0 Gb/s, Minimum 4 Serial ATA Interface with RAID 0,1,5,10 Support. (Hard Disk të Konfiguruar në RAID 1). Display:- Included LCD/LED 24" same brand Display ports:- (1) VGA and (1) DP/DVI/HDMI Media Device:- DVD+/-RW Ports:- (8) USB ports, min (4) USB 3.0/USB 3.1 (1) DP/HDMI (1/1) Headphone/Microphone Jack Networkingti:- 10/100/1000 Mbps LAN (RJ-45); Charger :- 2 EU 220 V Keyboard, Mouse :- QWERTY, Optical Mouse of same brand Graphic Card:- Dedicated 6 GB Memory OS:- Licensed Pre Installed Windows 11 Pro Sound:- Integrated, (2) x built-in Speakers (stereo)
Dynamic Display Panel
Hardware: A 40-inch TV screen and display interface shall be provided for indoor use (exact location to be specified during detailed engineering). Displayed Metrics: The interface must display, at a minimum: Instant Power (kW), Total Produced Energy (MWh), and cumulative CO2 emissions saved (Tons). Interface Design: The graphic design, including illustrations and text, must be submitted to and approved by the facility operators prior to implementation. Communication: The Contractor shall supply and install the required communication devices (LAN or other wired technology) to link the plant's remote monitoring system with the display panel.
Auxiliary Transformer 0.8kV to 0.4kV
Monitoring Room
AC Cabling
CU /XLPE /PVC ) Size (2Cx6+1C4E ) mm2
CU /XLPE /PVC ) Size (4x16 ) mm2
AC Distribution Board
Supply, install, test, and commissioning of Three phase AC main distribution boards unit (MDB) - The distribution board should allow flexibility to connect switch disconnections, MCB, RCCD or direct cable. - MDB includes Main MCCB 150A,4P with branches MCCBs 2*63A,3P, 2*40A,3P, 1*10A at least. - Internal connection should be through bus bars the bus bar rating should be at least 210A. - Ingress protection must be at least IP41. - Enclosure material should be galvanized steel sheets or powder-coated steel. - Fault level: at least 15 kA. - Minimum Number of ways is at least 8. - Bidders are advised to use high quality breakers preferably Schneider, ABB or equivalent. - Warranty: at least two years.
Supply, install, test, and commissioning of Single phase AC Sub distribution boards unit (SDB) - The distribution board should allow flexibility to connect switch disconnections, MCB, RCCD or direct cable. - SDB includes Main MCB 63A,2P and MCB size 1*20A,1P, 1*16A,1P, 4*10A at least. - Internal connection should be through bus bars the bus bar rating should be at least 100A. - Ingress protection must be at least IP41. - Enclosure material should be galvanized steel sheets or powder-coated steel. - Fault level: at least 15 kA. - Minimum Number of ways is at least 6. - Bidders are advised to use high quality breakers preferably Schneider, ABB or equivalent. - Warranty: at least two years.
WIRING SYSTEM
Supply, Installation, testing and commissioning complete in all respect for following items: Price to include (i) wires & conduits with accessories (ii) end connections of wires (iii) ceiling roses, Light point (iv) all circuits & sub circuits(v) switch, socket, plate, PVC / Steel conduit / surface back box as required complete with all necessary hardware & accessories, etc.
Wiring for light point/ ceiling fan point with2.5 sq.mm .FR PVC insulated copper conductor single core cable in concealed type Heavy gauge PVC Conduits , with modular switch 10 Amps, modular plate, suitable GI box and earthing the point with 1.5 sq.mm. FR PVC insulated copper conductor single core cable etc as required. (Including supply of cables, conduits from the distribution board up to the point complete with all accessories, Loop earthing cables etc. complete as per drawing and UNOPS engineer)
SOCKETS AND POWER CONNECTIONS.
Supply, install, test, and commission a complete socket outlet point (Legrand or equivalent) or PowerPoint with at lees 3x4 sqm PVC insulated multistrand copper conductor cable in concealed 25 mm dia PVC pipe, including all conductors, cables, conduits, boxes, Socket outlets, and all connections between the appropriate distribution boards and the socket outlet or power connection point for the following:
13A-230V 2P+E dublix socket outlet multible Standard.
outlet 13A duplex switched desk mounted
20A-230V 2P+E switch British Standard.
EMERGENCY & EXIT SIGN LIGHTING 10A 240V/50HZ +E POWER SOCKET OUTLET BRITISH STANDARD.
LIGHTING FIXTURES:
TYPE :F8 LIGHTING LUMINARIES 1200mm LENGTH WITH LED LAMP 2X18W, 1900lm . - Mount type: Surface Mount; - Color: White; - Lamp luminous efficacy: not less than 100 lm/W; - Housing: Metal; - Input Voltage and frequency: 220-240V, 50 Hz; - Working Lifetime (Hour): at least 15,000 h; - Certification: All related certificates shall be provided such CE, RoHS; - Warranty at least two years.
TYPE:F14 EMERGENCY LIGHTING FIXTURE WITH 1*5W LED AND PROVIDED WITH BACKUP BATTERY OF 3 HOURS DURATION. - Mount type: wall Mount; - Color temperatures (CCT): 5000 K to 6500 K; - Input Voltage and frequency: 220-240V, 50 Hz; - Working Lifetime (Hour): at least 50,000 h; - Certification: All related certificates shall be provided such CE, RoHS; - Warranty at least two years.
TYPE: F13 WALL MOUNTED DIRECT/INDIRECT LIGHTING FIXTURE WITH 20W LED LAMP. technical specification and drawing, - Lamp luminous efficacy: not less than 90 Im/w; - Voltage rating: 220-240 VAC, 50 Hz ±2%; - Working life time: not less than15,000; - The color temperature range: 5000K – 6500K; - Deigned with IP 65 protection aluminum body ; - Operating Temperature range: up to 50°C; - Certification: All related certificates shall be provided such CE, RoHS; - Wall Mounted type; - Warranty: at least two years.
TYPE:F12 WALL-MOUNTED EXIT SIGN LUMINAIRE, 4W LED LAMP AND WITH DOUBLE-SIDED PICTOGRAM RIGHT - LEFT DIRECTION/ UP-DAWN.
Supply, installation, testing, and commissioning of a 56-inch ceiling fan, 220–240 VAC, 50 Hz, complete with energy-efficient motor, speed regulator, mounting accessories, wiring connections, and all necessary fittings for a complete and operational installation.
Supply, install, test, and commission 1.5 Ton Refrigeration split air conditioner inverter type, including alternate operation and temperature control unit with all wiring requirements Two units will be used in duty mode and alternative mode. - Rated Power Consumption: ≤ 1.7 kW at rated cooling capacity - Rated Running Current: ≤ 7.5 A at 230 V AC, 1-phase, 50 Hz - Capacity: 18000 BTU; - Voltage: 220-240; - Frequency: 50 Hz; - Single phase; - Noise level shall not exceed 45 dB; - Star rating 3 stars or above; - Suitable for wall mounting; - The outdoor unit shall be housed inside a painted metal cage made of mild steel.
Fire alarm System
Supply and install 2 Zone at least Conventional Fire alarm system panel in generator room including all requirements from fire resistant cable 2C*1.5 sqr.mm, trunkeys ,pipes, termination, testing and proper labeling with complete Diagrams & documentation. Technical Specifications: - 2 zone panel - Each zone support to install at least 15 detector. - 2 sounder circuits - Include back up battery - EN54 Approved from LPCB
Supply and install Smoke Detector including all required fire resistant cable Technical Specifications: - Detector Class: A - Operating Voltage:9 TO 28V DC - Alarm Current: not less than 5mA - Sensitivity according to EN 54-10 - EN54 Approved from LPCB
Supply and install Heat Detector including all required fire resistant cable Technical Specifications: - Detector Class: A - Operating Voltage:9 TO 28V DC - Alarm Current: not less than 5mA - Sensitivity according to EN 54-10 - EN54 Approved from LPCB
Supply and install Manual Call Point (Break glass) including all required fire resistant cable Technical Specifications: - Detector Class: A - Operating Voltage:9 TO 28V DC - Alarm Current: not less than 5mA - EN54 Approved from LPCB
Supply and install Conventional bells(sounders) including all required fire resistant cable Technical Specifications: - Nominal voltage 9 - 28 Vdc - Purpose-made weather proof range. - EN54 Approved from LPCB
Supply, install, test and commissioning 5kg Carbon Dioxide (CO2) Extinguisher complete with mounting bracket, safety pin, pressure gauge, inspection tag, signage, and all accessories required for a complete operational fire protection system, in accordance with applicable fire safety standards.
Supply, install, test and commissioning 6kg Powder Extinguisher complete with mounting bracket, safety pin, pressure gauge, inspection tag, signage, and all accessories required for a complete operational fire protection system, in accordance with applicable fire safety standards.
Supply, installation, testing, and commissioning of 20 kg Carbon Dioxide (CO₂) fire extinguisher, complete with discharge horn/nozzle, hose assembly, operating valve, safety pin, pressure indication where applicable, suitable stand, identification/signage, and all necessary accessories. The extinguisher shall be suitable for electrical and energized equipment fires, comply with the applicable international fire-safety standards, and be supplied fully charged and ready for operation.
Supply, installation, testing, and commissioning of 20 kg Powder Extinguisher, complete with discharge horn/nozzle, hose assembly, operating valve, safety pin, pressure indication where applicable, suitable stand, identification/signage, and all necessary accessories. The extinguisher shall be suitable for electrical and energized equipment fires, comply with the applicable international fire-safety standards, and be supplied fully charged and ready for operation.
CCTV system
Supply, install, test and commission Surveillance system including but not limited all Main system components and accessories network cables, galvanized steel and/or PVC conduits, Water Proof Boxes with IP65 protection, turnkeys …etc. All of which shall be according to the specifications, drawings. Codes of practice and highest prevailing engineering standards, for the following:
Outdoor VF Bullet Network Camera 8MP: Supply and installOutdoor VF Bullet Network Camera 8MP according to the following specifications; Image Sensor:1/2.4" progressive scan CMOS Max. Resolution: Up to 3072 x 2048 Min. Illumination: 0.016 lux @ (f/1.6, AGC on), 0 lux with IR Lens Type:2.8 mm, 4 mm, and 6 mm Focal Length & FOV: 2.8 mm, horizontal FOV: 99°, vertical FOV: 61°, diagonal FOV: 128° Main Stream: 20 fps (3072 × 2048, 3072 × 1728, 2944 × 1656), 30 fps (2560 × 1440, 1920 × 1080, 1280 × 720) Wide Dynamic Range: 120 dB IR Range:Up to 100 ft (30 m) Protection: IP67. - The warranty period should be 12 months.
Indoor Fixed Dome Network Camera 8MP : Supply and install Indoor Fixed Dome Network Camera 8MP according to the following specifications; Image Sensor: 1/2.9" Progressive Scan CMO Max. Resolution: 3072 × 2048 Min. Illumination: Color: 0.01 lux @(F1.2, AGC ON), 0.028 lux @(F2.0, AGC ON), 0 lux with IR Digital Noise Reduction: 3D DNR Lens Type: 2.8 mm, 4 mm, and 6 mm Focal Length & FOV: 2.8/4/6/8 mm 2.8 mm, horizontal FOV: 97°, vertical FOV: 63°, diagonal FOV: 120 Main Stream: 50Hz: 20 fps (3072 × 2048, 3072 × 1728, 2944 × 1656), 25 fps (2560 × 1440, 1920 × 1080, 1280 × 720) Wide Dynamic Range:120 dB IR Range: Up to 30 m Protection: IP67
IP Network Video recorder (NVR) Technical Specifications: Third-party network cameras supported, IP video Input 32 channel POE, Output Resolution VGA/ HDMI,H.265, H.264 & USB storage , at least 4 SATA interfaces for 4HDDs , DDNS,support minimum 160Mbps incoming bandwidth ,Recording Resolution 8M pixel preview ,Synchronous playback optionsHDD Capacity minimum 6TB storage voltage system 220v,50z - The warranty period should be 12 months.
Supply and install 50" inch LED FHD Monitor with all installation accessories -Full HD; - 2xHDMI, Ethernet port, USB; - Wall mount bracket; -10 merte HDMI cable to be included; -voltage system 220v,50z. - The warranty period should be 12 months.
Supply, install, test, and commission industrial-grade 24-port Long-Range PoE Gigabit Ethernet Switch, complete with an IP54-rated weatherproof junction box suitable for pole mounting on a standalone solar street lighting pole. The item shall include all required mounting brackets, cable glands, connectors, termination accessories, Cat6 patch cords, surge protection devices (where required), labeling, grounding, testing, commissioning, and all other accessories necessary to provide a complete, fully operational, and integrated CCTV communication network. The switch shall be specifically designed for outdoor CCTV applications and shall comply with the following minimum technical requirements: Ports: Minimum 24 × 10/100/1000 Mbps RJ45 PoE ports, plus a minimum of 2 × Gigabit uplink ports (RJ45 and/or SFP fiber). PoE Compliance: IEEE 802.3af, IEEE 802.3at (PoE+), with automatic power detection and protection. PoE Power Budget: Minimum 250 W, with intelligent power management and overload protection. Long-Range PoE: Support extended transmission mode over Cat6 cable with a minimum transmission distance of 250–300 m, and up to 800 m on designated long-range ports while maintaining stable communication and camera power. Data Transmission: Minimum 10 Mbps data rate in long-range mode, with Gigabit switching performance for standard Ethernet connections. Switching Capacity: Minimum 52 Gbps non-blocking switching fabric with wire-speed forwarding. MAC Address Table: Minimum 8K entries. Surge Protection: Built-in industrial surge and lightning protection of not less than 6 kV per Ethernet port and power input. Network Features: Support QoS (802.1p), VLAN, port isolation, broadcast storm control, loop prevention, IGMP Snooping, Auto MDI/MDIX, Auto-Negotiation, and IEEE 802.3x Flow Control. Management: Unmanaged or managed type as specified in the project requirements. Managed switches shall support Web GUI, SNMP, VLAN configuration, port monitoring, and remote diagnostics. Operating Environment: Operating temperature -30°C to +75°C minimum, relative humidity 5–95% (non-condensing). Enclosure: IP54-rated weatherproof junction box suitable for outdoor installation on solar street lighting poles, with corrosion-resistant mounting accessories. Power Supply: Compatible with the project power supply, including over-voltage, overload, and short-circuit protection. Standards: Comply with IEEE 802.3, IEEE 802.3u, IEEE 802.3ab, IEEE 802.3af, IEEE 802.3at, CE, FCC, RoHS, and applicable IEC EMC and safety standards.
HDD 6TB, PoE switch (1*24 )and 12U rack, patch panels, PDU, and all related accessories.
Multifunctional Network Video Recorder 24 channels for real time viewing and recording @ 480/400fps
Data ethernet& IP phone socket outlet
Supply, install, testing and commissioning of complete RJ45 - Cat.7A Data socket outlet including, conduits, boxes and all related accessories as required per drawings.
singel RJ-45 socket outlet
double RJ-45 socket outlet
FLUSH MOUNTED INTERFACE PVC 100x100 mm IP 21
FLUSH MOUNTED INTERFACE PVC 100x100 mm IP 54
TV socket outlet
Supply, install, testing and commission of complete TV socket outlet including, conduits, boxes, and all related accessories.
TV SOCKET
Autonomous, waterless dry cleaning robot system
Spare Part
PV Modules and Installation Accessories
PV module with the same specifications mentioned in Item No.1.1
MC4 Connectors: Original MC4 or certified equivalent, UV-resistant
Installation Accessories: Module mounting clamps (mid and end) and fasteners
300 kW String Inverters
Internal Fan Assembly: Replacement cooling fan kits for 300 kW inverters
Communication Cards: Integrated Wi-Fi/GPRS/RS485 modules
7 MVA 0.8/11kV Step-up Transformer
Bushings & Studs: Complete set of H.V. and L.V. bushings
Bimetallic Connectors: For H.V. and L.V. bushing connections
Relays & Gauges: Spare Buchholz relay and Magnetic Oil Level Gauge (MOG)
Consumables: Silica gel refills for breathers (3 changes) and Gasket/O-ring set
0.8 kV LV Switchgear
Protection Devices: Microprocessor-based LSIG protection unit
Auxiliary Components: Sets of Shunt Trip, Under-voltage coils, and Charging motors
Loose Devices: LED indicating lamps and control fuses
Earthing and ESE Lightning System
Exothermic Welds: Mold & Powder for 50 mm^2 connections
Earth Enhancement: Bentonite or specialized EEC compound
11kV Overhead Lines (OHL) System
Insulators: 11kV Porcelain Pin and 80kN Disc Insulators
Surge Arresters: 12kV, 10kA Gapless Zinc Oxide type
Conductor Hardware: PG Clamps, Dead-end assemblies, and Binding wire
Drop-Out Fuses: 11kV, 100A DO Fuse units and spare elements
11kV Ring Main Unit (RMU)
Indicators: Voltage Presence Indicating System (VPIS) modules
Fire Detection System
Detectors: Smoke and Heat detectors (Site-wide system)
Manual Call Points: Indoor/Outdoor type with break glass
Autonomous, waterless dry cleaning robot system
Supply and provide a complete set of manufacturer-recommended spare parts, consumables, maintenance equipment, and special tools required for the operation, routine maintenance, troubleshooting, and repair of the autonomous, waterless dry-cleaning robot system for the duration of the project warranty and maintenance period. The package shall include, as a minimum, replacement cleaning components, brushes, wheels/tracks, drive components, batteries and/or battery-related components, charging accessories, sensors, electrical and communication components, fuses, connectors, fasteners, and all other consumable and wear parts recommended by the manufacturer.
Special Safety Kit Tools
Complete Safety Kit for the System (including all PPE, electrical safety, rescue, LOTO, first aid, emergency response equipment, warning signage, and all accessories required for safe operation and maintenance of the complete system as per below quantities per each:- - Insulated Tool Kit (1000 V):- 2 Pcs - Digital True RMS Multimeter (CAT IV):- 2 Pcs - AC/DC Clamp Meter 2 Pcs - Thermal Imaging Camera:- 1 PC - Torque Wrench Set:- 2 Pcs - Safety Kit: • Arc Flash Personal Protective Equipment (PPE) Kit :- 2 Pcs • Safety Helmet with Electrical Protection (Class E):- 28 Pcs • Safety Goggles and Face Shield:- 6 Pcs • Flame-Resistant (FR) Coveralls:- 28 Pcs • High-Visibility Safety Vest:- 28 Pcs • Safety Shoes with Electrical Hazard (EH) Protection:- 28 Pcs • Hearing Protection (Ear Plugs/Ear Muffs):- 4 Cartons • Lockout/Tagout (LOTO) Kit with padlocks, tags, and hasps:- 6 Pcs each • First Aid Kit (Industrial Grade):- 6 Pcs • Eye Wash Kit:- 4 Pcs • Fire Blanket:- 6 Pcs • Emergency Escape Breathing Device (EEBD):- 2 Pcs • Safety Barricades, Warning Tape, and Traffic Cones:- 8 Pcs each • Danger, High Voltage, and Emergency Signage:- 8 Pcs each • Emergency Exit and Evacuation Signage:- 6 Pcs • Portable Emergency Lighting:- 4 Pcs • Emergency Communication Device (two-way radio or equivalent):- 2 Pcs • Stretcher and Emergency Rescue Equipment:- 2 Pcs
Description.
Civil and Archirictrucal BoQs.
Electrical BoQs.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Annex 3 - Civil - Husswain Mini-Grid Technical Specifications.pdf
Bidding document • 0.84 MB
Annex 5A - Civil Drawing - General Site Husswain Mini-Grid Power Station.pdf
Bidding document • 11.81 MB
Annex 5C - Typical Drawing - D-01- Security Fence with Curb.pdf
Bidding document • 1.48 MB
Annex 5C - Typical Drawing - D-03- Inverter Mounting Structure.pdf
Bidding document • 0.76 MB
Annex 5C - Typical Drawing - D-04 Cable Trenches & Cable Trays For PV Arrays.pdf
Bidding document • 1.10 MB
Annex 5C - Typical Drawing - D-05- Earthing and Lightning Systems.pdf
Bidding document • 2.08 MB
Annex 5C - Typical Drawing - D-06- Lightning Systems Installation.pdf
Bidding document • 0.53 MB
Annex 5C - Typical Drawing - D-07- Lighting System Installation.pdf
Bidding document • 0.63 MB
Annex 5C - Typical Drawing - D-08- Weather Station.pdf
Bidding document • 0.38 MB
Annex 5C - Typical Drawing - D-09-Foundation Of The Steel Container.pdf
Bidding document • 0.24 MB
Annex 5C - Typical Drawing - D-10 -Manhole Concrete Details.pdf
Bidding document • 0.42 MB
Annex 5C - Typical Drawing - D-11- Retaining Walls.pdf
Bidding document • 0.52 MB
Annex 5D - Drawing - 36 PV Modules Ground Level Mounting Structure.pdf
Bidding document • 1.15 MB
Annex 5E - Drawing - Control and Monitoring Room 5.4m x 7 m.pdf
Bidding document • 0.77 MB
Annex 7A - ESMP -Supply and Installation of solar Mini grid power plant in Husswein Almaharah.pdf
Bidding document • 3.43 MB
Annex 7B - UNOPS Minimum Health and Safety Requirements for Contractors - EN.pdf
Bidding document • 0.62 MB
Annex 7C - GS04 PSEAH Specific Guidance for Contractors EN.pdf
Bidding document • 0.09 MB
Annex 7D - Forced Labor Declaration Form.docx
Bidding document • 0.20 MB
Company Employee Summary Mandatory.xlsx
Bidding document • 0.05 MB
DRAFT - Construction Contract for Small Works.pdf
Bidding document • 1.48 MB
Project Sign Board.pdf
Bidding document • 0.58 MB
RFQ-2026-65288 - Solicitation, Section VI Returnable Schedules.docx
Bidding document • 1.87 MB
Small Works RFQ Section-I Instructions to Bidders.pdf
Bidding document • 1.86 MB
REV 1 - Annex 4 - Husswain Mini-Grid Solar Power Station Bill of Quantitis.xlsx
Bidding document • 0.14 MB
REV 1 - Annex 5C- Typical Drawings - D-02-DC Wiring Single Line Diagram.pdf
Bidding document • 0.16 MB
Minutes for Pre-bid Meeting RFQ-2026-65288.pdf
Bidding document • 0.14 MB
REV 1 - RFQ-2026-65288- Solicitation, Sections II, III, IV, V.pdf
Bidding document • 1.18 MB
REV 1 - Annex 6 - Technical specifications for Goods and Comparative Data Table.docx
Bidding document • 0.88 MB
REV 1 - Annex 2 - Electrical - Husswain Mini-Grid Technical Specifications.pdf
Bidding document • 1.20 MB
REV 1 - Annex 1 - Scope of Work Husswain Mini-Grid Solar Power Station.pdf
Bidding document • 3.74 MB
REV 1 - Annex 5B - Electrical Drawings - Husswain Mini-Grid Power Station.pdf
Bidding document • 8.77 MB
Notice on UNGM.html
Notice page • 0.13 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .