| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC BHAGWANPURA DISTY SYSYTEM CONCRETE LINING M 15 WITH 10 ENHANCED CAPACITY FROM RD 28900 42528 OFFTAKING AT RD 90200 R 2ND PATIALA FEEDER | ₹1.1 Cr | L1 | Accepted-AOC Awarded |
| 2 | L2₹1.1 Cr+₹73,227.61 (0.67%)Rejected-AOC | ₹1.1 Cr+₹73,227.61 (0.67%) | L2 | Rejected-AOC High Rate |
| 3 | L3₹1.3 Cr+₹16.4 L (15.0%)Rejected-AOC | ₹1.3 Cr+₹16.4 L (15.0%) | L3 | Rejected-AOC High Rate |
Tender Value
Refer Docs
EMD Value
₹2.1 L
Closing Date
18 Nov 2020, 1:00 pmClosed
Executive Engineer Lehal Divsion Ib Patiala
Executive Engineer Lehal Divsion Ib Patiala
Estimate With Concrete Lining from RD 0 to 19270 Tail of Minor No1 of Bhawanigarh Distributary off taking at RD 13765L of Bhawanigarh Distributary
2020_WR_55584_3
004
Open Tender
Civil Works - Canal
Item Rate
90 days
Lehal Division IB patiala
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
₹2.1 L
Yes
7 Dec 2020
3 Nov 2020
18 Nov 2020
3 Nov 2020
18 Nov 2020
3 Nov 2020
Amount
Jungle clearance on running canals and branches, and drains with discharge upto 53 cs/sec.
Earth work in excavation of foundation of structures as per drawing and technical specificationss including setting out ,construction of shoring and bracing ,removal of stumps and other deleterious matter, dressing of side and bottom and backfilling with approved material.Mechanical Means Depth upto 3 m
Excavation of soil (any type) using hydraulic excavator CK 90 excavation with hydraulic excavator of 0.9 cum capacity including cutting trimming bottom and side slopes in accordance with requirement of grades and cross sections, including all lift and combined lead upto 60 mtr.
Excavation of soil using hydraulic JCB and hydraulic tractor trolly with disposal upto 2.97 km katcha including cutting and loading in trolly trimming bottom and side slopes in accordance with requirement of grades and cross secions and transporting to embankments locations with all leads.
Extra for laying earth as per specification for compaction in 20 Cm. layers and dressing including the cost of rolling and watering as per PWD specificationss.
Earth work for lip cutting for lining of irrigation channels inclusive of all allowance leads and dressing (as per earth work statement) (a) 0-1.5 mt. depth
(b) 1.5-3.0 mtr depth
Dressing of Earth work (New)
Dismantaling of old lining and brick work in cement sand mortar.
Dressing and preparation of sub grade for side slopes. a) in bed
b) In side slope
Providing and laying cement concrete (M-15) sleepers iin bed and side slopes below the joints of concrete lining mixed in automatic computerized batching and mixing plant and transported to the site in transit mixers including supply, carriage, loading and unloading of material complete in all respect as per design/drawing and PWD specificationss. a) in bed
b) In cup section
Laying 1:3 ( cement: water) cement slurry with cement @ 2.25 kg per sqmt on prepared bed & side slope before laying concrete.
Providing and laying cement concrete lining 60mm thick or less manually for irrigation channels using cement concrete (M-15) mixed in Automatic Computerized Batching and Mixing plant and Transported to the site in Transit mixers,including supply, carriage, loading & unloading of material complete in all respect as per design/drawing and PWD specfication (on side slope vertical height up to 3.50 mt.) a) in bed
b) In cup section
Providing and laying cement concrete (M-15) for coping mixed in automatic computerized batching and mixing plant and transported to the site in transit mixers including supply, carriage, loading & unloading of material complete in all respect as per design/drawing and PWD specifications.
Filling of construction joints sealing compound including supply carriage, of material complete in all respect as per design/drawing and PWD specifications.
Filling of expansion joints with special impervious hot pour 12.5 mm wide including supply, carriage, of material complete in all respect as per design/drawing and PWD specifications. a) For 60 mm thick slab of lining
Providing and laying LDEP 150 micron over sleeper on construction joints and expansion joints complete in all respect as per design/drawing and PWD specifications.
Shuttering for faces of concrete lining on side slopes and bed complete in all respect as per design/drawing and PWD specifications.
Extra for Bitumen Painting @ 0.69 kg per sqmt.
Dag belling single kassi stroke minimum 7.5cm depth complete in all respect as per design/drawing and PWD specifications.
Making temporary sirki sarkanda godown 3mx3m size with walls 2.5 mt. height 1.5 brick burnt brick but including the cost of other materials.
Ordinary distance marks (km stone) after every 1000 feet interval.
Earth work involved in dismentalling of outlet H upto 0.50m
Dismantling of APM of type outlet involved dismantling cement masonary& RCC slab with 'H' uptp 0.50 mt.
Adjusting new APM block in correct 'y' and fixing in position
C.C 1:4:8 with brick ballast 40mm gauge
Brick masonry in 1:4 CSM
RCC 1:2:4 for slab
Bending binding and placing in position CTD bars Fe 500
Extra labour for dressing of bricks for outlet with (H) upto 0.50mtr
Any other items
GURDEV SINGH CONTRACTOR
SUBHASH CHAND CONTRACTOR
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .