| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹91.8 LAccepted-AOC ADITYAPUR 02 SARAIKELA KHARSAWAN | EAST SINGHBUM | JHARKHAND | 831002 | ₹91.8 L | L1 | Accepted-AOC EELTNO220DT31082026 |
| 2 | L2₹96.6 L+₹4.8 L (5.21%)Rejected-AOC BARIDIH | GODDA | JHARKHAND | 813206 | ₹96.6 L+₹4.8 L (5.21%) | L2 | Rejected-AOC EELTNO220DT31082026 |
Tender Value
₹92.0 L
EMD Value
₹1.8 L
Closing Date
20 Jun 2026, 5:00 pmClosed
E.E. NREP JAMSHEDPUR, EAST SINGHBHUM
E.E. OFFICE NREP JAMSHEDPUR, EAST SINGHBHUM
CONSTRUCTION OF PCC ROAD FROM GURABANDHA TOWARDS ARJUNBERA SABAR TOLA BASTI.
2026_RDSPL_115157_1
NREP/JSR/Epro-02/2026-27/GR-3
Open Tender
Civil Works
Percentage
180 days
UNDER GURABANDHA BLOCK.
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹1.8 L
Yes
11 Sept 2026
13 Jun 2026
22 Jun 2026
13 Jun 2026
20 Jun 2026
13 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in foundation trenches in ordinary soil (vide classfication of soil item - A) and disposal of excavated earth a obtained to a distance up to 50M including all lifts with leveling ramming the foundation trenches removing roots of trees shurbs all complete as per approved design and per building specification and direction of E/I. | 1,114.82 | M3 | 167.33 | ₹1,86,542.83 |
| 2 | Compacting original ground supporting embankment loosing, levelling --do-- | 671.58 | M3 | 62.3 | ₹41,839.43 |
| 3 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401. | 671.58 | M3 | 1,458.8 | ₹9,79,700.9 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering All work up to plinth level : 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) | 899.91 | M3 | 4,961.73 | ₹44,65,110.44 |
| 5 | Providing separation membrane of impermeable plastic sheeting 125mm thick. | 4,405.2 | M² | 13 | ₹57,267.6 |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | 639.49 | M² | 194.5 | ₹1,24,380.81 |
| 7 | Filling in foundation trenches and plinth in layers. Not exceeding 150 mm thick well watered, rammed fully compacted and fine dressed with earth obtained after cutting within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 149.99 | M3 | 128.88 | ₹19,330.71 |
| 8 | Carriage of materials
Cement | 370.61 | MT | 777.7 | ₹2,88,223.4 |
| 9 | Sand | 861.09 | M³ | 748.6 | ₹6,44,611.97 |
| 10 | Stone Chips | 923.1 | M³ | 703.96 | ₹6,49,825.48 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.62 MB
SBDNIT02GR3.pdf
Tender Documents • 0.53 MB
BOQ_155710.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .