Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹32.2 LAdmitted-Finance 0 SUBHASH NAGAR SIFHPURA SIDHPURA ETAH UTTAR PRADESH 207246 | KASGANJ | UTTAR PRADESH | 207246 | L1 | Admitted-Finance | ||
| 2 | L2₹32.6 L+₹33,916.49 (1.05%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹32.6 L+₹34,568.73 (1.07%)Admitted-Finance | L3 | Admitted-Finance |
Tender Value
₹38.5 L
EMD Value
₹1.9 L
Closing Date
28 May 2026, 2:00 pmClosed
EO NP GAWAN
OFFICE EO NP GAWAN SAMBHAL
12- NP GAWAN WARD 05 V 10 MOHALLA SHEKHAN ME OTARI KE MAKAN SE DARYAV SINGH KE MAKAN TAK CC SADAK V NALI NIRMARN KARYA
2026_DOLBU_1145710_24
1506/NPG/2026-27 DT 04-05-2026 T1
Open Tender
Civil Works
Percentage
30 days
GAWAN
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,995
Yes
EO NAGAR PANCHAYAT GAWAN
₹1.9 L
1 Jun 2026
11 May 2026
29 May 2026
11 May 2026
28 May 2026
11 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling cement concrete or bricks or interlocking tiles and c.c. flooring including base concrete and including stacking of dismantled materials as directed by the Engineer-in -charge with in a distance of 60meeter (200feet).chapter no 17 in item no 697. | 1,362.6 | sqm | 45 | ₹61,317 |
| 2 | Excavation in foundation in ordinary soil (loan, clay or sand) including lift up to 1.5 m and lead up to 30m and including filling waterning and ramming of excavated earth in to the trenches or in to the space in to the building and the side of foundation tranches.3 and including all material labour, T&P, and all taxes for the proper Conpletion of the work. as per direction of Engineer in charge. | 121.44 | cum | 110 | ₹13,358.4 |
| 3 | Earthwork Construction of embankment with approved material obtained from borow pits with all lifts and leads trancporting upto 5.00 Km to sites, spreading, grading to required slope and compected to meet requirement of table 300.2 | 923.4 | cum | 202.2 | ₹1,86,711.48 |
| 4 | PCC work with 4cm. Guage brick ballast fine sand of 1.25 F:M. and cement in proportion of 8:4:1 in foundation and under floors including supply of all meterials, labour and T&P etc. required for proper completion of work. SI No 275 | 40.48 | Cum | 3,500 | ₹1,41,680 |
| 5 | M-150 brick work in 1:3 cement and coarse sand mortar in including all meterial, labour, and T&P etc for proper complection of the work.all meterial, labour, and T&P etc. required for proper completion of the work. SI No 307. | 52.37 | cum | 5,150 | ₹2,69,705.5 |
| 6 | Cement Concrete with 2 cm guage stone grit instead 4cm guage stone ballastof fine sand of 1.25 F.M and cement in proportion of 1:2:4 in foundation and under floors and incliding supply of all meterial T&P and labour cess etc. as per direction of Engineer in charge.required for proper completion of the work. (SI No- 279 A) | 15.75 | Cum | 6,700 | ₹1,05,525 |
| 7 | 12mm thick plaster with 1:4 cement and coarse sand of fineness modulus 1.25 including of all meterial, labour, and T&P etc. required for proper completion of the work. SI No 584 | 303.6 | sqm | 190 | ₹57,684 |
| 8 | Construction of granular sub- base by providing well graded material spreading in uniform layers with mother grader on prepared surface mixing by mix in place method with rootavator at OMC and compacting with smooth wheeled roller to achieve the desined density complete as pr technical specifications Clauses 401 | 186.62 | cum | 3,824.2 | ₹7,13,672.2 |
| 9 | P/Fixing of 80mm thick I shaped ordinary gray 445/446 machanically compressed old c.c. tiles / inter locking cement concrete pavers block manufactured by high pressure & controlled vibration machine having plain dimension 200x(160+120mm) with minimum 5mm thich topping of P.P.Cement mixed with 25% marbel powder including cost of all material ,2cm thick bedding sand layer under the C.C. Paver Block , labour, T&P etc required of proper complition of work .(As per SOR 2017-18,Additional ItemNo.-5(1) | 1,866.2 | sqm | 900 | ₹16,79,580 |
| 10 | R.C.C. Work with cement approved coarse sand and 2cm. gauge approved stone grit in proportion of 1:1½:3 in lintels of doors, windows and sunshades excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I Binding wire and including necessary centering and shuttering etc. and supply of all meterials, labour and T&P etc. required for proper completion of work. Binding wire of supplied by the contractor free of cost. chapter no 05 in Item no 283A | 2.23 | cum | 7,900 | ₹17,617 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 11.84 MB
BOQ_2146243.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .