| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.3 LAccepted-AOC HNO 365 STREET NO 12 TALAB TILLO JAMMU RISHI TRADING CO TALAB TILLO ROAD OPP FRIENDS LANE JAMMU JAMMU KASHMIR 180002 | JAMMU | JAMMU AND KASHMIR | 180002 | L1 | Accepted-AOC LOWEST / NEGOTIATED | |
| 2 | L2₹4.4 L+₹67,610 (18.0%)Rejected-Finance | L2 | Rejected-Finance 2ND LOWEST | |
| 3 | L3₹5.1 L+₹1.4 L (36.9%)Rejected-Finance H N 131 GOPLAPUR NEW SHIVPURI GOPLAPUR GORAKHPUR UTTAR PRADESH 273016 | GORAKHPUR | UTTAR PRADESH | 273016 | L3 | Rejected-Finance 3RD LOWEST |
Tender Value
Refer Docs
EMD Value
₹3,500
Closing Date
29 Sept 2021, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SUPERINTENDING ENGINEER
ELECTRICITY URBAN DISTRIBUTION CIRCLE, BUNGLOW NO.-9, OLD POWER HOUSE COLONY, RAILWAY STATION ROAD, GORAKHPUR
WORK AGAINST SANCTIONED PACKAGE
2021_PVVNV_621398_1
14/EUDC(G)/2021-22
Open Tender
Electrical Works
Lump-sum
30 days
AREA OF EUDC GKP
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
SUPERINTENDING ENGINEER EUDC
₹3,500
27 Jan 2022
20 Sept 2021
30 Sept 2021
20 Sept 2021
29 Sept 2021
20 Sept 2021
180 days
Amount
fo|qr uxjh; forj.k [k.M&f}rh;] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 12@2021&22 ¼jlwyiqj] xzhuflVh Qst&02] xksj[kiqj esa uydwi ds fo|qr la;kstu gsrq fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 25 KVA Transformer
S.T Pole 11 mtr. long
ACSR Weasel conductor
11 KV Pin insulator with Pin
11 KV Dropper angle
11 KV Sub Station Base angle
11 KV Top Channel
Stay Set Complete
11 KV Disc insulator with fitting 45 KN (T&C) Type
11 KV Cable AL.3x70 sq.mm XLPE
Supply of following material/fitting complete in all respect :-
Alluminium Lugs 70sq.mm
Holding Clamp For TOP Channel, Dropper, Z clamp for T/F
Nuts & Bolts of different size
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
Laying, stringing and hanging of 11 KV XLPE Cable AL.3x70 sq.mm
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
fo|qr uxjh; forj.k [k.M&f}rh;] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 13@2021&22 ¼?kks"khiqj] xksj[kiqj esa uydwi ds fo|qr la;kstu gsrq fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 25 KVA Transformer
S.T Pole 11 mtr. long
ACSR Weasel conductor
11 KV Pin insulator with Pin
11 KV Dropper angle
11 KV Sub Statuion Base angle
11 KV Top Channel
Stay Set Complete
Earthing Complete
11 KV Tpmo
11 KV Fuse set
LT Cable AL. 4x25 sq. mm
T-Off Channel
11 KV Dis Insulator With Fiting
Supply of following material/fitting complete in all respect :-
Nuts & Bolts of different size
Clamps For Top, Dropper, TPMO, Fuse set, STP etc.
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
Errection of TPMO and Fuse set
fo|qr uxjh; forj.k [k.M&f}rh;] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 14@2021&22 ¼bLekbyiqj dkth th dk eSnku] xksj[kiqj esa uydwi ds fo|qr la;kstu gsrq fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 25 KVA Transformer
S.T Pole 11 mtr. long
11 KV Pin insulator with Pin
11 KV Dropper angle
11 KV Sub Station Base angle
11 KV Top Channel
Stay Set Complete with 5 Kg. wire
11 KV Disc insulator with fitting 45 KN (T&C) Type
Earthing Complete
11 KV Tpmo
11 KV Fuse set
11 KV T-off channel
ACSR dog conductor
11 KV V Type X Arm
Supply of following material/fitting complete in all respect :-
F Bracket
Nuts & Bolts of different size
Clamps For Top, Dropper, TPMO, Fuse set, STP etc.
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of ST Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/STP/LT clamp, F-Bracket, LT shacle insulator, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). In case of ST Pole making Plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Laying, stringing, sagging, binding and jumpering of ACSR Dog conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
Errection of TPMO and Fuse set
fo|qr uxjh; forj.k [k.M&izFke] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 18@2021&22 ¼15 osa foRr vk;ksx ds vUrxZr tydy foHkkx uxj fuxe okMZ la0 21 csfr;kgkrk esa iwoZ es;j Jherh lR;k ik.Ms; ds ?kj ds ikl] xksj[kiqj esa 25 fd0ok0 ds uydwi fo|qrhdj.k dk dk;ZZ½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 63 KVA Transformer
S.T Pole 11 mtr. long
S.T Pole 9 mtr. long
ACSR Weasel conductor
11 KV Pin insulator with Pin
11 KV Dropper angle
11 KV Sub Station Base angle
11 KV Top Channel
Stay Set Complete
11 KV Disc insulator
Earthing Complete
11 KV Fuse set
LT PVC Cable 3.5x70 sq. mm
LT AB Cable (3X120+1X95+1X16)sq.mm
Supply of following material/fitting complete in all respect :-
Clamps for Top, Dropper angle etc with nuts & bolts
Distribution Box with Clamp (Distribution box shall be made from 20 SWG CRCA sheet by Deep Drown method with powder coating & size of box shall be 418 mm X 300mm X 120 mm (Roof of the box shall be tapered on both sides to drain the rain water)
Dead end clamp with I hook
Suspension clamp with I hook
AL Lugs
Nuts & Bolts of different size
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of ST Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/STP/LT clamp, F-Bracket, LT shacle insulator, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). In case of ST Pole making Plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Fabrication, errection, commissioning & Testing of 63 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
Laying, stringing, sagging, binding and jumpering of LTABC Cable (3X120+1X95+1X16) with fixing of Distribution Box with Clamp, Insulated Dead end clamp with I hook, Suspension clamp with I hook(Insulated), LT insulated Piercing connector, XLPE 1X35 Sq.mm. Al. cable for enerzing DB.
Errection of Fuse set
fo|qr uxjh; forj.k [k.M&izFke] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 19@2021&22 ¼15 osa foRr vk;ksx ds vUrxZr tydy foHkkx uxj fuxe okMZ la0 60 :Lreiqj] xksj[kiqj esa 25 fd0ok0 ds uydwi fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 63 KVA Transformer
S.T Pole 11 mtr. long
ACSR Weasel conductor
11 KV Dropper angle
11 KV S/S Base angle
11 KV Top Channel
Stay Set Complete
11 KV Disc insulator
Earthing Complete
11 KV Fuse set
LT PVC Cable 4x25 sq. mm
11 KV Polymeric Pin insulator with Pin
Supply of following material/fitting complete in all respect :-
Clamps for Top, Dropper angle etc with nuts & bolts
Z clamp
Nuts & Bolts of different size
AL Lugs
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
Fabrication, errection, commissioning & Testing of 63 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
Errection of Fuse set
fo|qr uxjh; forj.k [k.M&izFke] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 20@2021&22 ¼fijkiqj] fjyk;Ul Vkoj ds ikl] xksj[kiqj esa uydwi ds fo|qr la;kstu gsrq fo|qrhdj.k dk dk;ZZ½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 25 KVA Transformer
S.T Pole 11 mtr. long
ACSR Weasel conductor
11 KV Pin insulator with Pin
Cable AL.3x70 sq. mm XLPE 11 KV ( Double Circuite)
11 KV Dropper angle
11 KV Sub Station Base angle
11 KV Top Channel
Stay Set Complete with 5 Kg. wire
Cable Jointing Kit 3x70 sq. mm XLPE 11 KV ( Double Circuit)
Earthing Complete
11 KV Fuse set
11 KV T- Off Channel
11 KV TPMO
Supply of following material/fitting complete in all respect :-
Nuts & Bolts of different size
Clamps For Top, Dropper, TPMO, Fuse set, STP etc.
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of ST Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/STP/LT clamp, F-Bracket, LT shacle insulator, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). In case of ST Pole making Plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Laying, stringing and hanging of 11 KV XLPE Cable AL.3x70 sq.mm
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
Errection of TPMO and Fuse set
fo|qr uxjh; forj.k [k.M&izFke] xksj[kiqj ds vUrxZr tek ;kstuk ys[kk'kh"kZ esa Lohd`r iSdst la[;k 21@2021&22 ¼yksfg;k buDyso vkoklh; ;kstuk Qst&izFke esa 25 ,p0ih0 dk lejlscqy ,oa 10 ,p0ih0 dk izs'kj iEi ds fo|qr la;kstu gsrq ykbu fuekZ.k dk dk;ZZ½ ds dk;ksZ dks lseh VuZdh vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k%&
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
11/0.4 KV 63 KVA Transformer
S.T Pole 11 mtr. long
ACSR Weasel conductor
11 KV Pin insulator with Pin
11 KV Dropper angle
11 KV Sub Station Base angle
11 KV Top Channel
Stay Set Complete with 5 Kg. wire
11 KV Disc insulator
Earthing Complete
11 KV D.O. Fuse set
11 KV T- Off Channel
Supply of following material/fitting complete in all respect :-
Clamps for Top, Dropper angle etc with nuts & bolts
AL Lugs
Cu Z clamp
Nuts & Bolts of different size
The excavation of 2 nos. foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
Painting of Pole with Aluminium paint & Red oxide paint provided by contractor
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
Fabrication, errection, commissioning & Testing of 63 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification
Errection of Fuse set
M/s Electro Shine India
M/s S.B.S. Traders
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .