| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹4.5 CrAdmitted-Finance | -27.77% | ₹4.5 Cr | L1 | Admitted-Finance |
| 2 | L2₹5.4 CrAdmitted-Finance | -12.37% | ₹5.4 Cr | L2 | Admitted-Finance |
| 3 | L3₹5.9 CrAdmitted-Finance | -5.33% | ₹5.9 Cr | L3 | Admitted-Finance |
Tender Value
₹6.2 Cr
EMD Value
₹12.4 L
Closing Date
27 Jul 2026, 12:00 pmClosed
EECD V
EECD V IFC Deptt Paryavaran Complex Saidulajab ND-30
Construction of Double storey Community Hall in K2 Block in Devli Assembly Constituency AC-47.
2026_IFC_295693_1
NIT-35/2026-27/EECD-V/IFCD
Open Tender
Civil Works
Works
365 days
Devli AC-47
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹12.4 L
28 Jul 2026
21 Jul 2026
27 Jul 2026
21 Jul 2026
27 Jul 2026
21 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. All kinds of soil | 1,076 | Cubic metre | 177.5 | ₹1,90,990 |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | 960 | Cubic metre | 196 | ₹1,88,160 |
| 3 | Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) Along external wall where the apron is not provided using chemical emulsion @ 7.5 litres / sqm of the vertical surface of the substructure to a depth of 300mm including excavation channel along the wall & rodding etc. complete: With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration | 117 | metre | 38.9 | ₹4,551.3 |
| 4 | Supplying chemical emulsion in sealed containers including delivery as specified. Chlorpyriphos/ Lindane emulsifiable concentrate of 20% | 262 | litre | 234.75 | ₹61,504.5 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 134 | Cubic metre | 6,812 | ₹9,12,808 |
| 6 | Providing and laying damp-proof course 40 mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5 mm nominal size derived from natural sources) | 139 | Square metre | 410.85 | ₹57,108.15 |
| 7 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement.All works upto plinth level Concrete of M25 grade with minimum cement content of 330 kg /cum. | 116 | Cubic metre | 9,504.75 | ₹11,02,551 |
| 8 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cemenAll works above plinth level upto floor V level. Concrete of M25 grade with minimum cement content of 330 kg /cum. | 376 | Cubic metre | 9,860.4 | ₹37,07,510.4 |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 78,720 | Kilogram | 107.85 | ₹84,89,952 |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form for. Foundations, footings, bases of columns, etc. for mass concrete | 188 | Square metre | 392.15 | ₹73,724.2 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.31 MB
BOQ_393433.xls
BOQ • 0.88 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].