Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 LAccepted-Finance | ₹1.1 L | L1 | Accepted-Finance Lowest Amount Quoted |
| 2 | L2₹1.2 LRejected-Finance MOHALLA LOTANPURA DISTRICT BUDAUN | BUDAUN | BUDAUN | UTTAR PRADESH | ₹1.2 L | L2 | Rejected-Finance Highest Amount Quoted |
| 3 | L3₹1.3 LRejected-Finance | ₹1.3 L | L3 | Rejected-Finance Highest Amount Quoted |
Tender Value
₹1.7 L
EMD Value
₹20,000
Closing Date
8 May 2026, 12:00 pmClosed
Executive Engineer
Executive Engineer, Provincial Division, PWD, Budaun
Construction of separate Toilet for use of Video Conferencing Building located in Collectorate campus, District Badaun.
2026_CEBLY_1144398_1
1091(4)/Nivida/2025-26 dt 20/04/2026
Open Tender
Civil Works - Buildings
60 days
Budaun
Please refer Tender Documents
3 documents required · 3 mandatory
₹678
₹20,000
Yes
Budaun
14 May 2026
1 May 2026
8 May 2026
1 May 2026
8 May 2026
1 May 2026
2 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil (DSR 2021 INo-2.8.1) | 7.55 | Cum. | 190 | ₹1,434.5 |
| 2 | 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) (DSR 2021 I No 4.1.8) | 0.89 | Cum. | 4,960 | ₹4,414.4 |
| 3 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) (DSR 2021 Item No-6.1.2) | 7 | Cum. | 5,193 | ₹36,351 |
| 4 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 12.5 in superstructure above plinth level up to floor V level in all shapes and sizes in :Cement mortar 1:6 (1 cement : 6 coarse sand).(DSR 2021 I.N. 6.3.1) | 4.5 | Cum. | 6,772 | ₹30,474 |
| 5 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. (DSR 2021 No-2.27) | 0.9 | Cum | 1,546 | ₹1,391.4 |
| 6 | Providing and fixing pressed steel door frames confirming to IS: 4351 manufactured from commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lock jamb, bead and if required angle threshold of mild steel angle of section 50x25mm, or base ties of 1.25mm pressed mild steel welded or rigidly fixed together by mechanical means, adjustable lugs with split end tail to each jamb including steel butt hinges 2.5mm thick with mortar guards, lock strike-plate and shock absorbers as specified and applying a coat of approved steel primer after pre-treatment of the surface as directed by Engineer-in-charge: Profile-E (DSR 2023.I. No- 10.14.3.1) | 8.3 | R.M. | 466 | ₹3,867.8 |
| 7 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works (DSR 2023, 10.25.2) | 4.4 | kg. | 126 | ₹554.4 |
| 8 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) (DSR 2023 INo-5.1.2) | 0.18 | Cum | 6,586 | ₹1,185.48 |
| 9 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). (DSR 2023 Item No 5.3) | 1.05 | Cum. | 8,378 | ₹8,796.9 |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers (DSR 2023 Item No- 5.9.5) | 2.38 | Sqm. | 536 | ₹1,275.68 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.48 MB
T1.pdf
Tender Documents • 2.26 MB
BOQ_2138177.xls
BOQ • 0.66 MB
Download all tender documents and submit your bid