| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹35.5 CrAccepted-AOC 15A2 1 INTUC 5 SANKARANKOVIL ROAD RAJAPALAYAM TALUK VIRUDHUNAGAR DISTRICT 626 117 | VIRUDHUNAGAR | TAMIL NADU | 626117 | ₹35.5 Cr | L1 | Accepted-AOC Awarded |
| 2 | L2₹37.7 Cr+₹2.1 Cr (6.01%)Rejected-Finance 33 GURU ILLAM V T PANDIAN NAGAR 4TH STREET KARIAPATTI 626 106 | VIRUDHUNAGAR | TAMIL NADU | 626106 | ₹37.7 Cr+₹2.1 Cr (6.01%) | L2 | Rejected-Finance High Quoted |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not complied with prequalification |
Tender Value
₹35.5 Cr
EMD Value
₹17.9 L
Closing Date
17 Feb 2026, 11:00 amClosed
Superintending Engineer
Office of the Superintending Engineer Highways C and M Tirunelveli AR Line Road Palayamkottai
Formation of Bypass to Mallankinaru starts at Km 8 100 Melathulukkankulam Vilakku and ends at Km 12 100 Mudiyanoor of Virudhunagar to Krishnapuram Road SH 184 TN-116
2026_HWAY_651949_1
T N No. 42 2025-226 HDO Dated 02 02 2026
Open Tender
Civil Works - Highways
Percentage
360 days
Aruppokottai
Average Annual Turnover
Completed Contracts
Minimum quantities of works in 1yr during the last 5yrs
Personnel capabilities
Equipment capabilities
Financial position
Audited balance sheet for the last 5yrs
Litigation history
Bid capacity
9 documents required · 9 mandatory
₹0
₹17.9 L
23 Mar 2026
6 Feb 2026
17 Feb 2026
6 Feb 2026
17 Feb 2026
9 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. | - | - | - | - |
| 2 | Road A | 99,954 | Square meter | 9.18 | ₹9,17,577.72 |
| 3 | Picking 5cm to 10cm old metalled surface and sectioning 1Sqm
Picking the existing BTsurface upto80mm as per MORTH Rev.V Clause No. 111, 112, 202 depth directed by the departmental officers and collecting the picked up salvaged metal and stacking the same for reuse and deposting the debris excluding cost of materials including all labour charges for picking and all other tools and plants employed of the work and including all other incidental chargesetc.,complete as per standard specifications as per MORTH Rev.V Clause No. 111, 112, 202 | - | - | - | - |
| 4 | Road A (Branch road improvements) | 278.47 | Square meter | 23.36 | ₹6,505.06 |
| 5 | Earthwork excavation in all classes of soils except hard rock requiring blasting, and depositing on bank with all leads and lifts as per SS20B; including cost of all labour charges, materials, tools, equipment and all incidental charges; including compacting with power roller, watering; including all hire and fuel charges for all tools and plants; removal of other deleterious matter and obstructions; trimming of bottom of excavation; backfilling; clearing up the site and disposal of all surplus materials etc., complete as per standard specification. | - | - | - | - |
| 6 | Road A | 3,764 | Cubic Metre | 131.89 | ₹4,96,433.96 |
| 7 | Providing compaction for embankment /making up of low berms using the available box cut earth including all hire and fuel charges for power roller for compaction, water sprinkler, including all labour charges for laying, spreading, watering etc., complete and as directed by the departmental engineers | - | - | - | - |
| 8 | Road A | 3,764 | Cubic Metre | 28.17 | ₹1,06,031.88 |
| 9 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositingonbankwith all leads and lifts as per SS20B including cost of all labour charges,materials, tools, equipments andall incidental charges, includingcompacting withvibratorysoil compactor,watering, includingall hireandfuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation backfilling, clearingup the site and disposal of all surplusmaterialsetc., complete as per standard specification. For embankment / sub grade | - | - | - | - |
| 10 | Road A | 1,39,733 | Cubic Metre | 660.32 | ₹9,22,68,494.56 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.10 MB
PQ.pdf
Additional Documents • 0.39 MB
PB.pdf
Tender Documents • 1.06 MB
BOQ_781764.xls
BOQ • 0.55 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .