Tender Value
₹2.2 Cr
EMD Value
₹4.3 L
Closing Date
27 Jul 2026, 3:00 pm
Rectification/Straightening of leaning OHE mast/structure under KGP Division.
TRD-KGP-W-2026-27-07
TRD-KGP-W-2026-27-07
Open
18 Months
Unknown (Unspecified Location)
₹0
₹4.3 L
3 Jul 2026
3 Jul 2026
13 Jul 2026
Item Breakup - A-Schedule
Per Track Preparation of OHE Design & Drawing KM
Concrete for foundation/plinth including supply cum of sand, ballast & cement. Total 3440078.00
Item Breakup - B-Schedule
Supply of fabricated and galvanised traction MT mast/TTC/Portal
Supply of fabricated and galvanised steel work MT other than mast Total 8530419.00
Item Breakup - C-Schedule
Supply of conventional cantiliver assembly with Each 610gm/sq.m galvanization in structural tubes (without insulator). Total 2220368.00
Item Breakup - D-Schedule
Supply of Stay Insulator.
Supply of Bracket Insulator. Total 811760.00
Item Breakup - E-Schedule
Supply of section insulator assembly including Each core & cut-in insulator. Total 322960.00
Item Breakup - F-Isolators
Supply of 25KV single pole isolator without Each earth contact assembly & post insulator. Total 91212.00
Item Breakup - G-Schedule
Supply and erection of UV protected HDPE Sqm Mesh inside the Portal boom/fabricated structures as per RDSO SMI TI/MI/0050, Rev.-1 or latest revision under power block.. Total 86000.00
Item Breakup - H-Schedule
Supply of materials for termination of FTA with Each complete fittings (Including Supply of cut-in- insulator).
Supply of double conductor termination of OHE Each (with Cut-in-insulator).
Supply of Guy rod assembly.
Supply of OHE equipments excluding catenary, Per Track contact, jumper and dropper wires & erection KM of overhead equipment including catenary, contact, jumper, LSW, & dropper wire.
S u p p l y of anticreep Anticreep wire. KHARAGPUR DIVISION-ELECTRICAL/SOUTH EASTERN RLY Total 583406.00
Item Breakup - I-Schedule
Supply of Galvanized steel flexible wire bond Each for traction with lugs for various length of each bond complete with lugs-3.0mtr.
Supply of Galvanized steel flexible wire bond Each for traction with lugs for various length of each bond complete with lugs-3.5mtr.
Supply and erection of Galvanized steel flexible Each wire bond for traction with lugs for various length of each bond complete with lugs-4.5mtr. Total 1092960.00
Item Breakup - J-Schedule
Erection of fabricated and galvanised traction MT mast/TTC/Portal
Erection of fabricated and galvanised steel MT work other than mast
Erection of conventional cantiliver assembly Each with 610gm/sq.m galvanization in structural tubes (without insulator).
Erection of section insulator assembly including Each core & cut-in insulator
Erection of anticreep with Railway Supply Each Anticreep wire
Straightening of Leaning OHE mast/Structure.
Erection of 25KV single pole isolator without Each earth contact assembly & post insulator
Erection of materials for termination of FTA Each with complete fittings (Including Supply of cut- in-insulator)
Erection of double conductor termination of Each OHE (with Cut-in-insulator)
Erection of Guy rod assembly
Erection of OHE equipments including catenary, Per Track contact, jumper and dropper wires and feeder KM wire.
Shifting of OHE from old mast to new mast
Erection of Galvanized steel flexible wire bond Each for traction with lugs for various length of each bond complete with lugs-3.0mtr.
Erection of Galvanized steel flexible wire bond Each for traction with lugs for various length of each bond complete with lugs-3.5mtr.
Erection of Galvanized steel flexible wire bond Each for traction with lugs for various length of each bond complete with lugs-4.5mtr.
Erection of regulating equipment, Modified 3 Each pulley type with counter weight
Removal catenary, contact,jumper and dropper wires KM
Modification adjustment of OHE and T/W checking of OHE KM
Dismantling & Removal of mast, AT Mast Each including TTC/Portal upright etc.
Dismantling & removal of SPS including Portal MT boom/TTC Boom, DA etc. KHARAGPUR DIVISION-ELECTRICAL/SOUTH EASTERN RLY
Dismantling of Cantilever Assembly.
Dismantling of OHE termination assembly
Dismantling & Removal of Anchor assembly
Dismantling of Anticreep
Dismantling of of FTA
Dismantling of Section Insulator
Dismantling of Isolator
Dismantling of Regulating Equipment
Transportation of materials.
Extra erection charge under power block (100% Lumpsum Erection Charges on Item No. 1, 2, 3, 4, 5, 7, 8, 9, 11, 12, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27 & 28. Total 4495142.15
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
13.Newe-BGGuidelines_16_06_2026.pdf
ATTACHMENT
1.ExplanatoryNote..pdf
ATTACHMENT
2.TechnicalSpecification.pdf
ATTACHMENT
3.SpecialCondition.pdf
ATTACHMENT
4.Mandate_Form.pdf
ATTACHMENT
5.Indemnity_Bond_Format.pdf
ATTACHMENT
6.PaymentCondition.pdf
ATTACHMENT
7.Annexure-VA.pdf
ATTACHMENT
8.FinancialCriteria-Annexure-VIB.pdf
ATTACHMENT
9.BidSecurity-Annexure-VIA.pdf
ATTACHMENT
10.TenderFormAnnexure-I.pdf
ATTACHMENT
11.IRGCC_April-2022.pdf
ATTACHMENT
12.IRGCCApril2022AdvanceCorrectionSlipNo.11.pdf
ATTACHMENT
Download all tender documents and submit your bid