| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.2 LAccepted-Finance | L1 | Accepted-Finance BOQ Rate accepted | |
| 2 | L2₹6.4 L+₹18,370 (2.96%)Accepted-Finance | L2 | Accepted-Finance BOQ Rate accepted |
| Sl No | Description | Qty | Unit | RAJAM CONSTRUCTIONS | THAVAM ENTERPRISES |
|---|---|---|---|---|---|
| 1.00 | Filling with M sand complying with standard specification for filling in foundation and basement with watering and consolidation including cost of labour, lead, lift, etc. complete. | 10.5 | M3 | 27,825 ₹32,833.5 | 26,250 ₹30,975 Lowest |
| 2.00 | Providing PCC 1:2:4 using OP/PP cement with 12 to 20 mm machine crushed HBG metal including cost of all materials, labour, lead, lift, curing, etc. complete. | 22.7 | M3 | 2,54,240 ₹3,00,003.2 | 2,49,700 ₹2,94,646 Lowest |
| 3.00 | R.R Masonry in C.M.1:5 including cost of all materials, labour, lead, lift, curing, etc. complete. | 22.9 | M3 | 2,09,535 ₹2,47,251.3 | 2,06,100 ₹2,43,198 Lowest |
| 4.00 | Pointing the RR Masonry wall with C.M 1:5, including cost of all materials, labour, lead, lift, curing, etc. complete. | 231 | M2 | 99,330 ₹1,17,209.4 | 92,400 ₹1,09,032 Lowest |
| 5.00 | Supplying and fixing of weep holes using approved quality PVC pipe of160mm dia of 4kg/cm2 including cost of specials, all other materials required, labour, lead, lift, etc., complete. | 37.8 | Rm | 47,250 ₹55,755 | 45,360 ₹53,524.8 Lowest |
Tender Value
Refer Docs
EMD Value
₹4,900
Closing Date
29 Dec 2025, 2:00 pmClosed
Chief Engineer TTPS Tuticorin
Office of the Superintending Engineer Civil TTPS
Repair Works to the existing Drain in the West side of 457.5 E Road from CH 190 mtr to CH 295 mtr from Unit 4 and 5Tunnel Manhole to Unit 4 and 5 Entrance
2025_EB_630832_1
CE SE C TTPS Spec.No. 357 25 26
Open Tender
Civil Works - Others
Item Rate
90 days
Tuticorin Thermal Power Station
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹4,900
Yes
31 Dec 2025
10 Dec 2025
30 Dec 2025
10 Dec 2025
29 Dec 2025
10 Dec 2025
Filling with M sand complying with standard specification for filling in foundation and basement with watering and consolidation including cost of labour, lead, lift, etc. complete.
Providing PCC 1:2:4 using OP/PP cement with 12 to 20 mm machine crushed HBG metal including cost of all materials, labour, lead, lift, curing, etc. complete.
R.R Masonry in C.M.1:5 including cost of all materials, labour, lead, lift, curing, etc. complete.
Pointing the RR Masonry wall with C.M 1:5, including cost of all materials, labour, lead, lift, curing, etc. complete.
Supplying and fixing of weep holes using approved quality PVC pipe of160mm dia of 4kg/cm2 including cost of specials, all other materials required, labour, lead, lift, etc., complete.
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
BOQ_754371.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .