| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹32.5 LAccepted-AOC | ₹32.5 L Quoted ₹30.4 L | L1 | Accepted-AOC accepted |
| 2 | L2₹32.8 LRejected-AOC | ₹32.8 L | L2 | Rejected-AOC rejected |
| Sl No | Description | Qty | Unit | S.MATHURAM CONTRACTOR L1 | SRI TIRUMALA ENGINEERING WORKS L2 |
|---|---|---|---|---|---|
| 1.00 | Charges for removal of the local pressure / temperature gauges and refixing them after calibration in boiler, turbine & generator areas. | 400 | Nos. | 515 ₹2.1 L | 550 ₹2.2 L |
| 2.00 | Charges for removal of pressure / temperature transmitters including disconnecting the control cables, removal of clamps & manifold and refixing them after calibration in boiler, turbine & generator areas. | 600 | Nos. | 515 ₹3.1 L | 550 ₹3.3 L |
| 3.00 | Charges for dismantling, cleaning, replacement of gaskets (280x280mm) and re-fitting of level switch | 40 | Nos. | 2,512 ₹1.0 L | 2,600 ₹1.0 L |
| 4.00 | Charges for removing and refitting of accessories in pneumatic control valves & dampers such as I/P converters, air regulators, air lock relays, positioner and position feedback transmitters sending to lab for testing, and receiving the tested instruments from lab. | 80 | Nos. | 2,323 ₹1.9 L | 2,400 ₹1.9 L |
| 5.00 | Charges for cutting and welding of take-off catch point in mills, flue gas, primary and secondary air path. | 80 | Nos. | 825 ₹66,000 | 900 ₹72,000 |
| 6.00 | Charges for 3 Nos. Of single point cutting and welding of pipe size ½” impulse lines of mill, flue gas, primary and secondary air path including cost of gas, welding electrodes & consumables such as cotton waste, hacksaw blade, etc., | 100 | Nos. | 551 ₹55,100 | 600 ₹60,000 |
| 7.00 | Charges for flushing of impulse lines of all types of transmitters in Boiler & Turbine Area | 1,200 | Nos. | 1,092 ₹13.1 L | 1,200 ₹14.4 L |
| 8.00 | Charges for Material and Tools Handling Disassembling and Reassembling Works in the Calibrating of Control Actuators. | 180 | Nos. | 1,092 ₹2.0 L | 1,200 ₹2.2 L |
| 9.00 | All types of Panel cleaning includes DCS, UPS, Power Packs, Power Supply Panel, etc., removal of Modules, Cleaning of Modules and refixing the Modules. | 100 | Times | 2,341 ₹2.3 L | 2,500 ₹2.5 L |
| 10.00 | Releasing, transporting, overhauling, checking, re-fixing and conducting functional test on 4 Nos. Burner tilt power cylinders. | 4 | Nos. | 11,969 ₹47,876 | 12,500 ₹50,000 |
Tender Value
Refer Docs
EMD Value
₹32,400
Closing Date
21 Jan 2025, 2:00 pmClosed
SE/ES/NCTPS-I
Superintending Engineer Electrical System NCTPS I Chennai 120
NCTPS I ES Circle C I Dn S Dn II Carrying out maintenance activities of C I equipments in Unit II BOP System and allied areas for a period of 360 days during the year 2025 2026
2025_EB_516953_1
CE/NCTPS-I/SE/ES/WC-40/2024-25
Open Tender
Power/Energy Projects/Products
360 days
NCTPS-I
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹32,400
Yes
16 May 2026
7 Jan 2025
22 Jan 2025
7 Jan 2025
21 Jan 2025
7 Jan 2025
Amount
Charges for removal of the local pressure / temperature gauges and refixing them after calibration in boiler, turbine & generator areas.
Charges for removal of pressure / temperature transmitters including disconnecting the control cables, removal of clamps & manifold and refixing them after calibration in boiler, turbine & generator areas.
Charges for dismantling, cleaning, replacement of gaskets (280x280mm) and re-fitting of level switch
Charges for removing and refitting of accessories in pneumatic control valves & dampers such as I/P converters, air regulators, air lock relays, positioner and position feedback transmitters sending to lab for testing, and receiving the tested instruments from lab.
Charges for cutting and welding of take-off catch point in mills, flue gas, primary and secondary air path.
Charges for 3 Nos. Of single point cutting and welding of pipe size ½” impulse lines of mill, flue gas, primary and secondary air path including cost of gas, welding electrodes & consumables such as cotton waste, hacksaw blade, etc.,
Charges for flushing of impulse lines of all types of transmitters in Boiler & Turbine Area
Charges for Material and Tools Handling Disassembling and Reassembling Works in the Calibrating of Control Actuators.
All types of Panel cleaning includes DCS, UPS, Power Packs, Power Supply Panel, etc., removal of Modules, Cleaning of Modules and refixing the Modules.
Releasing, transporting, overhauling, checking, re-fixing and conducting functional test on 4 Nos. Burner tilt power cylinders.
Cleaning of secondary air aerofoils inside the FD fan duct, choke removal of secondary air flow transmitter impulse lines
Overhauling of Actuators. Charges for releasing of ID/FD/ PA/HAD/ CAD Electrical Actuators in Boiler area from Gear Box in existing location, Cleaning, Inspection of defective spares.
SRI TIRUMALA ENGINEERING WORKS (BID ID -1233722)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.05 MB
BOQ_615185.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid