EXECUTIVE ENGINEER CIVIL BR III KMC
109 M A K A SARANI KOLKATA 700054
RESTORATION OF PAVER BLOCK PASSAGE AT 16/1/1/41/11, B.B. GHOSH SARANI AND ITS SURROUNDING AREAS IN WARD NO-14 EXCAVATED BY C.E.S.C
2026_KMC_1044464_1
KMC/EE-III/014/11/26-27
Open Tender
CIVIL WORKS
Percentage
30 days
EXECUTIVE ENGINEER CIVIL BR III KMC
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹6,000
6 Oct 2026
6 Oct 2026
29 Oct 2026
6 Oct 2026
27 Oct 2026
6 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in cutting to form road section in correct profile including removal of spoil not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post work | 33.34 | M3 | 79.9 | ₹2,664.03 |
| 2 | ORDINARY CEMENT CONCRETE ( MIX 1:2:4 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES | 16.67 | M3 | 5,498 | ₹91,657.16 |
| 3 | BUILDING WORKS (D) Flooring A. ORIGINAL WORKS 48. Supplying & laying as per IRC-SP:063-2004 paver unit of any shade of approved quality as per relevant IS code, laid in pattern as directed in pavement, footpath, driveway (paver block only), etc including necessary underlay complete in all respect with all labour and material. [Border concrete if necessary to be paid separately]. Note: Sub-grade CBR should not be less than 5. (b) 50 mm thick interlocking designer concrete paver block M- 30 grade for non-traffic zone,buiding premises,garden,parks,domestic drive as per IS: 15658- 2006(over 20-30 mm medium sand bed on 200mm thk bound gnaular /granular base course including cost of sand for sand bed but excluding cost of base course & subgrade preparation.) (ii) Coloured Decorative | 33.34 | SQM | 875 | ₹29,174.25 |
| 4 | Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary. Note:- Add cost at site of the materials to arrive at the complete rate. The compaction factor for dry, clean sand may be taken as 0.835. (The payment is to be made on the basis of finished compacted volume). d) For Coarse Sand | 11.11 | M3 | 1,502.72 | ₹16,701.23 |
| 5 | Laying of interlocking Paver Blocks as per approved design over 20-30mm th medium yellow sand bed with true to line,lavelling,proper compaction with vibrator etc. with jointing with kerb/edge should be made with Cement Concrete (1:2:4)etc. as per the direction of the Engineer-in-charge and including cost of materials,labour etc. complete | 824.81 | SQM | 124 | ₹1,02,276.44 |
| 6 | Raising manhole cover and frame with CBW (1:4), 250mm thick up to 100mm high with 20mm thick sand and cement plaster including finishing with neat cement after cutting the asphaltum pavement and taking out and re-fixing the existing manhole cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13)) | 4 | EA | 2,070.03 | ₹8,280.12 |
| 131 | Estimated amount | - | - | - | - |
| 132 | Add: 9%SGST | 1 | LS | 13,091.41 | ₹13,091.41 |
| 133 | Add: 9%CGST | 1 | LS | 13,091.41 | ₹13,091.41 |
| 134 | 1% LWC | 1 | LS | 2,443.73 | ₹2,443.73 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.90 MB
Tendernotice_2.pdf
PDF • 5.35 MB
Tendernotice_3.pdf
PDF • 0.81 MB
Tendernotice_4.pdf
PDF • 0.70 MB
BOQ_2561688.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .