Tender Value
₹3.9 L
EMD Value
₹8,000
Closing Date
9 Jan 2020, 6:00 pmClosed
Superintending Engineer -I 3x200MW BTPS Obra
Office of the superintending Engineer -I BTPS Obra
Preventive maintenance of small pumps and transportation of spares parts/ consumable from CSD-II to site store for unit no. - 9, 10 and 11 of 3X200MW, BTPS, Obra
2019_RVUNL_404232_1
T-15/SE-I/BTPS/TMD-I/2019-20
Open Tender
Miscellaneous Works
Fixed-rate
365 days
Unit no.9, 10 and11, 3x200MW BTPS OBRA
As per PQC
3 documents required · 3 mandatory
₹296
Deputy Chief Accounts Officer CFA and BO BTPS OBRA
₹8,000
30 Jun 2020
16 Nov 2019
16 Jan 2020
16 Nov 2019
9 Jan 2020
16 Nov 2019
16 Nov 2019 - 9 Jan 2020
Amount
Removal of chocking from the bearing cooling line of condensate pump by brush and high pressure air.
Replacement of cooling line / removal of chocking of bearing cooling of condensate pump by cutting welding at different places.
Removal of chocking of gland cooling line of drip pump by brush from header to drip pump.
Removal of mud from the cooling coil of BFP booster pump bearing by cutting and brazing.
Removal of chocking of gland cooling line of BFP Booster pump by cutting welding from header to gland box.
Removal of chocking /mud from the seal water cooler including O/H of seal water cooler of BFP.
Removal of chocking / mud from the header of BPF lub oil cooler and working oil cooler. (Main header inlet & outlet.)
Replacement of gland cooling header and branch line of BFP with proper union and square block / flange.
Installation of new phosphate dozing pump / Hydrazine pump/BCW pump / SWC pump / CW Booster pumps in 3X200MW unit.
Filling gland in condensate pump.
Filling gland in drip pump at both ends.
Cleaning of suction filter of hydrazine in phosphate pump.
Changing the plunger of hydrazine dozing pump.
Removal of mud /foreign partcle from the suction filter of air washer pumps.
Changing the plunger of phosphating dozing pump.
Transportation of spares part / consumable / oil from CSD to site store
Cleaning of main oil tank filter by air in 3X200MW units.
Checking level in different tank/ preventive maintenance work of different equipment of turbine during running / shut down of turbine at least 26 days in month per unit. (One job per unit.)
M/S ADITIYA VISHWAKARMA CONTRACTOR
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .