| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹69.7 LAccepted-Finance | ₹69.7 L | L1 | Accepted-Finance Low Rate |
| 2 | L2₹80.2 L+₹10.6 L (15.1%)Rejected-Finance | ₹80.2 L+₹10.6 L (15.1%) | L2 | Rejected-Finance High Rate |
Tender Value
Refer Docs
EMD Value
₹70,400
Closing Date
27 Aug 2024, 3:00 pmClosed
Superintending Engineer Electricity Work Circle
Superintending Engineer Electricity Work Circle, Mirzapur
Construction of 11 KV line, capacity increase of 11/0.4 KV distribution transformers and construction of new 11 KV line under the business plan year 2024-25 under Power Distribution Division-I, Mirzapur.
2024_PVVNV_935830_3
19/EDC(M)/2024-25
Open Tender
Electrical Works
Lump-sum
180 days
Superintending Engineer Electricity Work Circle
Please Refer Tender Document
2 documents required · 2 mandatory
₹3,540
Superintending Engineer Electricity Work Circle
₹70,400
30 Aug 2024
20 Aug 2024
28 Aug 2024
20 Aug 2024
27 Aug 2024
20 Aug 2024
Amount
Supply of following Decentralized materials at the works site as per RESSPO norms.
Stone pad 300x300x75 mm (Provided by Contractor)
X-arms holding clamps with bolts & nuts for ST/PCC poles. (Provided by Contractor)
F-bracket with bolts & nuts for ST/PCC poles (Provided by Contractor)
Al. binding wire (Provided by Contractor)
M.S clamp for Top, T-off channel with bolts & nuts for ST/PCC poles (Provided by Contractor)
Guarding Angle Clamps for ST/PCC poles (Provided by Contractor)
P.G clamps for weasel conductor (Provided by Contractor)
Danger board with clamp & bolts for ST/PCC poles (Provided by Contractor)
Barbed wire GI (Provided by Contractor)
E-bracket with bolts & nuts (Provided by Contractor)
160 mm OD PN-4 PE-80 Grade UV stabilized HDPE Pipe as per IS: 4984 in 6 meter (Provided by Contractor)
Jointer for G.I pipe 6" dia (Provided by Contractor)
All lugs 70/120 mm2 (Provided by Contractor)
Cartage of following materials from ESC, Mirzapur to work site including loading & unloading charge.
ST Poles 11 mtr long (Provided by Department)
PCC Poles 8.5 mtr long (Provided by Department)
Line materials with ACSR Weasel Conductor (Provided by Department)
11 KV VCB O/G, 200/100/5A (Provided by Department)
11 KV XLPE Cable size 3x185 mm2 (Provided by Department)
Transformer 63 KVA, (Provided by Department)
Transformer 25 KVA, (Provided by Department)
Erection
Erection of single support ST/PCC pole for construction of 11 KV/LT line including digging of pit, fitting of all accessories, back filling of earth & others required work.
Grouting of pole with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost)
Grouting of stay sets including digging of pit with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms, fixing binding and nuzzling of stay wire. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost)
Earthing of Poles
Stringing & sagging of 3 phase HT/LT line upto proper sag including laying of ACSR Weasel Conductor, binding with insulators & jumpering.
Erection of Sectional Double Pole Structure of ST pole including digging of pit, fitting of all accessories, back filling of earth, grouting of each pole & stay sets as per RESSPO norms (cement sand & brick ballast wil be supplied by the constractor on his own his own cost)
Erection of Sectional Double Pole Structure of PCC pole including digging of pit, fitting of all accessories, back filling of earth, grouting of each pole & stay sets as per RESSPO norms (cement sand & brick ballast wil be supplied by the constractor on his own his own cost)
Erection of Sectional Double PCC Pole Structure with the help of one pole already erected including digging of pit, fitting of all accessories, back filling of earth, grouting of each pole & stay sets as per RESSPO norms (cement sand & brick ballast wil be supplied by the constractor on his own his own cost)
Gaurding of 11 KV line as per RESSPO norms
Drill/cut of stone in hilly area for erection of pole
Mounting of 25 KVA Transformer as per RESSPO norms
Mounting of 63 KVA Transformer as per RESSPO norms
Laying of O/H 11 KV XLPE cable size 3x185 mm2 as per RESSPO norms
Laying of U/G 11 KV XLPE cable size 3x185 mm2 including cost of sand & bricks as per RESSPO norms
Filling of I/D/O/D 11 KV cable jointing kit size 3x185 mm2 as per RESSPO norms
Installation of 11 KV VCB pannel (O/G), 200/100/5A as per RESSPO norms
Testing & commissioning of O/G 11 KV swichgear as per RESSPO norms
Earthing for Indoor structure including 11 KV VCB pannel etc through boring till the water level with G.I Pipe & G.I strip and connect of all structure as per RESSPO norms
Drilling under the Railway Track by HDD machine for crossing the 11 KV XLPE cable
Laying of 160 mm OD PN-4 PE-80 Grade UV Stabilized HDPE Pipe as per IS:4984 in 6 meter with jointer
Laying charge of 11 KV 3x185 mm2 XLPE cable from D/P to D/P
Cartage of received back 10 KVA Transformer from work site to ESC, Mirzapur including loading & unloading charge
Cartage of received back 25 KVA Transformer from work site to ESC, Mirzapur including loading & unloading charge
KRISHNA ETERPRISES
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .