Tender Value
₹3.7 L
EMD Value
₹3,651
Closing Date
29 Jun 2026, 4:00 pmClosed
Executive Engineer Irrigation Division No 3 Wyra
Irrigation Division No 3, Wyra, Q No CADA 2, NSP Camp Khammam
Reconstruction of Road culvert at KM 0.08 and aquaduct at KM 0.69 on 1R DP of Rapally Major of Bonakal Branch Canal, Pedda Gopati (V), Konijerla(M), Khammam District (6th Call)
710767
N I T. No: 04/2025-26, Dt: 18.07.2025
OPEN
Civil Works
KHAMMAM, TELANGANA
8 documents required · 8 mandatory
₹130
₹3,651
22 Jun 2026
22 Jun 2026
23 Jun 2026
Clearing thick jungle growth ( less than 50 percent open space ) including bushes upto 30 cm / parthenium and other weeds including burning or disposing off the same as directed etc., complete.
Excavation for Structures- Mechanical Means : Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) (for Foundations)
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for sub-structure / super-structure works., including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete with initial lead upto 50 m and all lifts. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90 cum, Blending Ratio of CA--50:30:20, FA : 0.40cum ) (for Super Structure)
Manufacture, Supply and Delivery of R.C.C. Socket and Spigot pipes conforming to B.I.S. 458/2003 at ex-factory (rate per meter of effective length) Excluding transportation, taxes & duties.(600 mm dia NP2)
Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes and collars ), machinery, labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 24.8 kg / joint, FA : 0.025 cum/joint, Hemp Yarn : 0.22kg/joint)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
NIT No.4 2025-26.docx
TENDER_DOCUMENT • 0.19 MB
NIT 4-BOQ (1).xls
TENDER_DOCUMENT • 0.62 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .