| 1 | L1₹1.6 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹1.5 L+₹14,182 (10.7%)Rejected-Finance | L2 | Rejected-Finance QUOTED HIGHEST RATE |
Tender Value
Refer Docs
EMD Value
₹1,700
Closing Date
7 Dec 2020, 12:00 pmClosed
SE CEDC CUDDALORE
SE CEDC CUDDALORE
1) Providing water supply arrangements to the toilet in the Valayamadevi control room building at Valayamadevi 110 KVSS 2) Improvement works to the toilet sewage pipe line work of the Valayamadevi Control room building at Valayamadevi 110 KVSS 3) Con
2020_EB_185834_1
18/2020-21
Open Tender
Civil Works
Works
Srimushnam
Please refer tender documents
2 documents required · 2 mandatory
₹0
₹1,700
Yes
26 Feb 2021
23 Nov 2020
8 Dec 2020
23 Nov 2020
7 Dec 2020
23 Nov 2020
Amount
A) water supply arrangements
a) Providing water supply arrangements to the toilet in the valayamadevi control room building at valayamadevi 110 KV SS
Supplying and laying PVC pipe line of 50mm dia OD 10Kg per cm2 for water supplying including cost of pipe pipe specials adhesive solvent labour lead lift etc complete
Re filling with excavated soil other than sand complying with standard specification
Supplying and fixing 25mm PVC tap with cost tap labour etc complete
Supplying and fixing of 25mm dia OD 10Kg per cm2 including cost of material labour lead and lift and including cost of special etc complete
Supplying and fixing of 1000 lit capacity sintex tank of approved quality including cost of materials labour for fixing lead lifts etc complete
Supplying and fixing of 1HP jet Pump set including cost of materials labour dfor fixing lead lifts etc complete
Supplying and fabrication and placing in position of MS per RTS steel reinforcement for RCC works including labour for cutting bending tying and fixing in position as per specification including cost of all materials lead lift labour cost of binding wire etc complete
Providing RCC M20 Mix using 12 to 20mm HB stone jelly for roof slab including form work curing cost of all materials lead and lift etc complete but excluding cost of reinforcement as directed by engineer incharge.
b) Improvement works to the toilet sewage pipe line work of the valayamadevi control room building at valayamadevi 110KV SS
Dismantling the brick work in the existing damaged manhole including cost of all materials lead lift etc complete
Earth work excavation and depositing on bank with in initial lead of 10m and initial lift of 2m in hard red earth shales murrams gravel stoney earth and earth mixed with small size boulders etc complete
Filling with clean river sand complying with standard specification etc Complete
P C C 1 is to 2 is to 4 using 40mm HBG jelly including cost of all materials labour lead lift curing etc complete
Brickwork in CM I is to 6 mix using III class brick of size 9" x4 3/8"x2 3/4" for foundation and walls including cost of all materials labour lead lift curing etc complete
Plastering in CM 1 is to 5 12mm thick for brick walls including cost of all materials labour lead lift curing etc complete
Supplying anf fixing C I man hole cover of size 0.60 x0.60 cm for inlet and outlet manhole and building outside manhole cover for heavy duty including lead lift labour etc complete
Supplying and filling with gravel including cost of all materials labour lead and lift etc complete
Providing and ficing 110 mm OD 6Kgf PVC for sewage line including cost of bend clamp shoe etc complete
Supply and fixing wash basin of size 550mmx400mm with all accessories such as cast iron bracket 32 mm Dia C P waste coupling 32 mm dia B Class G I waste pipe 15 mm dia GM wheel valve 15mm dia nylon connection 15mm dia brass nipples 15mm CP Pillar tap with all accessories including cost of all materials labour lead lift etc complete
c) Construction of sump for water supply to the toilet in the valayamadevi control room building at valayamadevi 110KV SS
Earth work excavation and depositing on bank with in initial lead of 10m and initial lift of 2m in hard red earth shales murrams gravel stoney earth and earth mixed with small size boulders etc complete
Supplying and filling of river sand in foundation and basemet with well watering and consolidation as per atd sprcn including cost of all labour lead lift etc complete
PCC M15 concrete using 40mm HBS machine crushed metal for foundation including cost of all labour lead lift etc complete
Brickwork in CM I is to 6 mix using III class brick of size 9" x4 3/8"x2 3/4" for foundation and walls including cost of all materials labour lead lift curing etc complete
Plastering in CM 1 is to 5 12mm thick for brick walls including cost of all materials labour lead lift curing etc complete
K.Karthikeyan
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_222318.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .