| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹83.3 LAccepted-AOC NEAR JODHKA HANDLOOM PUREWAL COLONY PANIPAT HARYANA 132105 | PANIPAT | PANIPAT | HARYANA | 132105 | L1 | Accepted-AOC Being L1 bidder for overall items of NIT | |
| 2 | L2₹1.1 Cr+₹24.5 L (29.4%)Rejected-Finance MCF 890 F BLOCK MCF 890 SANJAY COLONY SANJAY COLONY SECTOR 23 VILLAGE TOWN FARIDABAD CITY FARIDABAD FARIDABAD HARYANA 121005 INDIA | FARIDABAD | HARYANA | 121005 | L2 | Rejected-Finance Being L2 bidder | |
| 3 | L3₹1.3 Cr+₹43.6 L (52.4%)Rejected-Finance 549 E KANSHI NAGAR MODEL TOWN AMBALA CITY HARYANA 134003 | AMBALA CITY | AMBALA | HARYANA | 134003 | L3 | Rejected-Finance Being L3 bidder | |
| 4 | L4₹1.5 Cr+₹64.6 L (77.6%)Rejected-Finance SITE OFFICE PTPS PANIPAT | PANIPAT | PANIPAT | HARYANA | L4 | Rejected-Finance Being L4 bidder |
Tender Value
Refer Docs
EMD Value
₹2.0 L
Closing Date
8 Nov 2024, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Anurag Jain
Executive Engineer BMD-IV for CE/PTPS UNIT-6 PTPS Panipat
TWO YEARS RATE CONTRACT FOR RUNNING MAINTENANCE OF BALL TUBE MILLS (BBD-4760), GRAVIMETRIC FEEDERS ETC. OF 210MW, UNIT-6, PTPS, PANIPAT
2024_HBC_405230_1
2024C670345B 224D 4429 A913 9E7A64813B5A713PGC
Open Tender
Machineries/ Mechanical Engg Items
Works
730 days
ASSAN KHURD
A) Bidders to have successfully carried out the work of maintenance of Bowl or Ball Tube Coal Mills, Coal Mill reject systems and Coal handling plant systems of generating Units of 110 MW or above and should have a minimum 01-year experience
2 documents required · 2 mandatory
₹1,180
₹2.0 L
Yes
22 Jan 2025
19 Oct 2024
12 Nov 2024
19 Oct 2024
8 Nov 2024
19 Oct 2024
19 Oct 2024 - 8 Nov 2024
Amount
Unit Rates to be quoted for Ist year
PART-A (Annexure-A attached) Daily General, Routine Mtc./Break-down Mtc. of Coal Mills, Gravimetric feeders, Seal Air Fans, Fire Fighting and steam inerting system of Unit-6 coal mills, covered under Item No.1 to 5 of Part-A, Annexure-IV of the scope of work.
Part-B UNIT RATE ITEMS (ANNEXURE-B attached) Inspection of Girth Gear and Pinion teeth and adjustment of Pinion for getting required matching and clearances. It includes opening & refixing of sound hood Panels, grease distribution Panel & its lines, girth gear seal air belt & its adjustment also, replacement of Pinion labyrinth seal & pinion bearing servicing, clearance adjustment & filling of fresh grease etc. and normalization.
Removing & refixing of pinion along with DE & NDE bearing housing. It includes replacement of bearing on either end and normalization.
Overhauling of the main reducer, including replacement of coupling halves, bearings, seals, gears, shafts or any other worn out/damaged components if required and normalization.
Replacement of main reducer with new/repaired & serviced reducer and normalization.
Replacement of Aux. reducer and its cleaning, servicing complete work and normalization.
Checking and replacement of mill drive system i.e. Auxiliary motor to Pinion including opening, servicing and refixing of couplings complete work and normalization.
Inspection of support bearing including cleaning of internals & oil spray nozzles, checking of bearing clearance & shell lift and replacement of window gaskets, if required and normalization.
Replacement/opening, repairing & refixing of support bearing liner including shifting the cradle inside the mill and lifting the shell for liner replacement, checking & adjustment of bearing clearances and shell lift and normalization.
Alignment of driving pinion with main reducer, main reducer with main motor and main motor with Auxiliary reducer.
Replacement/dismantlement, complete servicing & assembly of screw conveyor assembly including opening & refixing hot air box, replacement/repair of drive bars & protecting sleeves and screw conveyor alignment, replacement, removal & refixing of bearing housing, replacement of half wear sleeves and felt seals. Adjustment of bearing housing for getting equal clearance in rewelding. Checking & adjustment of clearance of screw conveyor flange with conveyor body. Replacement/repair of hot air tube/body liners of screw conveyor assembly and locking & straightening of ribbon at coal inlet end and normalization.
Replacement of screw conveyor ribbon(complete) including vertical positioning of the screw conveyor assembly and alignment of new ribbon with other ribbons, cutting and removal of old ribbon and chain links and welding on new ribbon, locking & straightening of ribbon at coal inlet end and final adjustment of ;chain links for getting proper running clearances in the trunion tube & normalization.
Replacement/repositioning of liner plates of mill shell including perfect site cleaning, grinding of liners sides, tightening of liner bolts after 50% and 100% ball charging, readjustment of shell liners for shell balancing and normalization.
Removal of balls from mill shell: a) Segregation of balls of more than 20mm dia and filling & sealing in the drums(per drum)
b) Segregation of balls of less than 20mm dia and filling & sealing in drums and transporting to scrap yard (per drum)
Initial Ball charging to mill including transportation of balls from stores (while mills are under capital shutdown or after complete segregation of grinding media) per ton.
Replacement/readjustment of girth gear seal air belt including perfect cleaning of sealing surface, seal counter flange, and the existing belt(for adjustment purpose) and providing proper stiffeners, air tightness check and normalization.
Replacement/readjustment of trunion seal air gasket including perfect cleaning of sealing surface, seal counter flange and providing proper stiffeners, air tightness & normalization.
Replacement of Trunion Tube liners including removal of old liner and fixing of new liner and normalisation. The activity does not involve the removal of the Hot Air Box.
Replacement/Dismantlement, repair and reassembly of classifier outlet gates body and plate including replacement of seals, brass bushing and any other worn out component if any & normalization.
Replacement of ceramic tiles to reduce wear out of classifier outlet gates and normalization.
Replacement/removing, repair & refixing of transit pieces and T pieces including all cutting & welding work and normalization.
Replacement/removing & refixing of purge air expansion joint and purge air duct and all cutting & welding and normalization.
Replacement/removing & refixing of mill outlet elbow including replacement of spool pieces at its outlet pipe and normalization.
Replacement/removing & refixing of orifices in the PF Pipe line and normalization.
Replacement/removing & refixing of Rockwell coupling including replacement of coupling gaskets and normalization.
Putting patch by welding for attending coal leakage at any point, Length, width & thickness of patch piece about 300X250X12.5mm.
Replacement of rubber gaskets of victaulic coupling & normalization.
Replacement of long ceramic bend and normalization.
Replacement of short ceramic bend and normalization.
Replacement/removing & refixing of PF Pipe of 22” dia up to length of 2 Mtr. In the fuel pipe lines & normalization.
Replacement of PF pipe of dia 22” of length more than 2 Mtrs. & up to 5 Mtrs. Long in the fuel pipe line and normalization.
Replacement of centre feed pipe cone(Raw Coal Chute) at the Gravimetric feeder outlet and normalization.
Clearing of chocking of one PF Pipe from classifier outlet to Furnace and normalization.
Clearing of chocking of centre feed pipe from Gravimetric feeder out to mill inlet(either end) and normalization.
Complete Dismantlement, servicing & assembly of Ball feeding gate, burner outlet gate, feeder inlet gate & outlet gate including replacement of any damaged/worn out component if any and normalization.
Servicing & adjustment of damper including replacement of any component, if required, and normalization a) Hot air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization b) Cold air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization c) Mixed air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization d) By pass air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization e) Purge air damper.
Replacement/opening & refixing of feeder belt including dismantlement and assembly of all relevant components and belt tracking and normalization.
Servicing/Replacement of Dyno Drive System of R.C. Feeders & normalization. It includes replacement of worn out/damaged mechanical parts.
Servicing / Replacement of Main Drive Gear Box & normalization .It includes replacement of worn out/damaged components.
Supply of following manpower for the works on Boiler Area other than above stipulated works with required T & P:- a) Skilled labour
Supply of following manpower for the works on Boiler Area other than above stipulated works with required T & P:-( b) Unskilled labour
Unit Rates to be quoted for 2nd year
PART-A (Annexure-A attached) Daily General, Routine Mtc./Break-down Mtc. of Coal Mills, Gravimetric feeders, Seal Air Fans, Fire Fighting and steam inerting system of Unit-6 coal mills, covered under Item No.1 to 5 of Part-A, Annexure-IV of the scope of work.
Part-B UNIT RATE ITEMS (ANNEXURE-B attached) Inspection of Girth Gear and Pinion teeth and adjustment of Pinion for getting required matching and clearances. It includes opening & refixing of sound hood Panels, grease distribution Panel & its lines, girth gear seal air belt & its adjustment also, replacement of Pinion labyrinth seal & pinion bearing servicing, clearance adjustment & filling of fresh grease etc. and normalization.
Removing & refixing of pinion along with DE & NDE bearing housing. It includes replacement of bearing on either end and normalization.
Overhauling of the main reducer, including replacement of coupling halves, bearings, seals, gears, shafts or any other worn out/damaged components if required and normalization.
Replacement of main reducer with new/repaired & serviced reducer and normalization.
Replacement of Aux. reducer and its cleaning, servicing complete work and normalization.
Checking and replacement of mill drive system i.e. Auxiliary motor to Pinion including opening, servicing and refixing of couplings complete work and normalization.
Inspection of support bearing including cleaning of internals & oil spray nozzles, checking of bearing clearance & shell lift and replacement of window gaskets, if required and normalization.
Replacement/opening, repairing & refixing of support bearing liner including shifting the cradle inside the mill and lifting the shell for liner replacement, checking & adjustment of bearing clearances and shell lift and normalization.
Alignment of driving pinion with main reducer, main reducer with main motor and main motor with Auxiliary reducer.
Replacement/dismantlement, complete servicing & assembly of screw conveyor assembly including opening & refixing hot air box, replacement/repair of drive bars & protecting sleeves and screw conveyor alignment, replacement, removal & refixing of bearing housing, replacement of half wear sleeves and felt seals. Adjustment of bearing housing for getting equal clearance in rewelding. Checking & adjustment of clearance of screw conveyor flange with conveyor body. Replacement/repair of hot air tube/body liners of screw conveyor assembly and locking & straightening of ribbon at coal inlet end and normalization.
Replacement of screw conveyor ribbon(complete) including vertical positioning of the screw conveyor assembly and alignment of new ribbon with other ribbons, cutting and removal of old ribbon and chain links and welding on new ribbon, locking & straightening of ribbon at coal inlet end and final adjustment of ;chain links for getting proper running clearances in the trunion tube & normalization.
Replacement/repositioning of liner plates of mill shell including perfect site cleaning, grinding of liners sides, tightening of liner bolts after 50% and 100% ball charging, readjustment of shell liners for shell balancing and normalization.
Removal of balls from mill shell: a) Segregation of balls of more than 20mm dia and filling & sealing in the drums(per drum)
b) Segregation of balls of less than 20mm dia and filling & sealing in drums and transporting to scrap yard (per drum)
Initial Ball charging to mill including transportation of balls from stores (while mills are under capital shutdown or after complete segregation of grinding media) per ton.
Replacement/readjustment of girth gear seal air belt including perfect cleaning of sealing surface, seal counter flange, and the existing belt(for adjustment purpose) and providing proper stiffeners, air tightness check and normalization.
Replacement/readjustment of trunion seal air gasket including perfect cleaning of sealing surface, seal counter flange and providing proper stiffeners, air tightness & normalization.
Replacement of Trunion Tube liners including removal of old liner and fixing of new liner and normalisation. The activity does not involve the removal of the Hot Air Box.
Replacement/Dismantlement, repair and reassembly of classifier outlet gates body and plate including replacement of seals, brass bushing and any other worn out component if any & normalization.
Replacement of ceramic tiles to reduce wear out of classifier outlet gates and normalization.
Replacement/removing, repair & refixing of transit pieces and T pieces including all cutting & welding work and normalization.
Replacement/removing & refixing of purge air expansion joint and purge air duct and all cutting & welding and normalization.
Replacement/removing & refixing of mill outlet elbow including replacement of spool pieces at its outlet pipe and normalization.
Replacement/removing & refixing of orifices in the PF Pipe line and normalization.
Replacement/removing & refixing of Rockwell coupling including replacement of coupling gaskets and normalization.
Putting patch by welding for attending coal leakage at any point, Length, width & thickness of patch piece about 300X250X12.5mm.
Replacement of rubber gaskets of victaulic coupling & normalization.
Replacement of long ceramic bend and normalization.
Replacement of short ceramic bend and normalization.
Replacement/removing & refixing of PF Pipe of 22” dia up to length of 2 Mtr. In the fuel pipe lines & normalization.
Replacement of PF pipe of dia 22” of length more than 2 Mtrs. & up to 5 Mtrs. Long in the fuel pipe line and normalization.
Replacement of centre feed pipe cone(Raw Coal Chute) at the Gravimetric feeder outlet and normalization.
Clearing of chocking of one PF Pipe from classifier outlet to Furnace and normalization.
Clearing of chocking of centre feed pipe from Gravimetric feeder out to mill inlet(either end) and normalization.
Complete Dismantlement, servicing & assembly of Ball feeding gate, burner outlet gate, feeder inlet gate & outlet gate including replacement of any damaged/worn out component if any and normalization.
Servicing & adjustment of damper including replacement of any component, if required, and normalization a) Hot air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization b) Cold air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization c) Mixed air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization d) By pass air damper
Servicing & adjustment of damper including replacement of any component, if required, and normalization e) Purge air damper.
Replacement/opening & refixing of feeder belt including dismantlement and assembly of all relevant components and belt tracking and normalization.
Servicing/Replacement of Dyno Drive System of R.C. Feeders & normalization. It includes replacement of worn out/damaged mechanical parts.
Servicing / Replacement of Main Drive Gear Box & normalization .It includes replacement of worn out/damaged components.
Supply of following manpower for the works on Boiler Area other than above stipulated works with required T & P:- a) Skilled labour
Supply of following manpower for the works on Boiler Area other than above stipulated works with required T & P:-( b) Unskilled labour
RM TRIPATHI PRIVATE LIMITED (BID ID -1164618)
KG ASHTECH PVT. LTD, (BID ID -1163757)
APEX PROJECTS (BID ID -1164589)
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .