| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.4 CrAccepted-AOC | ₹1.4 Cr Quoted ₹1.5 Cr | L1 | Accepted-AOC Quoted Lowest Rate |
| 2 | L2₹1.5 Cr+₹1.9 L (1.31%)Rejected-AOC | ₹1.5 Cr+₹1.9 L (1.31%) | L2 | Rejected-AOC Rate Quoted Higher than L1 |
| 3 | L3₹1.5 Cr+₹3.7 L (2.49%)Rejected-AOC | ₹1.5 Cr+₹3.7 L (2.49%) | L3 | Rejected-AOC Rate Quoted Higher than L1 |
| Sl No | Description | Qty | Unit | KANDASAMYCHETTIAR BALASUBRAMANIAN L3 | KANTHAA CONSTRUCTIONS L2 | SRI SAIRAM CONSTRUCTIONS L1 |
|---|---|---|---|---|---|---|
| 1.00 | Dismantling , clearing away and carefully stacking materials useful for re-use for any thickness of Brick Masonry in lime mortar walls | 64.37 | cum | 265 ₹17,058.05 | 260 ₹16,736.2 | 255 ₹16,414.35 Lowest |
| 2.00 | Dismantling , clearing away and carefully stacking materials useful for re-use for any thickness of Brick Masonry in cement mortar walls | 15.72 | cum | 320 ₹5,030.4 | 315 ₹4,951.8 | 310 ₹4,873.2 Lowest |
| 3.00 | Dismantling , clearing away and carefully stacking materials useful for re-use for any thickness of terracing work in roof | 117.03 | sqm | 95 ₹11,117.85 | 90 ₹10,532.7 | 85 ₹9,947.55 Lowest |
| 4.00 | Dismantling , clearing away and carefully stacking materials useful for re-use for any thickness of RCC Concrete roof slab by using deploying machineries | 7.85 | cum | 4,800 ₹37,680 | 4,750 ₹37,287.5 | 4,700 ₹36,895 Lowest |
| 5.00 | Dismantling , clearing away and carefully stacking materials useful for re-use for any thickness of door and windows including removal of frames, hinges and fastenings | 46.44 | sqm | 180 ₹8,359.2 | 175 ₹8,127 | 170 ₹7,894.8 Lowest |
| 6.00 | Dismantling , clearing away and carefully stacking materials useful for re-use for any thickness of wrought and put-up framed timbers in roofs | 0.46 | cum | 830 ₹381.8 | 825 ₹379.5 | 810 ₹372.6 Lowest |
| 7.00 | Earth work excavation for foundation by Mechanical means for Isolated & Combined Footing etc. in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sites and raming of bottoms at the site, etc., complete complying with standard specification and as directed by the departmental officers. Upto 2.40m Depth. | 720 | m3 | 380 ₹2,73,600 | 375 ₹2,70,000 | 370 ₹2,66,400 Lowest |
| 8.00 | Earth work Open excavation by Mechanical Means for Open Earthwork in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard specification and as directed by the departmental officers.
Upto 2.40m Depth. | 40 | m3 | 210 ₹8,400 | 205 ₹8,200 | 200 ₹8,000 Lowest |
| 9.00 | Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers - Mixing by mechanical means | 32 | m3 | 5,690 ₹1,82,080 | 5,640 ₹1,80,480 | 5,580 ₹1,78,560 Lowest |
| 10.00 | Supplying and filling in foundation, basement, etc. with conveyed earth in layers of not more than 150mm thick layers well watered, rammed with surface vibrator and consolidated including conveyance charges etc. complete complying with standard specification and as directed by the departmental officers. | 141 | m3 | 550 ₹77,550 | 545 ₹76,845 | 530 ₹74,730 Lowest |
Tender Value
₹1.4 Cr
EMD Value
₹83,000
Closing Date
15 Oct 2025, 3:00 pmClosed
Superintending Engineer PWD Buildings Sivagangai
Superintending Engineer PWD Buildings C M Circle Sivagangai 630562
Construction of Sub Registrar office building at Sattur in Sattur Taluk of Virudhunagar District
2025_PWD_610376_1
24 SE Buildings C M Circle Sivagangai 2025 2026 dt 23 09 2025 4
Open Tender
Civil Works - Buildings
Lump-sum
210 days
Sattur Taluk of Virudhunagar District
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹83,000
27 Nov 2025
30 Sept 2025
16 Oct 2025
30 Sept 2025
15 Oct 2025
30 Sept 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .