| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1st₹5.9 LAccepted-AOC | 1st | Accepted-AOC 1st lowest | |
| 2 | 2nd₹6.3 L+₹25,006 (4.10%)Rejected-Finance L PHAIKHOLUM LOKTAK PROJECT CHURACHANDPUR MANIPUR 795124 | BISHNUPUR | MANIPUR | 795124 | 2nd | Rejected-Finance 2nd lowest | |
| 3 | 3rd₹6.4 L+₹33,009 (5.41%)Rejected-Finance | 3rd | Rejected-Finance 3rd lowest | |
| 4 | Not Admitted-Fee/PreQual/Technical NINGTHOUKHONG GOPINATH LEIKAI BISHNUPUR MANIPUR 795126 | BISHNUPUR | BISHNUPUR | MANIPUR | 795126 | - | Not Admitted-Fee/PreQual/Technical Others-Tender Cost and other offline documents not received. |
Tender Value
Refer Docs
Closing Date
24 Dec 2022, 5:00 pmClosed
DGM (Civil), PnC Division
Office of the DGM (Civil), PnC Division, NHPC Ltd., Loktak Power Station, Komkeirap, Manipur-795124
Construction of waiting shed at Lamdan Kuki Village, Leimatak under CSR-SD Scheme.
2022_NHPC_725362_1
NH-LPS-HOP012(21)/5/2022-CD-I and III/992
Open Tender
Civil Works
Works
120 days
NHPC Ltd., Loktak Power Station
Please refer Tender documents.
6 documents required · 6 mandatory
₹590
NHPC Ltd.
Exempted
10 Mar 2023
24 Nov 2022
28 Dec 2022
24 Nov 2022
24 Dec 2022
24 Nov 2022
Amount
Earth work in excavation in foundation trenches or drains including dressing of sides and ramming of bottoms lift up to 1.5m including getting out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50m. b) Hard/Dense Soil.
Providing and laying in position cement concrete. All works up to plinth level.
Random Rubble Masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement: 6 coarse sand : 12 graded stone aggregate 20mm nominal size) at plinth level with 7.1.1 Cement mortar 1 cement: 6 coarse sand)
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete up to plinth level. 5.20.1 Thermo-Mechanically treated bar.
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete: Above Plinth level. 5.20A.2 Thermo-Mechanically treated bar.
Centering and shuttering including strutting, propping etc. and removal of form for: 5.9.1 Foundations, footings, bases of columns, etc. for mass concrete.
Providing and laying position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level: 5.1.1 (1 cement:1.5 coarse sand:3 graded stone aggregate 20mm nominal size)
Centering and shuttering including strutting, propping etc. and removal of form for (5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts.
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level excluding cost of centering, shuttering, finishing and reinforcement 5.2.1 (1 cement: 1.5 coarse sand : 3 graded stone aggregate cum 20 mm nominal size).
Centering and shuttering including strutting, propping etc. and removal of form for (5.9.5 Lintels, beams, plinth beams, girders, bressumers and cantilevers.
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 159 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 5.3 (1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size).
Brick work with 1st class common burnt clay F.P.S. (non-modular) bricks in foundation and plinth in: 6.1.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
Half brick masonry with 1st class common burnt clay F.P.S. (non-modular) bricks in superstructure above plinth level upto floor V level in: 6.9.2 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means by lifting material using mobile crane.
Steel work in built up tubular (round, square or rectangular tubes etc.) trusses etc., including cutting. hoisting fixing in position and applying a priming coat of approved steel primer, including welding and bolted including special shaped washers etc. comploto.10.16.3 Electric resistance or induction butt welded tubes.
Filling in plinth with sandy soil under floors including watering ramming, consolidation and dressing complete.
Providing and fixing pre-coated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in charge. The sheet shall be fixed using self-drilling itself tapping screws of size (5.5x 55 mm) with EPDM seal, complete up to any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required with:12.46.2 Pre-coated galvanised iron profile sheets 0.40 mm thick.
12mm cement plaster of mix 1:4 (1cement:4 coarse sand).
Neat Cement punning.
Providing and applying white cement based putty of average thickness 1mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete.
Applying priming coats with primer of approved brand and manufacture, having low VOC (Volatile Organic Compound) content.
Wall painting with plastic emulsion paint of approved brand and manufacture to give an even shade. 13.43.1 Two or more coats on new work
Cement concrete flooring 1:2:4 (1 cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry, but excluding the cost of nosing of steps etc. complete.11.2.1 40mm thick with 20mm nominal size stone aggregate.
P/L cement Concrete in retaining wall 1:3:6 ( 1 cement : 3 c/sand:6 aggregate, 40 mm)
Add EPF @ 0.65%
Add CESS @ 1%
Add GST @ 18%
M/S JANGKHOLUN HAOKIP
M/S R.K.KESHORJIT SINGH
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .