| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 985721.98₹9.9 LAccepted-Finance SE MOTTUR VILLAGE SERPAPATTU POST THANDARAMPET TALUK TIRUVANNAMALAI DISTRICT 606753 | TIRUVANNAMALAI | TAMIL NADU | 606753 | ₹9.9 L | 985721.98 | Accepted-Finance Least Quote Value |
| 2 | 988704.18₹9.9 LRejected-Finance NO 38 BAJANAI KOVIL STREET ARUTHIRAPATTU VILLAGE AND POST TIRUVANNAMALAI TALUK TIRUVANNAMALAI DISTRICT | TIRUVANNAMALAI | TIRUVANNAMALAI | TAMIL NADU | ₹9.9 L | 988704.18 | Rejected-Finance Highest Quote Value |
| Sl No | Description | Qty | Unit | P.M.RADHAKRISHNAN L1 | Elumalai R L2 |
|---|---|---|---|---|---|
| 1.00Construction of Culvert in (3m Vent ) Adidaravidar Kudiyirupu near Threshing Floor @ Aruthirapattu Panchayat | |||||
| 1.01 | Earthwork excavation in hard soil with intral lead and lift asper SS 20B for foundation | 58.22 | Cum | 263.78 ₹15,357.27 | 263.78 ₹15,357.27 |
| 1.02 | Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification | 8.96 | Cum | 5,389.45 ₹48,289.47 | 5,389.45 ₹48,289.47 |
| 1.03 | Cement Concrete 1:3:6 (One Cement, Four M.Sand and eight hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification | 44.96 | Cum | 6,143.28 ₹2.8 L | 6,143.28 ₹2.8 L |
| 1.04 | Cement concrete 1:2:4 mix using 20 mm ISS metal including cost and conveyance of all materials to site and all labour charges etc completd. | 23.27 | Cum | 6,688.85 ₹1.6 L | 6,688.85 ₹1.6 L |
| 1.05 | Cement concrete 1:2:4 mix using 20 mm ISS metal including cost and conveyance of all materials to site and all labour charges etc completd. | 3.9 | Cum | 6,688.85 ₹26,086.52 | 6,688.85 ₹26,086.52 |
| 1.06 | Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. | 8.1 | Cum | 9,125 ₹73,912.50 | 9,125 ₹73,912.50 |
| 1.07 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (BGL) | 63.18 | Sqm | 547.5 ₹34,591.05 | 587.5 ₹37,118.25 |
| 1.08 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (AGL) | 108.18 | Sqm | 1,093 ₹1.2 L | 1,093 ₹1.2 L |
| 1.09 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire) | 0.88 | MT | 91,910.02 ₹80,880.82 | 91,910.02 ₹80,880.82 |
Tender Value
Refer Docs
EMD Value
₹10,000
Closing Date
26 Dec 2025, 4:00 pmClosed
BLOCK DEVELOPEMENT OFFICER(VP)
BLOCK DEVELOPEMENT OFFICE (TIRUVANNAMALAI)
Construction of Culvert in (3.00m)vent Adi Dravidar Kudiyiruppu near Threashing Floor at Aruthirapattu Panchayat in PMAGY 25-26
2025_RDTN_632777_1
A19/3721/2025 Dt. 08.12.2025
Open Tender
Civil Works
90 days
TIRUVANNAMALAI
REFER TENDER DOCUMENT
2 documents required · 2 mandatory
₹0
₹10,000
27 Dec 2025
16 Dec 2025
26 Dec 2025
16 Dec 2025
26 Dec 2025
16 Dec 2025
Amount
Construction of Culvert in (3m Vent ) Adidaravidar Kudiyirupu near Threshing Floor @ Aruthirapattu Panchayat
Earthwork excavation in hard soil with intral lead and lift asper SS 20B for foundation
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
Cement Concrete 1:3:6 (One Cement, Four M.Sand and eight hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
Cement concrete 1:2:4 mix using 20 mm ISS metal including cost and conveyance of all materials to site and all labour charges etc completd.
Cement concrete 1:2:4 mix using 20 mm ISS metal including cost and conveyance of all materials to site and all labour charges etc completd.
Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc.
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (BGL)
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (AGL)
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire)
Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Tarpaper
Weephole
GST Amount for providing Service to Government Contract Works for the above Construction Works. {GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Elumalai R (BID ID -1543769)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.