Tender Value
₹7.0 Cr
EMD Value
₹5.0 L
Closing Date
16 Mar 2026, 3:30 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
MNP PROCU.
13 conditions · 2 needing a document upload
2.2 Financial Eligibility Criteria: : The tenderer must have minimum average annual contractual turnover of 'V/N' or 'V' crores whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-II, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet. Please note: •Tenders submitted without credentials as per Annexure I & II of Tender document are liable to be rejected. •The Railway reserves the right to verify the genuine of the credentials of the tenderer as and when need arises.
2.1Technical Eligibility Criteria: a.The tenderer must have successfully completed any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: i.Three similar works costing not less than the amount equal to 30% of advertised value of the tender, or ii.Two similar works costing not less than the amount equal to 40% of advertised value of the tender, or iii.One similar work costing not less than the amount equal to 60% of advertised value of the tender. Definition of the similar nature of work:- "Supply, Erection and Testing of Fire Hydrant Line and addressable Fire Alarm system with RCC Foundation of minimum 1.0 Meter Height for Pipeline In Central/State Organization/ Zonal Railways/ Railway PUs/Public Sector Units." Note for Item 2.1: 1.Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organization, work experience certificate issued by Public listed company having average annual turnover of Rs 500 Crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. 2.In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
35 conditions · 10 needing a document upload
As per Tender Document.
The tenderer(s) shall also submit following documents in support of eligibility criteria along with their bids:
The audited balance sheet reflecting financial turnover certified by chartered accountant with her stamp, signature and membership number for the previous three financial years and the current financial year up to the date of opening of tender.
The following self-attested (signature, stamp and date on each page) documents shall be submitted by the bidder(s)/tenderer(s) in support of identity, bank, bid cost, EMD and profile details of their firm/company:1. Certificate for GSTN registration 2. EMD (Earnest Money Deposit) receipt 3. Tender Document Cost receipt 4. PAN Card in which PAN is readable 5. Copy of Firm Registration 6. Bank Mandate form (NEFT Details of Bank for payment) 7. Cancelled Cheque of Bank Account 8. Power of attorney or Signatory authorization letter 9. Address, Contact/Mobile Nos. & Email-ids.
Note: Power of Attorney/Signatory authorization letter should be signed by director of the company/firm. (JV not allowed)
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Self-attestation of documents/certificates: Each page of the copy of documents/certificates in support of credentials, submitted by the bidder, shall be self-attested by the bidder or authorized representative of the bidding firm. Self-attestation shall include signature, stamp and date (on each page). Only those documents will be considered for evaluating bid, which are duly self-attested (signature, stamp and date on each page) as above.
Tenderer(s)/Bidders are required to make payments towards Tender Document Cost (TDC) and Earnest Money Deposit (EMD) only through online payment modes available on IREPS portal like net banking, debit card, credit card etc.
The Railways reserves the right on its own or in response to any clarification requested or suggested by any person including that of the Tenderer to change/modify the tender document before 15 days from due date of closing at its sole discretion
As per Tender Document.
Supply, Installation, Erection & Testing of Fire Hydrant system and Alarm system with necessary accessories for new shops & Kendriya Vidyalaya at MCF/RBL as per scope of work.
MCF-FHPL-NS-KV-2026-106
MCF-FHPL-NS-KV-2026-106
Open
Works - General
4 Months
Rae Bareli, Uttar Pradesh
₹0
₹5.0 L
16 Mar 2026
20 Feb 2026
2 Mar 2026
258 items across 10 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 1,58,11,448.49 | ||
| Supply and Foundation work of MS Heavy grade pipe 150NB (ERW as per IS: 1239- I(heavy) IS: 3589,6.35 mm Thick),MAKE-TATA/JINDAL | — | — | — | 36,56,500 | |
| Installation, Erection & Testing work of MS Heavy grade pipe 150NB (ERW as per IS: 1239-I(heavy) IS: 3589,6.35 mm Thick),MAKE-TATA/JINDAL | — | — | — | 9,72,700 | |
| Supply and Foundation work of MS Heavy grade pipe 80NB (ERW as per IS: 1239- I(heavy) IS: 3589,6.35 mm Thick),MAKE-TATA/JINDAL | — | — | — | 1,89,600 | |
| Installation, Erection & Testing work of MS Heavy grade pipe 80NB (ERW as per IS: 1239-I(heavy) IS: 3589,6.35 mm Thick),MAKE-TATA/JINDAL | — | — | — | 37,200 | |
| RCC foundation for pipe line size-500x500x2000 mm (including - steel, sand & concrete) | — | — | — | 57,25,312.5 | |
| Supply and Foundation work of MS Structure/angle for pipe support | — | — | — | 3,48,100 | |
| Installation, Erection & Testing work of MS Structure/angle for pipe support. | — | — | — | 1,09,150 | |
| Supply and Foundation work of One coat primer and two coat paint for pipe line & support | — | — | — | 54,524.6 | |
| Installation, Erection & Testing work of One coat primer and two coat paint for pipe line & support | — | — | — | 5,595.25 | |
| Supply and Foundation work of Butter fly valve 150NB,MAKE-KARTAR/SANT/ZOLOTO/SIR | — | — | — | 99,400 | |
| Installation, KARTAR/SANT/ZOLOTO/SIR | — | — | — | 9,450 | |
| — | — | — | valve | ||
| — | — | — | 150NB,MAKE- | ||
| Supply and Foundation work of GI clamp for pipe support. | — | — | — | 32,340 | |
| Installation, Erection & Testing work of GI clamp for pipe support. | — | — | — | 6,720 | |
| Supply and Foundation work of Wrapping coating for underground pipe.( 4mm thick pypkote Tape as per IS: 10221) | — | — | — | 2,01,300 | |
| Installation, Erection & Testing work of Wrapping coating for underground pipe.( 4mm thick pypkote Tape as per IS: 10221) | — | — | — | 29,700 | |
| Supply and Foundation work of Hydrant Valve, NEW AGE/KARTAR/FORCE | — | — | — | 5,64,021.15 | |
| Installation, Erection & Testing work of Hydrant Valve, MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 63,850.6 | |
| Supply and Foundation work of Hose Reel Drum With 30mtr hose pipe, MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 3,17,903.67 | |
| Installation, Erection & Testing work of Hose Reel Drum With 30mtr hose pipe, MAKE- NEW AGE/KARTAR/FORCE | — | — | — | 45,835.86 | |
| Supply and Foundation work of Branch Pipe/Nozzle, MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 2,46,610.65 | |
| Installation, AGE/KARTAR/FORCE | — | — | — | 43,421.4 | |
| Supply and Foundation work of Fire Hose Cabinet Box (Fabricated of 16G MS sheet (800X800X250) mm with 4mm thick glass., MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 5,29,105.5 | |
| Installation, Erection & Testing work of Fire Hose Cabinet Box (Fabricated of 16G MS sheet (800X800X250) mm with 4mm thick glass.MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 84,269.35 | |
| Supply and Foundation work of Hose Pipe 15 Meter Long (RRL Hose as per IS: 636, Type-A), MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 9,50,771.8 | |
| Installation, Erection & Testing work of Hose Pipe 15 Meter Long (RRL Hose as per IS: 636, Type-A), MAKE-NEW AGE/KARTAR/FORCE | — | — | — | 97,059.6 | |
| loading, unloading & transportation of Fire hydrant materials. | — | — | — | 86,282.13 | |
| Supply and Installation work of ABC/6KG as per IS: 15683 (2018)Service pressure < 19 bar powder based (as per IS 4308) | — | — | — | 4,36,625 | |
| Supply and Installation work of Co2/BC/4.5KG as as per IS: 15683 (2018)Service pressure < 19 bar Carbon Dioxide based (as per IS 15222) | — | — | — | 4,20,000 | |
| Supply and Foundation work of Addressable Manual call point Make- Agni/Simplex/EST | — | — | — | 1,44,279 | |
| Installation, Agni/Simplex/EST | — | — | — | 27,976.05 | |
| — | — | — | call point | ||
| Supply Agni/Simplex/EST | — | — | — | 1,91,901.42 | |
| — | — | — | cum | ||
| — | — | — | sounder | ||
| Installation, Erection & Testing work of Addressable Hooter cum sounder Make- Agni/Simplex/EST | — | — | — | 34,171.56 | |
| Supply and Foundation work of Isolator | — | — | — | 10,577 | |
| Installation, Erection & Testing work of Isolator | — | — | — | 2,380 | |
| Supply and Foundation work of SMPS 5 Amp for Hooter, | — | — | — | 31,273.75 | |
| Installation, Erection & Testing work of SMPS 5 Amp for Hooter, | — | — | — | 5,540.65 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
TenderDocument_.pdf
ATTACHMENT
Drawings.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .