| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹77.8 LAccepted-AOC 16 PRATAP NAGAR CHARBHUJA RAWATBHATA RAJASTHAN 323307 | RAWATBHATA | CHITTORGARH | RAJASTHAN | 323307 | L1 | Accepted-AOC Lowest bidder | |
| 2 | L2₹80.0 L+₹2.1 L (2.70%)Rejected-Finance | L2 | Rejected-Finance Other than lowest bidder. | |
| 3 | L3₹85.6 L+₹7.8 L (9.96%)Rejected-Finance | L3 | Rejected-Finance Other than lowest bidder. | |
| 4 | L4₹90.0 L+₹12.1 L (15.6%)Rejected-Finance | L4 | Rejected-Finance Other than lowest bidder. | |
| 5 | L5₹1.3 Cr+₹48.6 L (62.5%)Rejected-Finance H NO 39 3 CHANNI HIMMAT JAMMU 180015 J K | JAMMU | JAMMU AND KASHMIR | 180015 | L5 | Rejected-Finance Other than lowest bidder. |
| Sl No | Description | Qty | Unit | M/S VED PAUL MAHAJAN L3 | M/S ANIL MAHAJAN L5 | M/s Hansi Builders and Consultants L2 | BR CONSTRUCTIONS L4 | M/S GUPTA CONSTRUCTION CO. L1 |
|---|---|---|---|---|---|---|---|---|
| 1.00NOTE: Schedule ‘A’ Part I to VIII under Ser No. 1.10 to 1.80 are Prepriced by MES. | ||||||||
| 1.10 | Lump sum price worked out by the Contractor for “BUILDING WORK” as listed in Schedule ‘A’ Part-I | 1 | Lump sum | 80,00,000 ₹80,00,000 | 1,15,00,000 ₹1,15,00,000 | 72,80,000 ₹72,80,000 | 84,24,000 ₹84,24,000 | 72,00,000 ₹72,00,000 Lowest |
| 1.20 | Lump sum price worked out by the Contractor for “INTERNAL WATER SUPPLY WORKS” as listed in Schedule ‘A’ Part-II | 1 | Lump sum | 24,500 ₹24,500 | 65,000 ₹65,000 | 29,207 ₹29,207 | 28,000 ₹28,000 | 20,000 ₹20,000 Lowest |
| 1.30 | Lump sum price worked out by the Contractor for “INTERNAL ELECTRIFICATION WORKS” as listed in Schedule ‘A’ Part-III | 1 | Lump sum | 2,90,000 ₹2,90,000 | 4,55,000 ₹4,55,000 | 3,50,000 ₹3,50,000 | 2,81,000 ₹2,81,000 Lowest | 3,00,000 ₹3,00,000 |
| 1.40 | Lump sum price worked out by the Contractor for “EARTHWORK FOR SCH ‘A’ PART- II TO PART- VIII” as listed in Schedule ‘A’ Part-IV | 1 | Lump sum | 25,600 ₹25,600 | 75,000 ₹75,000 | 29,125 ₹29,125 | 20,500 ₹20,500 | 20,000 ₹20,000 Lowest |
| 1.50 | Lump sum price worked out by the Contractor for “EXTERNAL ELECTRIC SUPPLY WORKS” as listed in Schedule ‘A’ Part-V | 1 | Lump sum | 50,000 ₹50,000 | 1,10,000 ₹1,10,000 | 55,599 ₹55,599 | 46,500 ₹46,500 Lowest | 50,000 ₹50,000 |
| 1.60 | Lump sum price worked out by the Contractor for “EXTERNAL WATER SUPPLY WORKS” as listed in Schedule ‘A’ Part-VI | 1 | Lump sum | 5,000 ₹5,000 | 25,000 ₹25,000 | 6,125 ₹6,125 | 4,500 ₹4,500 Lowest | 6,000 ₹6,000 |
| 1.70 | Lump sum price worked out by the Contractor for “ROADS/PATH WORKS” as listed in Schedule ‘A’ Part-VII | 1 | Lump sum | 95,000 ₹95,000 Lowest | 2,60,000 ₹2,60,000 | 1,27,518 ₹1,27,518 | 1,11,500 ₹1,11,500 | 1,15,000 ₹1,15,000 |
| 1.80 | Lump sum price worked out by the Contractor for “SEWAGE DISPOSAL WORKS” as listed in Schedule ‘A’ Part-VIII | 1 | Lump sum | 40,000 ₹40,000 Lowest | 1,20,000 ₹1,20,000 | 62,603 ₹62,603 | 52,500 ₹52,500 | 50,000 ₹50,000 |
| 2.00SCHEDULE `A' PART - IX MISC B/R & E/M ITEMS is not prepriced by MES and prepriced rates indicates 0.0 under column 6 signified this fact only. | ||||||||
Tender Value
₹74.5 L
EMD Value
₹1.4 L
Closing Date
12 Mar 2026, 6:00 pmClosed
Col Amit Bhardwaj
HQ CWE Jammu PIN-180003
PROVN OF ORs LIVING LINE AND PROVN OF STORE SHED AT MIL STN JAMMU UNDER GE SATWARI
2025_MES_744300_2
CWE/JP-70/2025-26
Open Tender
Civil Works
Works
365 days
GE Satwari
As per tender documents
9 documents required · 9 mandatory
₹1,000
Yes
GE Satwari
₹1.4 L
Yes
2 Apr 2026
19 Feb 2026
14 Mar 2026
19 Feb 2026
12 Mar 2026
5 Mar 2026
19 Feb 2026 - 23 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.1 | Lump sum price worked out by the Contractor for “BUILDING WORK” as listed in Schedule ‘A’ Part-I | 1 | Lump sum | 85,00,000 | ₹85,00,000 |
| 1.2 | Lump sum price worked out by the Contractor for “INTERNAL WATER SUPPLY WORKS” as listed in Schedule ‘A’ Part-II | 1 | Lump sum | 29,207.83 | ₹29,207.83 |
| 1.3 | Lump sum price worked out by the Contractor for “INTERNAL ELECTRIFICATION WORKS” as listed in Schedule ‘A’ Part-III | 1 | Lump sum | 3,52,643.93 | ₹3,52,643.93 |
| 1.4 | Lump sum price worked out by the Contractor for “SITE CLEARANCE AND EARTHWORK” as listed in Schedule ‘A’ Part-IV | 1 | Lump sum | 80,570.82 | ₹80,570.82 |
| 1.5 | Lump sum price worked out by the Contractor for “EXTERNAL ELECTRIC SUPPLY WORKS” as listed in Schedule ‘A’ Part-V | 1 | Lump sum | 65,585.4 | ₹65,585.4 |
| 1.6 | Lump sum price worked out by the Contractor for “EXTERNAL WATER SUPPLY WORKS” as listed in Schedule ‘A’ Part-VI | 1 | Lump sum | 7,522.89 | ₹7,522.89 |
| 1.7 | Lump sum price worked out by the Contractor for “ROADS/PATH WORKS” as listed in Schedule ‘A’ Part-VII | 1 | Lump sum | 1,33,061.9 | ₹1,33,061.9 |
| 1.8 | Lump sum price worked out by the Contractor for “SEWAGE DISPOSAL WORKS” as listed in Schedule ‘A’ Part-VIII | 1 | Lump sum | 74,820.78 | ₹74,820.78 |
| 2SCHEDULE `A' PART - IX MISC B/R & E/M ITEMS is not prepriced by MES and prepriced rates indicates 0.0 under column 6 signified this fact only. | |||||
| 2.1 | INTERNAL WATER SUPPLY WORKS | - | - | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.36 MB
TENDER70.pdf
Tender Documents • 3.19 MB
BOQ_843793.xls
BOQ • 0.32 MB
cori02_merged.pdf
PDF • 35.54 MB
tender70revisedmerged.pdf
PDF • 8.45 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .