Tender Value
₹7.5 L
EMD Value
₹15,000
Closing Date
30 Sept 2026, 6:00 pm
Executive Engineer RRWD SMC
Executive Engineer RIGHT RIVER WORKS DIVISON REGAL LANE LAL CHOWK
Construction of tile lane and pipe drain from the hj/o Haroon Ahmad Maqdoomi to h/o Mushtaq Ahmad Sheikh and others at Shah Mohalla Ahmad Nagar (SXRCDF26270279)
2026_HAUDD_323989_11
NOTICE INVITING ETENDER No. 34 of 2026-2027 Dated 09.09.2026 RRWD SMC
Open Tender
Civil Works
Percentage
60 days
Shah Mohalla Ahmad Nagar
Please refer Tender documents.
2 documents required · 2 mandatory
₹303
FA/CAO AC NO 0216010200000007
₹15,000
9 Sept 2026
9 Sept 2026
1 Oct 2026
10 Sept 2026
30 Sept 2026
10 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Engagment of Labourers for site Clearance | 4 | No. | 553 | ₹2,212 |
| - | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 meters’ lead. For thickness of tiles above 25 mm and upto 40 mm. | 382.32 | Sqm | 89.95 | ₹34,389.68 |
| - | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-incharge: 1:3:6 or richer mix (i/c equivalent design mix) | 4.34 | Cum | 1,725.2 | ₹7,487.37 |
| - | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 Sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed: All kinds of soil : 1 meter from cutting edge | 26.33 | Cum | 479.3 | ₹12,619.97 |
| - | Providing aand laying stone soling including compacting, watering including all carriages of material complete including head load | 3.29 | Cum | 850 | ₹2,796.5 |
| - | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 19.34 | Cum | 5,202.9 | ₹1,00,624.09 |
| - | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 11.71 | Cum | 5,733.6 | ₹67,140.46 |
| - | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 26.34 | Cum | 6,591.25 | ₹1,73,613.53 |
| - | Chequerred precast cement concrete tiles 22mm thick in footpath and courtyard, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing, cleaning and curing complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand). Light shade using white cement | 108.73 | sqm | 1,293.6 | ₹1,40,653.13 |
| - | Removing of old damaged unserviceable PVC Pipes of various Dias i/c necessary excavation/wherever required and laying and fixing of new PVC pipes of approved Brand and quality B type including necessary fittings, all complete job 250 mm | 94.51 | Rmt | 1,246.4 | ₹1,17,797.26 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.24 MB
BOQ_1092221.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .