| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹91.0 LAccepted-AOC NO 1 9 A AGRAHARAM THIYAGARAJAPURAM NARASINGAMPETTAI THANJAVUR DISTRICT 609802 | THANJAVUR | TAMIL NADU | 609802 | L1 | Accepted-AOC Lowest Bidder | |
| 2 | L2₹93.2 L+₹2.3 L (2.51%)Rejected-Finance | L2 | Rejected-Finance Highest Rate |
Tender Value
₹92.2 L
EMD Value
₹92,300
Closing Date
16 May 2023, 3:00 pmClosed
Additional Collector (Dev)/Project Director
DRDA Office, 2nd Floor, New Collectorate,Thanjavur
Thanjavur District - Strengthening and 5 years maintenance of 3 Road works Package No. 23 in Thiruppanandal Block Under MGSMT 2022-2023.
2023_RDTN_304248_1
DIPR/2142/Tender/2023
Open Tender
Civil Works - Roads
Item Rate
180 days
Thiruppanandal
As per Tender document
9 documents required · 9 mandatory
₹0
₹92,300
11 Jul 2023
26 Apr 2023
16 May 2023
26 Apr 2023
16 May 2023
26 Apr 2023
Amount
Part 01:Strengthening and 5 years maintenance of Thirumandurai - 50 Sathanur Road in Thirumandurai Panchayat Km 0/0-1/200.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
Providing and laying Water Bound Macadam Grading - III (63mm to11.20mm) IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.21cum for 10 sqm and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method)
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25 MM THICK USING CMP (Grade-II) - Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory / phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Supplying and fixing kilo Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
60 cm Equilateral triangle cautionary signboard (Pedestrian crossing, Major Road ahead, Speed breaker ahead, School zone, Side road left and right, X-junction ahead, Curve ahead)
Pedestrain Crossing
Major Road ahead
Provision for White Marking 4" wide
Construction of 1.50 m RCC slab culvert @ Chainage 415 m.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Culvert at Ch. 415m
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Culvert at Ch. 415m
Cement concrete of grade CC 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Culvert at Ch. 415m
Cement concrete of grade CC 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Culvert at Ch. 415m
Supply and Erecting Steel Centering including cost and conveyance to worksite and all labour charges etc., completed. (Below Basement)
Culvert at Ch. 415m
Supply and Erecting Steel Centering including cost and conveyance to worksite and all labour charges etc., completed. (Above Basement)
Culvert at Ch. 415m
Cement concrete of grade CC 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Culvert at Ch. 415m
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Culvert at Ch. 415m
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Culvert at Ch. 415m
Construction of 1.50 m RCC slab culvert @ Chainage 710 m.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Culvert at Ch. 710m
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Culvert at Ch. 710m
Cement concrete of grade CC 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Culvert at Ch. 710m
Cement concrete of grade CC 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Culvert at Ch. 710m
Supply and Erecting Steel Centering including cost and conveyance to worksite and all labour charges etc., completed. (Below Basement)
Culvert at Ch. 710m
Supply and Erecting Steel Centering including cost and conveyance to worksite and all labour charges etc., completed. (Above Basement)
Culvert at Ch. 710m
Cement concrete of grade CC 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Culvert at Ch. 710m
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Culvert at Ch. 710m
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Culvert at Ch. 710m
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part 02: Strengthening and 5 years maintenance of Thiruppanandal -Sivapurani Mananchery Road in Thirulogi Panchayat Km 0/0-0/960.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
Providing and laying Water Bound Macadam Grading - III (63mm to11.20mm) IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.21cum for 10 sqm and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method)
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25 MM THICK USING CMP (Grade-II) - Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory / phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Supplying and fixing kilo Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
60 cm Equilateral triangle cautionary signboard (Pedestrian crossing, Major Road ahead, Speed breaker ahead, School zone, Side road left and right, X-junction ahead, Curve ahead)
Pedestrain Crossing
Major Road ahead
Side road left and right
Provision for White Marking 4" wide
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part 03: Strengthening and 5 years maintenance of Kagithapattarai - Serugudy Road in Kavanur Panchayat Km 0/0-0/400.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
Providing and laying Water Bound Macadam Grading - III (63mm to11.20mm) IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.21cum for 10 sqm and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method)
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25 MM THICK USING CMP (Grade-II) - Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory / phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
60 cm Equilateral triangle cautionary signboard (Pedestrian crossing, Major Road ahead, Speed breaker ahead, School zone, Side road left and right, X-junction ahead, Curve ahead)
Pedestrain Crossing
Major Road ahead
School Zone
Side road left and right
Provision for White Marking 4" wide
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}.
G SWAMINATHAN AND CO
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .