| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹65.0 LAccepted-AOC BHOGAWAN HOUSE NO 207 CITY TOWN SILAPATHAR P O BHOGAWAN P S SILAPATHAR DISTRICT DHEMAJI PIN 787059 | DHEMAJI | ASSAM | 787059 | ₹65.0 L | L1 | Accepted-AOC L1 BIDDER |
| 2 | L2₹65.0 LRejected-AOC JILIKA PATH OPP KALAKHETRA CITY TOWN GUWAHATI PO BAGHORBARI PS DISPUR DIST KAMRUP M PIN 781037 | KAMRUP METRO | ASSAM | 781037 | ₹65.0 L | L2 | Rejected-AOC L1 BIDDER |
| Sl No | Description | Qty | Unit | Utpal Doley L2 | Birat Basumatary L1 |
|---|---|---|---|---|---|
| 1.00 | Embankment Construction with Material Obtained from Borrow Pits:
Construction of embankment with approved material obtained from borrow pits with all lifts upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirment of table 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 (i) From private land. | 2,227.48 | cum | 290 ₹6.5 L | 400 ₹8.9 L |
| 2.00 | Granular Sub-base with coarse graded materials (Table : 400-1) : (A) By Mix in place Method:
Construction of Granular Sub-base by providing coarse Graded Materials, spreading in uniform LAYER 1s with motor grader on prepared surface, mixing by mix in place method with rotovator at OMC and compacted with vibratory roller to achieve the desired complete as per cl. 401 (ii) For Grading i Material | 140.06 | cum | 2,500 ₹3.5 L | 2,000 ₹2.8 L |
| 3.00 | Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301 | 400 | cum | 3,300 ₹13.2 L | 3,000 ₹12 L |
| 4.00 | Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302
(I) Stone/Boulder | 72 | cum | 2,000 ₹1.4 L | 2,200 ₹1.6 L |
| 5.00 | Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302 | 36 | cum | 1,800 ₹64,800 | 2,000 ₹72,000 |
| 6.00 | RCC Box Culvert: (3 x 3m x 3m) at CH- 1100 m:
Excavation for Structures:arthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m,dressing of sides and bottom and backfilling in trenches with excavated suitable material.
I.Ordinary soil
(i)upto 3 m depth | 245.45 | cum | 150 ₹36,817.50 | 100 ₹24,545 |
| 7.00 | Filling in Foundation Trenches as per Drawing & Technical Specification Clause 305.3.9 (I) Sand Filling | 15.43 | cum | 1,200 ₹18,516 | 1,100 ₹16,973 |
| 8.00 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203
(B) With Natural Gravel
(II) P.C.C. Grade M15, Nominal Mix (1:2.5:5) | 19.92 | cum | 4,800 ₹95,616 | 5,000 ₹99,600 |
| 9.00 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203
A) With crushed stone
(IV) RCC Grade M20 | 54.49 | cum | 6,000 ₹3.3 L | 6,200 ₹3.4 L |
| 10.00 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203
(B) With Natural Gravel
(III) P.C.C. Grade M20, Nominal Mix (1:2:4) | 39.18 | cum | 6,000 ₹2.4 L | 5,800 ₹2.3 L |
Tender Value
₹65 L
EMD Value
₹1.3 L
Closing Date
6 Jan 2026, 4:30 pmClosed
EE, Jonai TRD, Silapathar
O/o Executive Engineer, Jonai Territorial Road Division, Silapathar, 787059
Recovery and Reconstruction of Silasuti Jipu-Brahmapur under NDRF (PDNA-2022) for the year 2025-26 under Jonai Territorial Road Division in Dhemaji District
2025_PWD_49769_1
TB68/JTRD/PDNA-22/2025-26/2092 Dtd 26/12/2025
Open Tender
Civil Works
Sissiborgaon
Please refer Tender documents.
6 documents required · 6 mandatory
₹1,950
₹1.3 L
Yes
22 Mar 2026
31 Dec 2025
7 Jan 2026
31 Dec 2025
6 Jan 2026
31 Dec 2025
Embankment Construction with Material Obtained from Borrow Pits: Construction of embankment with approved material obtained from borrow pits with all lifts upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirment of table 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 (i) From private land.
Granular Sub-base with coarse graded materials (Table : 400-1) : (A) By Mix in place Method: Construction of Granular Sub-base by providing coarse Graded Materials, spreading in uniform LAYER 1s with motor grader on prepared surface, mixing by mix in place method with rotovator at OMC and compacted with vibratory roller to achieve the desired complete as per cl. 401 (ii) For Grading i Material
Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301
Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302 (I) Stone/Boulder
Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302
RCC Box Culvert: (3 x 3m x 3m) at CH- 1100 m: Excavation for Structures:arthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m,dressing of sides and bottom and backfilling in trenches with excavated suitable material. I.Ordinary soil (i)upto 3 m depth
Filling in Foundation Trenches as per Drawing & Technical Specification Clause 305.3.9 (I) Sand Filling
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 (B) With Natural Gravel (II) P.C.C. Grade M15, Nominal Mix (1:2.5:5)
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 A) With crushed stone (IV) RCC Grade M20
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 (B) With Natural Gravel (III) P.C.C. Grade M20, Nominal Mix (1:2:4)
Plain/reinforced concrete in sub-structure complete as per drawings and technical specifications Clauses 802, 804, 805, 806, 807, 1202 & 1204 (B) With Natural Gravel (II) P.C.C. Grade M20, (I)Nominal Mix (1:2:4)
Plain/reinforced concrete in sub-structure complete as per drawings and technical specifications Clauses 802, 804, 805, 806, 807, 1202 & 1204 (A) With Crushed Stone (IV) R.C.C. Grade M25, (I) For Height Upto 5 m
Providing and laying reinforced cement concrete in super-structure as per drawing and Technical Specification' clauses 800, 1205.4 and 1205.5 A) With crushed stone ii) RCC Grade M25 (a)Height upto 5m
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/Jindal Steel/Shyam Steel/RINL) in foundation complete as per drawing and technical specifications clauses 1000 and 1202
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/Jindal Steel/Shyam Steel/RINL) in sub-structure complete as per drawing and technical specifications clauses 1002,1005,1010 and 1202
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/Jindal Steel/Shyam Steel/RINL) in super-structure complete as per drawing and technical specifications clauses 1002,1010 and 1202
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequat space between vertical posts for expansion, complete as per approved drawings and technical specifications.
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications (A) With Crushed Stone
Drainage Spouts complete as per approved drawing and Technical Specification
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specification clauses 614,709,1204.3.7
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification clause 1204.3.8 (i) Granular material
Providing and Laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications clause 1301
Boulder apron laid in wire crates : Providing & laying boulder apron laid in wire crates made with 4mm dia GI wire conforming to IS:280 & IS:4826 in 100mmX100mm mesh.(weaved diagonally) incldg.10% extra for laps and joints laid with stone boulder wieghting not less than 25 kg each as per drawing and technical specifications clause 1301
Construction of Return Wall and Curtain Wall in the existing damaged Culvert: Excavation for Structures:arthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m,dressing of sides and bottom and backfilling in trenches with excavated suitable material. I.Ordinary soil (i)upto 3 m depth
Filling in Foundation Trenches as per Drawing & Technical Specification Clause 305.3.9 (I) Sand Filling
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 (B) With Natural Gravel (II) P.C.C. Grade M15, Nominal Mix (1:2.5:5)
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803,1202 & 1203 (B) With Natural Gravel (III) P.C.C. Grade M20, Nominal Mix (1:2:4)
Plain/reinforced concrete in sub-structure complete as per drawings and technical specifications Clauses 802, 804, 805, 806, 807, 1202 & 1204 (B) With Natural Gravel (II) P.C.C. Grade M20, (I)Nominal Mix (1:2:4)
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specification clauses 614,709,1204.3.7
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification clause 1204.3.8 (i) Granular material
Providing and Laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications clause 1301
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.62 MB
SDB01.pdf
Tender Documents • 4.19 MB
BOQ_79125.xls
BOQ • 0.29 MB
FOB01.pdf
Additional Documents • 0.25 MB
Download all tender documents and submit your bid