Tender Value
₹12.5 L
EMD Value
₹25,062
Closing Date
10 Apr 2026, 6:00 pmClosed
EXECUTIVE ENGINEER, PHED, DIS RURAL DIV I Jaipur
EXECUTIVE ENGINEER, PHED, DIS RURAL DIV I Jaipur
OPERATION AND MAINTENANCE OF TUBE WELL and PUMP HOUSE IN GONER UNDER JEN SECTION CHANDLAI SUB DIV CHAKSU
2026_PHCJA_549966_1
NIT no. 10/2026-27
Open Tender
Civil Works - Water Works
365 days
As Per Tender
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
EXECUTIVE ENGINEER, PHED, DIS RURAL DIV I Jaipur
₹25,062
Yes
16 Apr 2026
4 Apr 2026
13 Apr 2026
4 Apr 2026
10 Apr 2026
4 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Maintenance of pipelines irrespective of size and material which includes repairing of bursts and leakages, pollution control, survey and removal of choking, disconnection of illegal connections, collection and recording minimum 10 nos. residual chlorine samples during daily supply timings, interconnections and all works related to pipeline network in existing distribution/ rising main pipelines of all sizes by digging out suitable size of pit in soft and loose soil/ hard soil including cutting of black top, WBM and CC top of road of any size at work site. This will also include cutting of pipe ends, fixing of pipe piece with jjointing material to make repair leak proof and refilling of pit by excavated sand by ramming it at sides of pipes and upto ground level. For entire job, contractor will use their own T and P. Contractor with his own resources shall arrange dewatering, JCB and tractor compressor if any and restore any amenity at his own cost damaged while performing the work in this item. The work includes daily patrolling and repair the leakages within stipulated time and complete maintenance of pipeline network of rising and distribution pipeline network within the scope of work for per km pipeline per month. Jointing material shall be provided by the department. Minimum labour for a following kms pipelines to be deployed: | |||||
| 1.01 | 1 km to 50 km - One fitter and One beldar | - | Each/Month | - | - |
| 2Running expenditure ‘of pump houses which includes complete operation of pumpmotor, maintenance of Iog-books as directed by ‘Engineer-in-charge, general upkeeping of premises, security arrangements, Reguiar ‘ chemical dosing in CWR, cleaning and desilting of SR/CWR/SUMP once every six months, daily valve operation under the Campus of pump house and all other works as mentioned in scope of work in tender document for per pump house per month. (excluding repairing of pumping machinery etc.) | |||||
| 2.01 | Up to 100 HP | - | Each/Month | - | - |
| 5.01 | Maintenance of centrifugal pump sets and motor including cost of rewinding of motor, material components & accessories required to repair pumpsets, starters etc. of electric panels, deinstallation and re installation of pumpsets complete in all respect .for per Centrifugal pump set with pannel per month. maintenance of histroy sheet asdirected by Engineer-in-charge for centrifugal pump set per month. Operated load of Centrifugal Pump sets (HP) | - | - | - | - |
| 6.01 | 13.0 HP to 20.0 HP | - | Each/Month | - | - |
| 7.01 | Daily/periodical operation of valves at suppIy times for specified by department per sluice valve per month. (Valve rod and cap to be arranged by contractor). | - | - | - | - |
| 8.01 | 80-300 mm | - | Each/Month | - | - |
| 9.01 | Maintenance of tubewells which includes round the clock monitoring of tubewells of all sizes, complete repairs/ rewinding of submersible pumpsets including cost of material components required to repair pumpsets, starters, meters etc. of electric panel of tube wells lowering and unlowering of pumpsets complete in all respect, maintenance of log-books and history sheet as directed by Engineer-in-charge for tubewell per month. | - | - | - | - |
| 10.01 | 8.0 HP to 10.0 HP | - | Each/Month | - | - |
stage.html
html • 0.03 MB
technical_980375.pdf
techsummary_980375.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.37 MB
BOQ_980375.xls
BOQ • 0.38 MB
Tender.pdf
Tender Documents • 4.68 MB
Download all tender documents and submit your bid