Tender ID
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.4 LAccepted-AOC SOUTH THOTTAM PALAKKANTHU PO DINDIGUL WEST TALUK DINDIGUL 624 019 TAMIL NADU | 624019 | L1 | Accepted-AOC WORK ORDER | |
| 2 | L2₹8.7 L+₹33,194.07 (3.96%)Rejected-Finance | L2 | Rejected-Finance Rejected |
| Sl No | Description | Qty | Unit | S PRABHU SELVARAJ CONTRACTOR L1 | Sivakumar Contractor L2 |
|---|---|---|---|---|---|
| 1.0001) Construction of Drama Stage Building at Palaya ettamanayackenpatty H/ O Palakkanuthu ESTIMATE COST : 8.50 Lakhs | |||||
| 2.00 | Earthwork excavation in all clauses of soils and depositing on bank with initial lead and lift for foundation as per ss20B | 19.78 | Cum | 263 ₹5,202.14 Lowest | 273 ₹5,399.94 |
| 3.00 | Cement concrete 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc., complete. | 5.42 | Cum | 5,411 ₹29,327.62 Lowest | 5,627 ₹30,498.34 |
| 4.00 | Brick work in Cement Mortar1:5 (one cement and five sand) using best quality of country bricks of size 8-3/4" x 4-1/4" x 2-1/4" for foundation and basement including curing, etc., complete complying with standard specifiction. | 13.16 | Sqm | 6,098 ₹80,249.68 Lowest | 6,341 ₹83,447.56 |
| 5.00 | Refilling with excavated earth other than sand with an initial head load of 100 mts. and depositing the earth as shown by the departmental officers in layers of not more than 15 cm thick well rammed, watered and consolidated etc. complete complying with standard specification | 9.64 | Cum | 45 ₹433.8 Lowest | 46 ₹443.44 |
| 6.00 | Supplying and filling in foundation, basement, etc with filling sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. | 4.14 | Sqm | 1,777 ₹7,356.78 Lowest | 1,848 ₹7,650.72 |
| 7.00 | Supply and errection of centering for sides and soffits of cc works including cost and conveyance of all materials to site and all labour charges etc., complete. | 129.24 | Sqm | 1,094 ₹1,41,388.56 Lowest | 1,137 ₹1,46,945.88 |
| 8.00 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. | 1.41 | mt | 91,932 ₹1,29,624.12 Lowest | 95,609 ₹1,34,808.69 |
| 9.00 | Reinforced Cement Concrete 1:1.5:3 (One Cement, One and a half sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers | 15.45 | Sqm | 9,152 ₹1,41,398.4 Lowest | 9,518 ₹1,47,053.1 |
| 10.00 | Supply ing and appl ying of two coats of p utty of 3 mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. Tt shall then be sand papered (waterproof abrasive sheet) to give a smooth and even s urface. Any uneven ness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat 1 of putty alter 6 hours of 1st coat of putty and then sand papering (waterproof a bra sive s heet) th e same arte r it is dry and finishing thc surfa ce sm oot hIy, «tc., | 41.48 | Sqm | 308 ₹12,775.84 Lowest | 320 ₹13,273.6 |
Tender Value
Refer Docs
EMD Value
₹9,000
Closing Date
13 Feb 2026, 3:00 pmClosed
The Project Director DRDA Dindigul
The Project Director DRDA Dindigul
Capital Grant Fund Savings and Interest Scheme 2025- 2026 Construction of Drama stage Building - Palaiya Ettamanayakenpatti - Palakanuthu in Reddiyarchatram block of Dindigul District Package No. TN05-127
2026_RDTN_652299_1
DIPR-542-Tender 2026
Open Tender
Civil Works
Item Wise
120 days
DRDA DINDIGUL
Capital Grant Fund Savings and Interest Scheme 2025- 2026 Construction of Drama stage Building - Palaiya Ettamanayakenpatti - Palakanuthu in Reddiyarchatram block of Dindigul District Package No. TN05-127
2 documents required · 2 mandatory
₹0
₹9,000
DRDA DINDIGUL
28 Mar 2026
6 Feb 2026
13 Feb 2026
6 Feb 2026
13 Feb 2026
6 Feb 2026
11 Feb 2026
01) Construction of Drama Stage Building at Palaya ettamanayackenpatty H/ O Palakkanuthu ESTIMATE COST : 8.50 Lakhs
Earthwork excavation in all clauses of soils and depositing on bank with initial lead and lift for foundation as per ss20B
Cement concrete 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all materials to site and all labour charges etc., complete.
Brick work in Cement Mortar1:5 (one cement and five sand) using best quality of country bricks of size 8-3/4" x 4-1/4" x 2-1/4" for foundation and basement including curing, etc., complete complying with standard specifiction.
Refilling with excavated earth other than sand with an initial head load of 100 mts. and depositing the earth as shown by the departmental officers in layers of not more than 15 cm thick well rammed, watered and consolidated etc. complete complying with standard specification
Supplying and filling in foundation, basement, etc with filling sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Supply and errection of centering for sides and soffits of cc works including cost and conveyance of all materials to site and all labour charges etc., complete.
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification.
Reinforced Cement Concrete 1:1.5:3 (One Cement, One and a half sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers
Supply ing and appl ying of two coats of p utty of 3 mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. Tt shall then be sand papered (waterproof abrasive sheet) to give a smooth and even s urface. Any uneven ness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat 1 of putty alter 6 hours of 1st coat of putty and then sand papering (waterproof a bra sive s heet) th e same arte r it is dry and finishing thc surfa ce sm oot hIy, «tc.,
Plastering with cement mortar 1:3 mix to 10mm thick including cost and conveyance of all materials & all labour charges etc., complete.
Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers.
Weathering course in brick jelly lime concrete using broken brick jelly of size 20mm uniform gauge in pure slaked lime (no sand to be used) to the proportion of brick jelly to lime being 32:12.5 by volume and laid over the RCC roof slab in a single layer of required slope and finished by beating the concrete with wooden beaters of approved pattern, keeping the surface constantly wet by sprinkling lime jaggery water, etc., complete as per standard specification and as directed by the deparmental officers.
Finishing the top of roof with one course of machine pressed tiles of size 200mm x 200mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers
White washing two coats with shell lime including cost & conveyance of all materials to site and all labour charges etc.complete.
Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the walls smooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification.
Painting two coats of newly plastered wall surface with ready mixed plastic Exterior emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat etc., complete complying with standard specification.
Towards supply and delivery of steel door as per std. Specification of size 0.90m x 2.00m
Towards supply and delivery of steel window as per std. Specification of size 0.90m x 1.20m.
Supplying and fixing of 110mm dia PVC pipe in position best approved of BIS quality PVC rain water down fall pipes having a pressure of 4 kg. / sq.cm including cost of necessry PVC shoe, PVC bend, cast iron gratings of required diameter and special clamps, brass screws, nails, etc., and fixing of cast iron gratings at junction of parapet and the RCC roof slab including finishing neatly etc., complete. The rate shall be inclusive of cast of removable cast iron grating. The PVC pipe shall be fixed in wall with special type of "U" clamp at the centre of the pipe line in addition to those for more than 3.0 metre pipe length, etc., complete complying with standard specification.
Provisions for Providing and lettering of Name board with work details incluidng all etc.,complete
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.03 MB
BOQ_782162.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .