| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹18.8 Laccepted-aoc | ₹18.8 L | accepted-aoc |
Tender Value
₹20.1 L
EMD Value
₹21,000
Closing Date
16 Feb 2026, 10:30 pmClosed
Public Works Department
Construction of CC drain from Chidanand Talakeris home to Ambedkar circle at Kohalli and Construction CC road from Yallammadevi temple to Maruti Kambales Tota at Hulagbal in Athani Taluka of Belagavi dist under 4059 SCP CMIDP for 2025-26.
PWD/2025-26/RD/WORK_INDENT33144
PWD/2025-26/RD/WORK_INDENT33144
Reserved
Roads
PWD Division Office Chikkodi
8 documents required · 8 mandatory
The Tenderer shall obtain any civil construction work the workdone certificate from financial year 2020-21 to 2024-25 (25% of the Amount Put to Tender i.e., Rs.5.03 Lakhs) in the prescribed format from the Competent Authority not below the rank of Executive Engieer(District Level Officer)and scan the Original Certificate and attach the scanned file to the Bid
The Tenderer shall achieved in at least one financial years an average annual financial turnover from financial year 2020-21 to 2024-25 of Rs. 20.12 Lakhs. (not less than the estimated cost under this contract)
The EMD of Rs. 21,000/- shall be paid in full through e-payment in favour of Executive Engineer, PWD, Chikodi Dn, Chikodi
CAT-I Caste Certificate issued by a competent authority / Tahsildar
For CAT-I contractors reservation category participate in the tender, the contractors should upload the domicile certificate stayed in KARNATAKA for minimum of 10 years issued by a competent authority / Tahsildar
₹510
₹21,000
16 Feb 2026
9 Feb 2026
18 Feb 2026
13 Feb 2026
Construction of CC drain from Chidanand Talakeris home to Ambedkar circle at Kohalli and Construction CC road from Yallammadevi temple to Maruti Kambales Tota at Hulagbal in Athani Taluka of Belagavi dist.
3.7 Compacting Original Ground - Compacting original ground supporting embankment - Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of emba... 161.62 m³
8.58.c Providing and laying Reinforced Cement Concrete pipe light duty NP2 for culverts, roadway utilities& crossingsas per IS 458:2003 in Single row including pointing ends and fixing collars with ... 10.00 m
3.6 Construction of Subgrade and Earthen Shoulders - Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting... 49.75 m³
4.2.B.v Granular Sub-Base - By Mix in Place Method - Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared sur... 107.75 m³
4.17 Wet Mix Macadam (Plant Mix Method) - Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC ... 80.81 m³
16.28 Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 150... 178.12 m³
8.54 Providing and fixing board displaying information, such as Name of work, Tender cost, Name of Contractor, Work completion and liability period etc, having rectangular shape of 1.2... 2.00 No.
CC DRAIN ESTIMATE
1.14.1 Mechanical Means -
Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, stru... 40.80 m³
2.1.6 Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates ... 5.10 m³
2.4.2 Providing and laying in position Cement Concrete for all Sub structures of building, Irrigation works, Sub structure works of bridges, Drain works & other parallel works fro... 12.30 m³
2.11.h Steel Fabrication
Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting,... 0.77 t
1.9 Manual Means -
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating Each depos... 5.40 m³
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Circular.pdf
Others - Govt Ltr • 2.53 MB
Tech Spec.zip
Others - Specification • 0.27 MB
bid-doc_wi_33144-kw-2-CAT-I.docx
Tender Document • 1.12 MB
Circular-1.pdf
Others - Govt Ltr • 0.74 MB
2015 Athani SC-ST lot.pdf
Others - Randamisation lot • 0.03 MB
Royalty Order.pdf
Others - Royalty • 4.03 MB