| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
Refer Docs
EMD Value
₹10,000
Closing Date
28 Oct 2022, 12:00 pmClosed
SE/CEDC/S-II,K.K.Nagar,chennai
110kv ss complex, SE/CEDC/S-II,K.K.Nagar,Chennai
Erection, Maintenance and Dismantling of electrical networks (OH Line and Cable) including Sub-stations maintenance in Tharamani Sub division of Adyar division for a period ending upto 31.03.2023.
2022_EB_256412_1
Spec.no.51-II/22-23,Rate contract for ere,main
Open Tender
Electrical and Maintenance Works
Works
180 days
SE/CEDC/S-II, K.K.Nagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹10,000
Yes
19 Dec 2022
14 Oct 2022
29 Oct 2022
14 Oct 2022
28 Oct 2022
15 Oct 2022
15 Oct 2022 - 28 Oct 2022
Amount
Excavation of Pole pit/Stay Pit
Excavation of Pole pit of size 2'x2'x1/6 of the height of the pole upto 8 mtr pole by using JCB or Manual
Excavation of Pole pit of size 2'x2'x1/6' of the height of the pole for 9 mtr/Square pole by using JCB or Manual
Excavation of RSJ /Rail/tubular pole pit above 9.0 M by using JCB or manual
Excavation of pit in Hard rock place which requires blasting
Excavation of pit in Hard rock place which does not requires blasting (Where Houses are located)
Excavation of Stay pit 2'x2'x5' depth by using JCB or manual
Erection of poles /Stay
Erection of RCC poles/PSC poles/Metal poles up to 8.00 M (27' ) by using JCB or manual
Erection of RCC poles/PSC poles/Metal poles 9.0 M by using JCB or maual
Erection of RSJ , Rail and fabricated poles above 9.0 M by using JCB or maual
Erection of stay set complete
FIXING OF Line Materails
Fixing of HT "V" cross arms(all types) / channel cross arms/guarding Cross arms
Fixing of LT 3 phase cross arms
Fixing of LT Single phase cross arms
Fixing of HT/LT TI Fittings
Fixing of HT pin Insulators 11 KV/ 22 KV/ 33 KV
Fixing of HT 11 KV strain disc.
Fixing of HT 22 KV/33 KV strain disc.
Fixing of LT pin Insulator
Fixing of LT shackle
Fixing of Aluminium Knob
Earthing of pole with pin including looping binding and burying
Earthing of additional Cross arm
Fixing of top channel 15' centre
Fixing of belting angle
Fixing of cross bracing(4 nos angles) 10' Centre
Fixing of cross bracing(4 nos angles) 15' Centre
Fixing of danger board
Erection of Transformer centre set arrangments
Fixing of Distribution Transformer Name Board (Name of the 22/11KV #, Name of the SS and Capacity) including Supply of board (1' x 1.5' x 3 mm thickness) including the cost of paint and labour charges
Fixing of LT Cable arrangements while erecting single pole DT
Fixing of Earth coller for earth pits
Erection of Aluminium bus bar pipe complete for HT bus bar arrangements for DP structure
For Triple pole and four pole structure
Excavation of stay pit by JCB or manual
Erection of stay set complete
LT BUS arrangement
Feeder arrangements with open type fuse units
LT -LAS fixing
Paving and Stringing of Conductor
Paving of Conductor, Stringing, binding, jumpering etc., complete with ACSR for lines with DOG conductor
Paving of Conductor, Stringing, binding, jumpering etc., complete with ACSR for lines with 7/4.09 mm
Paving of Conductor, Stringing, binding, jumpering etc., complete with ACSR for lines with 7/3.35 mm ACSR or 7/3.15 mm AAAC
Paving of Conductor, Stringing, binding, jumpering etc., complete with ACSR for lines with 7/2.59 mm or 7/ 2.50 mm
Painting of Poles and Materials
Numbering of pole by using Enamel paint including cost of paint and painting charges ( 150 diameter with 2.5" height letters or 100x150mm with 2.5"letters)
Painting of Cement Poles by using Distemper paint (Single Coat)
Painting of Metal Poles by using Aluminium paint (Single Coat)
Painting of top channel
Painting of AB switch
Painting cross Bracing (4 Nos. Angles) both 10' & 15' centre
Painting of Transformer (only one coat) upto 100 KVA
Painting of Transformer (only one coat) above 100 KVA
Painting of HG fuse.
Painting of HT metering set and Box
Painting of poles and all other metal parts while erecting new double pole
Painting of poles and all other metal parts while erecting D.P Structure
Painting of pole and all other metal parts while erecting new single pole distribution transformer Structure
Concreting of poles:
Structure Concreting , Concreting of poles with size (2'x2'x5') including cost of Cemnet ,jelly and Sand with a mixture of 1:3:6 and plastering of concrete with ratio 1:2
Sleeve concreting with size (2'x2'x3') including cost of excavation Cement ,jelly and Sand with a mixture of 1:3:6 and plastering of concrete with ratio 1:2 including materials
Stay concreting of Stay with Size 1.5' X 1.5' X 3.0' including cost of 40mm Cement,Jelly and sand (with supply) with mixture 1:3:6 along sleeve concreting and plastering of concrete portion above the ground level with ratio 1:2.
Erection of Structure
Erection of Double Pole Transformer Structure Complete
Excavation of structure pole pit 2' x 2' x 6' by using JCB or manual
Erection of poles by using JCB or manual
Erection of Top channel
Erection of Bed channel
Erection of Cross with stud for bed channel
Belting Angle
Erection of AB switch
Erection of H.G.Fuse
Structure earthing complete with 3 pits and earth loops
HT -LAS fixing
HT jumpering complete
Excavation of stay pit by JCB or manual
Erection of stay set complete
Feeder arrangements with open type fuse units
LT LAS fixing
Erection of Single pole Transformer Structure Complete
Excavation of structure pole pit 2' x 2' x 6' by using JCB or manual
Erection of poles by using JCB or manual
Erection of Tapping channel
Erection of Transformer centre set arrangements
Erection of AB switch
Erection of H.G.Fuse
Structure earthing complete with 3 pits and earth loops
HT -LAS fixing
HT jumpering complete
Excavation of say pit by JCB or Manual
Erection of stay set complete
Feeder arrangements with open type fuse units for 2 feeders
LT LAS fixing
Guarding arrangements
LT split neutral guarding
Flat guarding including fixing of 2 Nos. cross arms HTLT
D.O.T. Crossing
Railway Crossing ( cradle guarding).
. Loading , Unloading and Transporting of Materials
Transport of poles/Materials/ conductors /DT/Metering Set and other materials( excluding loading and unloading charges.)
a). Below 8 Kms.
b). Above 8 Kms. For additional Km.
Loading of poles up to 27' RCC/PSC/Metal poles
Loading of poles 30' RCC/PSC poles and RSJ Pole of all sizes
Unloading of poles
Loading of cement bag of 50Kg.
Unloading of cement bag of 50Kg.
Loading of Transformer oil drum with oil 200 Lit. capacity
Unloading of Transformer oil drum with oil 200 Lit. capacity
Loading of materials
Un-Loading of Materials
Loading and Stacking of Materials
Transporting of poles from road side to pole pit Location including loading and unloading of poles by using JCB or Manual Up to 200 m
Transporting of poles from road side to pole pit including loading and unloading of poles by using JCB or Manual above 200 m
Erection of Transformer
Loading or unloading of Transformer upto 200 KVA and Metering set
Loading or unloading of Transformer above 200 KVA
Erection of Transformer upto 200 KVA including connections
Erection of New Transformer above 200 KVA including connections
Loading/Unloading/Erection of HT Metering set including connections
Resagging of Conductors
Re-sagging of HT line with ACSR 7/4.72 mm Conductor
Re-sagging of HT / LT line with ACSR 7/4.09mm Conductor
Re-sagging of HT / LT line with ACSR 7/3.35mm or AAAC 7/3.15 mm conductor
Re-sagging of HT / LT with ACSR 7/2.59mm or AAAC 7/2.50 mm conductor
Other Works
Erection of street light including fixure fitting
Erection of street light service
Fixing of new SV/MV/LED lamp fittings
Assisting for survey of HT/LT
Hut service fixing
Agricultural service fixing / service
Breaking and Releasing of grills from RCCPSC poles
Releasing of single phase service wire and re-fixing.
Releasing of 3 phase service wire and (upto 50 HP) re-fixing.
Releasing of 3 phase service wire and (above 50 HP) re-fixing.
Labour charges for alteration of Back clamps to suit for the works
Labour charges for alteration of Stay clamps to suit for the works
Fixing of Double Channel X arm/ Double V' cross arm.
Erection of new earth pipe by replacing the corroded earth pipe including burying, looping and binding
Providing LT bus bar arrangement in distn. Trs. Structure location
Fixing of meter on LV side of DT
Earthing of new double pole distribution transformer structure complete
Erection of 3 nos new 10' Earth pipe replacing the corroded earth pipe and renewal of earthing including burying looping and binding.
Earthing of D.P.complete
Earthing of new single pole distribution transformer structure complete
Erection of concrete earth tub to Distribution Transformer earth pipe
Dismantling of detoriated cables/Replacement of various size(120,240 Sq.mm) from Distribution Transformer LT bushing to LT open type clamp and provision of suitable lugs at both the ends.
Dismantling and Erection of LT open type fuse unit Aluminium clamps
Dismantling of Distn. Transformer from structure Transporting to special Maintenance assisting the special maintenance crew in overhauling and reerection at the structure.
a)up to 8Kms
b)Above 8Kms per km
Releasing of ACSR/AAAC conductors from conductor drum and coiling ACSR 7/3.35, 7/2.59, AAAC 7/2.50, 7/3.15 MM (Per/Km.)
Tiding of service connection with erection of clamp jumper in Low tension single phase SC/line,Aerial Board, Fuse unit and looping.
Tiding of service connection with erection of clamp jumper in Low tension three phase line, Aerial Board, Fuse unit and looping.
Renewal of jumper from 22/11 KV line to AB switch to HG Fuse, HG Fuse to Distn. Transformer with PG clamps.
Cutting of coconut leaves /tree branches
Drilling of hole in channel only 3/4" & 1" per hole
Cutting of flat
Cutting of channel
Cutting of Angle
Cutting of pipe
RSJ pole cutting
RSJ pole welding
Providing of line spacers for single phase line
Providing of line spacers for three phase line
Hiring Charges for JCB
Clearing of Jungle
Clearing of scrup in Yard (DT/SS)
Set right the leaning of pole in HT/LT in Pin point
Set right the leaning of pole in HT/LT in Cut point
Erection of LT Shunt Capacitor
Ground patrolling of HT lines during Breakdown
Rectification of snapped HT line during Break down
Rectification of snapped LT line during Break down
Erection of Single phase meters
Erection of Three phase meters
Maintenance of Distribution Transformer
Monthly Maintenance
Maintaining Transformer Yard and earth pits neat and tidy
Cleaning the entire transformer including the bushings
Checking for oil level and reportingif the level is below the mark
Checking the earth connections and watering the earth pits
Checking the oil leaks and reporting if any noticed
Reconditioning the breather (by reactivating Silicagel or replacing it if necessary)
Checking the LT fuses and renewing them if necessary
Quarterly Maintenance
Renewing the HG fuses
Measuring the insulation resistance and Load currents
Annual Maintenance
Lubricating the AB switches and checking their operation
Checking the lines and earth connections of AB switch
Checking the lines and earth connections of HT and LT lightning arresters
Checking the HV and LV bushing connections
Substation Maintenance
Complete maintenance of Power Transformer of all capacities
Complete maintenance of Breaker,CT/PT for 110 KV and above
Complete maintenance of Breaker,CT/PT for capacity less than 110 KV
Complete maintenance of Centre Rotating Switch 110 KV and above
Complete maintenance of Centre Rotating Switch below 110 KV
Replacement of Clamps of all sizes
Complete maintenance of LAS 110 KV and above
Complete maintenance of LAS below 110 KV
Replacement of Jumpers less than 1 metre
Replacement of Jumpers more than 1 metre
Maintenance of earth pits and watering
Cleaning of control and relay panels (Front,Back and inside)
Mainenance of Capacitor Bank cell
Replacement of capacitor bank cell
Replacement of PT Insulator
Replacement of Female/Male contact for 110 KV
Replacement of Female/Male contact for less than 110 KV
Maintenance of Battery
LAYING OF HT CABLE
Excavtion of cable trench 0.6 meters width and 1.2 meters depth including cost
Normal Road (earth)
Tar Road
Concrete Road
Transporting of 11 KV HT cable from departmental stores to work spot by
3x300 sq mm XLPE (1 drum: 200 m)
3x120 sq mm XLPE (1 drum: 200 m)
LAYING OF HT CABLE
Laying of 300 sq mm XLPE cable
Laying of 120 sq mm XLPE cable
Covering HT cable by cement "V" trough after covering the cable with good loose earth including loading, unloading and transport from stores to site and letter painting of feeding details & Cable size on the trough
Refilling with excavated earth layers well consolidated as per std specification including all materials, lead, lift etc., complete.
Transport back any balance cable, empty drums and other materials if any by engaging private vehicle including recoiling, coiling and loading and unloading at both sides from workspot to departmental stores (minimum 2 empty drums)
LAYING OF LT CABLE
Transport of LT cable by engaging private vehicle including recoiling coiling and
240 sq.mm ( 1 drum - 200 meters)
120 sq. mm ( 1 drum - 500 meters)
25 sq. mm ( 1 drum - 500 meters)
16 sq. mm ( 1 drum - 500 meters)
Excavation of cable trench 45 cm width and 75 cm depth including cost of
Normal Road (earth)
Tar Road
Concrete Road
Laying of LT Cables
Laying of 240 sq.mm cable
Laying of 120 sq.mm cable
Laying of 25 sq.mm cable
Laying of 16 sq.mm cable
TRENCHLESS CABLE LAYING(NEW/RECTIFICATION)
Laying of cable using Trenchless technique with scanner without pipes
upto 50 mt LT/11 KV/33 KV single run
above 50 mt LT/11 KV/33 KV single run
ERECTION OF PILLAR BOX
Erection of pillar box including excavation of foundation pits as per standard
Mini pillar boxes for 3 feet
4/6/8 way pillar box 3 feet
4/6/8 way pillar box 4 feet
Cleaning, painting with Aluminium paint 2 coats & numbering pillar box with
8 way pillar box
6 way pillar box
4 way pillar box
Mini way pillar box
DISMANTLING OF PILLAR BOX
Dismantling of old pillar box including associated accessories, loading on the
4/6/8 way pillar box
Mini pillar box
Maintenance of pillars works such as replacement of damaged insulators worn out stembolts, lugs, termination of cables and dressing
8 way pillar box
6 way pillar box
4 way pillar box
Mini pillar box
Earthing of pillar boxes
8/6/4 and Mini pillar boxes
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .