Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.8 LAdmitted-Finance | -0.01% | ₹1.8 L | L1 | Admitted-Finance |
| 2 | L2₹1.8 LAdmitted-Finance | +5.00% | ₹1.8 L | L2 | Admitted-Finance |
| 3 | L3₹1.8 LAdmitted-Finance | +5.20% | ₹1.8 L | L3 | Admitted-Finance |
Tender Value
₹1.8 L
EMD Value
₹4,000
Closing Date
27 Jan 2026, 2:00 pmClosed
Dy. Chief Engineer ( SWM-I )
Office of the Dy.CE (SWM-I) SOLID WASTE MANAGEMENT DEPARTMENT Kolkata Municipal Corporation 48, Market Street Kolkata-700 087 West Bengal
CONSTRUCTION OF MULTIPLE CAMERA PROTECTION BOX AT DHAPA CHECK POST UNDER SWM-I DEPARTMENT.
2026_KMC_989158_1
KMC/SWM-I/DDG/M/02/25-26
Open Tender
Miscellaneous Works
20 days
DHAPA DUMPING GROUND
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹4,000
10 Mar 2026
16 Jan 2026
29 Jan 2026
17 Jan 2026
27 Jan 2026
19 Jan 2026
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 1. M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length,fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. II) For Structural Works in Roof Trusses etc. using joists, channels and angles of specified section weighing less than 22.5 kg/ m (3rd Corrigenda & addenda dated 04.06.2018)
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 15. Supplying 1.5mm thick M.S. sheet fitted and fixed on one or both faces of M.S./ W.I. gate etc. with point welding at not more than 150mm apart complete in all respect as per design including cost of all labour and materials.
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. B. REPAIRING 1. Labour for lowering and stacking after dismantling in parts R.S. joists, channels, angles, tees, plates etc.complete as directed (a) From 1st floor level
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. B. REPAIRING 2. Welding in M.S. structural work with gas or electric: (b) Continuous weld.
BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. B. REPAIRING 1. Labour for lowering and stacking after dismantling in parts R.S. joists, channels, angles, tees, plates etc.complete as directed (b) Add extra for each addl. Floor
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 3. Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge. (This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly a) 3.90 metre height
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 3. Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge. (This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly b) Extra for additional 3.6 height or part thereof
SECTION 1. ------------BUILDING WORKS (K) PAINTING, VERNISHING ETC A. ORIGINAL WORKS 1 (a) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc (This item is applicable to new work or old work when the original surface has been exposed by removal of old paint.)
BUILDING WORKS (K) PAINTING, VERNISHING ETC?(A) ORIGINAL WORKS.(2)(A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :(b) On steel or other metal surface :With super gloss (hi-gloss) -(iv) Two coats (with any shade except white)
Sub Total
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.13 MB
BOQ_2416698.xls
BOQ • 0.34 MB
FORM.pdf
Tender Documents • 0.78 MB
PRICE_BID.pdf
Tender Documents • 0.63 MB
Download all tender documents and submit your bid