| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.2 LAccepted-AOC | L1 | Accepted-AOC L1 Lowest | |
| 2 | L2₹9.0 L+₹74,987.46 (9.12%)Rejected-Finance | L2 | Rejected-Finance Higher Rate |
Tender Value
Refer Docs
EMD Value
₹20,000
Closing Date
12 May 2021, 2:00 pmClosed
EE MCD MZP
EE MCD MZP Irrigation Coloney Fataha, Mirzapur
Estimate for Construction of VRB of Hinauta Minor at km 0.600 and 1.700 Offtake from Ghaghar Main Canal LOT-1 Retender
2021_UPIDC_573166_13
Tender Notice No-05/E.E/2020-21
Open Tender
Civil Works
Item Rate
45 days
SONEBHADRA
Please refer Tender documents.
2 documents required · 2 mandatory
₹354
₹20,000
8 Oct 2021
5 May 2021
12 May 2021
5 May 2021
12 May 2021
5 May 2021
Amount
E.W. Excavation in foundation in canal with all lead upto 30 M lift upto 1.5 M in all types of soil including all Cost of materials, Labours , T&P & all Taxes
Sand filling in foundation of VRB with all lead lift including cost of all material labour T&P and taxes etc.
P/L C.C. 1:3:6 in foundation with all lead & Lift including all cost of Cement , materials, Labours, T&P & all Taxes
Centering & Shuttering for CC & RCC work with all lead & Lift including all cost of boulder , materials, Labours, T&P & all Taxes.
CC Slab of 1:1.5:3 with all lead & Lift including all cost of , materials, Labours, T&P & all Taxes.
Bending , Binding, Cutting & Placing of Steel reinforcement including cost of wire for RCC Slab with all lead & Lift including all cost of materials, Labours, T&P & all Taxes.
C.R. 1:3 Masonary with Cement and coarse sand including cost of all material labour t&p etc.
Cement pointing 1:2 with Cement and coarse sand including cost of all material labour t&p etc.
C.C. 1:2:4 in approach to road both side including cost of all material labour t&p and taxes etc.
Providing and fixing wheel guard on four side including all cost of size 0.20Mx0.20M, 1.50 long including all cost
E.W. in back filling of canal section with all lead & Lift including all cost of , materials, Labours, T&P & all Taxes.
Colour washing of two coat of parapet including cost of all materials,labour and T&P etc.
SHREYA CONTRUCTION
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .