| 1 | L1₹2.7 LAccepted-AOC HOUSE NO R17 ADARSH COLONY NEARBY MULLAH HOTEL NIT FARIDABAD 121001 | FARIDABAD | FARIDABAD | HARYANA | 121001 | ₹2.7 L Quoted ₹2.8 L | L1 | Accepted-AOC due to lowest amount |
| 2 | L2₹3.2 LRejected-AOC | ₹3.2 L | L2 | Rejected-AOC due to 2nd lowest amount |
Tender Value
₹4.6 L
EMD Value
₹9,200
Closing Date
23 May 2026, 5:00 pmClosed
Sandeep Dahiya
DIV Faridabad
A/mtc of Sewerage Scheme in Sector-65, Faridabad. Pro. and laying of 200 MM dia HDPE pipe in-front of plot No. 2523, Sector-65, Fbd. complete in all respect and all other works contingent thereto.
2026_HBC_521869_1
2026837A2A03 273C 45FF 97B9 B8D336B340F3248HSV
Open Tender
Civil Works
30 days
Faridabad (MC)
A/mtc of Sewerage Scheme in Sector-65, Faridabad. Pro. and laying of 200 MM dia HDPE pipe in-front of plot No. 2523, Sector-65, Fbd. complete in all respect and all other works contingent thereto.
2 documents required · 2 mandatory
₹250
₹9,200
Yes
5 Jun 2026
15 May 2026
25 May 2026
15 May 2026
23 May 2026
15 May 2026
15 May 2026 - 17 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. | 0.2 | per cum | 83 | ₹16.6 | BI01010001010000000000000515BI0100001114 |
| 2 | [7.20.2]Brick work with common burnt clay modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement Mortar 1:6 (1 cement : 6 coarse sand) | - | per cum | 4,146 | - | BI01010001010000000000000515BI0100001115 |
| 3 | [11.5.4]12 mm cement plaster of mix : 4. 1:6 (1 cement: 6 fine sand) | 1 | per sqm | 104 | ₹103.9 | BI01010001010000000000000515BI0100001116 |
| 4 | 6.16]Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | 1 | per cum | 6,113 | ₹6,106.89 | BI01010001010000000000000515BI0100001117 |
| 5 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more | - | per kg | 66 | - | BI01010001010000000000000515BI0100001118 |
| 6 | [21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening | - | Each | 1,155 | - | BI01010001010000000000000515BI0100001119 |
| 7 | [22.198.2]Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design : 2. With 20 mm diameter round bar | - | Each | 207 | - | BI01010001010000000000000515BI0100001120 |
| 8 | [6.30.2]Centering and shuttering including strutting, propping etc. and removal of form for 2. Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. | 1 | per sqm | 282 | ₹281.72 | BI01010001010000000000000515BI0100001121 |
| 9 | Making connection in existing sewer line running 200 mm i/d complete in all respect. | - | Each | 17,000 | - | BI01010001010000000000000515BI0100001122 |
| 10 | [6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 1 | per cum | 2,442 | ₹2,439.56 | BI01010001010000000000000515BI0100001123 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.90 MB
BOQ_600786.xls
BOQ • 0.35 MB
AD0163873.pdf
Additional Documents • 0.25 MB
Download all tender documents and submit your bid