Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.3 CrAccepted-AOC 143 SHASTRI NAGAR LAKHIMPUR KHERI | ₹2.3 Cr | L1 | Accepted-AOC technically qualified and quoted lowest amount |
| 2 | L2₹2.4 CrRejected-Finance RAMSEWAKPURAM COLONY HARIHAR PUR NILMAYA SAROJININAGAR LUCKNOW | LUCKNOW | LUCKNOW | UTTAR PRADESH | ₹2.4 Cr | L2 | Rejected-Finance QUOTED HIGHER RATE THAN L1 |
| 3 | L3₹2.5 CrRejected-Finance 35 8 5 RAMPUR GARDEN AMAN TRADERS 35 8 5 RAMPUR GARDEN NEAR L I C BUILDING BAREILLY UTTAR PRADESH BAREILLY BAREILLY UTTAR PRADESH 243001 UDYAM UP 15 0002258 09EUPPS2879C1ZW B R | BAREILLY | UTTAR PRADESH | 243001 | ₹2.5 Cr | L3 | Rejected-Finance QUOTED HIGHER RATE THAN L1 |
| 4 | L4₹2.5 CrRejected-Finance 01 REWARI REWARI HARYANA 123401 | REWARI | HARYANA | 123401 | ₹2.5 Cr | L4 | Rejected-Finance QUOTED HIGHER RATE THAN L1 |
| 5 | L5₹2.5 CrRejected-Finance 0 0 0 NEAR DAK BUNGLOW NH 1 A NH 1A UDHAMPUR UDHAMPUR JAMMU KASHMIR 182101 UDYAM JK 22 0002496 01AFRPJ1985K1Z4 R M | UDHAMPUR | JAMMU AND KASHMIR | 182101 | ₹2.5 Cr | L5 | Rejected-Finance QUOTED HIGHER RATE THAN L1 |
| Sl No | Description | Qty | Unit | M/S ASHISH KUMAR L4 | M/S CHAUDHARY ENTERPRISES L11 | M/S SRI RAM TRADERS L8 | SHIVAM ENTERPRISES L5 | M/s Aman Traders L3 | DHARAM DEV CHAUHAN L9 | NIRBHAY KUMAR MISHRA L6 | Durga Engineers and Earth Movers L10 | SHIVANAND SHUKLA L7 | M/s Nav Bharat Construction L1 | M/s Rai Construction L2 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | E/w in cutting in foundation of Culvert / Guide wall on channels above 10 Cumecs including lead upto 30 M. And lift upto 1.5 M and disposal and back filling as per Drawing & direction of engineer-in-charge. | 2,618.94 | Cum | 80 ₹2.1 L | 90 ₹2.4 L | 80 ₹2.1 L | 100 ₹2.6 L | 95 ₹2.5 L | 100 ₹2.6 L | - | 65 ₹1.7 L | 100 ₹2.6 L | 89.67 ₹2.3 L | 100 ₹2.6 L |
| 2.00 | Hiring & engaging Diesel Pump of 5 H.P. with POL For Dewatering at site.Workdone as per direction of Engineer-in-charge. | 2,400 | Hr. | 110 ₹2.6 L | 140 ₹3.4 L | 80 ₹1.9 L | 125 ₹3 L | 164.67 ₹4.0 L | 200 ₹4.8 L | 100 ₹2.4 L | 100 ₹2.4 L | 170 ₹4.1 L | 153.61 ₹3.7 L | 180 ₹4.3 L |
| 3.00 | Laying Plain Cement Concrete (M -10) in foundation 1:3:6 with stone grit including cost of material, labour, T&p etc, complete.Workdone as per as per Drawing & direction of engineer-in-charge. | 127.02 | Cum | 6,700 ₹8.5 L | 7,500 ₹9.5 L | 6,250 ₹7.9 L | 6,700 ₹8.5 L | 5,371.17 ₹6.8 L | 6,100 ₹7.7 L | 4,000 ₹5.1 L | 7,500 ₹9.5 L | 6,700 ₹8.5 L | 5,010.55 ₹6.4 L | 6,500 ₹8.3 L |
| 4.00 | Centring and shuttering For R.C.C. Work including rent of shuttering & all cost of labour and material T&P etc. required for porper completion of the work/M2.For bridge slab above 3.00m span.Workdone as per as per Drawing & direction of engineer-in-charge. | 1,592.11 | Sqm | 700 ₹11.1 L | 700 ₹11.1 L | 700 ₹11.1 L | 800 ₹12.7 L | 806.02 ₹12.8 L | 1,000 ₹15.9 L | 800 ₹12.7 L | 650 ₹10.3 L | 800 ₹12.7 L | 751.9 ₹12.0 L | 800 ₹12.7 L |
| 5.00 | Bending,Binding,Cutting and Placing in position reinforcement including all cost of labour and material T&P etc. required for porper completion of the work/MT.Workdone as per as per Drawing & direction of engineer-in-charge. | 95.06 | MT | 78,000 ₹74.1 L | 87,000 ₹82.7 L | 94,000 ₹89.4 L | 78,000 ₹74.1 L | 74,164 ₹70.5 L | 92,500 ₹87.9 L | 80,000 ₹76.0 L | 77,500 ₹73.7 L | 82,000 ₹77.9 L | 69,184.65 ₹65.8 L | 65,000 ₹61.8 L |
| 6.00 | Laying Plain Cement Concrete (M -15) in foundation 1:2:4 with stone grie including cost of material, labour, T&p etc, complete.Workdone as per as per Drawing & direction of engineer-in-charge. | 153.72 | Cum | 6,800 ₹10.5 L | 7,000 ₹10.8 L | 6,900 ₹10.6 L | 6,800 ₹10.5 L | 5,595.48 ₹8.6 L | 7,000 ₹10.8 L | 5,000 ₹7.7 L | 8,000 ₹12.3 L | 6,700 ₹10.3 L | 5,219.8 ₹8.0 L | 6,500 ₹10.0 L |
| 7.00 | Laying Reinforced Cement Concrete ( M25 ) in Raft , Abetment , Pires Guide/ w. Wall etc. in 1:1.60:3.20 with Superplasticizer (Admixture) 0.2% , WC 0.4 , 8.06 bag Cement with Coarse Sand & 10 mm - 20mm Kabrai stone Aggregate by using batching plant transit mixer & Concrete pump including cost of all material, labour, T&p etc, complete.Workdone as per as per Drawing & direction of engineer-in-charge. | 714.96 | Cum | 7,800 ₹55.8 L | 9,400 ₹67.2 L | 7,650 ₹54.7 L | 7,170 ₹51.3 L | 6,189.5 ₹44.3 L | 7,800 ₹55.8 L | 7,000 ₹50.0 L | 9,000 ₹64.3 L | 7,850 ₹56.1 L | 5,773.93 ₹41.3 L | 7,500 ₹53.6 L |
| 8.00 | Laying Reinforced Cement Concrete ( M30 ) in Slab , Wearing Coat,Parapet,kerb etc. in 1:1.60:3.20 with Superplasticizer (Admixture) 0.3% , WC 0.4 , 8.13 bag Cement with Coarse Sand & 10 mm - 20mm Kabrai stone Aggregate by using batching plant transit mixer & Concrete pump including cost of all material, labour, T&p etc, complete.Workdone as per as per Drawing & direction of engineer-in-charge. | 329.62 | Cum | 7,800 ₹25.7 L | 9,800 ₹32.3 L | 7,650 ₹25.2 L | 7,300 ₹24.1 L | 6,221.4 ₹20.5 L | 7,996 ₹26.4 L | 7,200 ₹23.7 L | 11,000 ₹36.3 L | 7,850 ₹25.9 L | 5,803.69 ₹19.1 L | 7,500 ₹24.7 L |
| 9.00 | S/F of local sand including cost of all material, labour and T&P etc. complete.Workdone as per as per Drawing & direction of engineer-in-charge. | 441 | Cum | 500 ₹2.2 L | 1,000 ₹4.4 L | 900 ₹4.0 L | 1,000 ₹4.4 L | 902.64 ₹4.0 L | 400 ₹1.8 L | 800 ₹3.5 L | 1,000 ₹4.4 L | 850 ₹3.7 L | 842.04 ₹3.7 L | 800 ₹3.5 L |
| 10.00 | Finishing walls with Premium Acrylic Smooth exterior paint ( apex Ultima,wethercoat, all Gard) including cost of all material and labour T&P etc required for proper completion of work | 319.17 | Sqm | 90 ₹28,725.30 | 100 ₹31,917 | 90 ₹28,725.30 | 100 ₹31,917 | 106.37 ₹33,950.11 | 110 ₹35,108.70 | 35 ₹11,170.95 | 130 ₹41,492.10 | 120 ₹38,300.40 | 99.22 ₹31,668.05 | 100 ₹31,917 |
Tender Value
₹3.1 Cr
EMD Value
₹6.3 L
Closing Date
17 Oct 2025, 1:00 pmClosed
SE SIX CIRCLE LUCKNOW
SE Six circle lucknow
janpad hardoi me hardoi shakha ke km 199.742 par sthit pul ke nav nirman ka karya
2025_UPIDC_1081543_16
03/SE-6/2025-26
Open Tender
Civil Works
500 days
unnao
please refer tender document
2 documents required · 2 mandatory
₹5,484
₹6.3 L
SE Six circle lucknow
16 Mar 2026
10 Oct 2025
17 Oct 2025
10 Oct 2025
17 Oct 2025
10 Oct 2025
13 Oct 2025
stage.html
html • 0.08 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid