| 1 | Admitted-Finance C O VOLTAS LIMITED SPARE PARTS DEPOT OLD HUTMENT COLONY NCL NIGAHI SINGRAULI M P 486884 | SINGRAULI | SINGRAULI | MADHYA PRADESH | 486884 | Admitted-Finance |
Tender Value
₹66.8 L
EMD Value
₹83,500
Closing Date
7 Aug 2024, 11:00 amClosed
GENERAL MANAGER (EXCAVATION)
OFFICE OF GM(EXCV) NIGAHI PROJECT,NCL,P.O-NIGAHI,DIST-SINGRAULI,M.P.
Offloading of different repair and maintenance work and daily General Checking and rectifica-tion work , demounting and mounting of Engine ,Transmission and Torque Converter as-sembly of CAT 789D 190T Dumpers for a pe-riod of 365 day (one year) atNWS
2024_NCL_312557_1
NGH/EXCV/TENDERS/24-25/061
Open Tender
Excavation Department Work
Item Rate
365 days
NIGAHI PROJECT
AS PER NIT
5 documents required · 5 mandatory
₹83,500
6 Oct 2024
15 Jul 2024
9 Aug 2024
15 Jul 2024
7 Aug 2024
16 Jul 2024
15 Jul 2024 - 25 Jul 2024
Amount
Scope of Work: Offloading of different repair and maintenance work and daily General Checking and rectifica-tion work , demounting and mounting of Engine ,Transmission and Torque Converter as-sembly of CAT 789D 190T Dumpers for a period of 365 day (one year) at NWS Nigahi Project having scope of work as follows- 1. Period: 365 days (a)Repair and Maintenance work and daily general checking and rectification work as per checklist of 29 nos. CAT789D 190T Dumpers fleet. (b)Manpower is required in General, First and Second shifts for performing repair and maintenance work and daily general checking and rectification work. (c)Work is to be performed as per periodic maintenance and schedule maintenance checklist of 29 nos. CAT 789D 190T dumpers. 2. Demounting and mounting of Engine and its related parts of 8 Nos CAT 789D 190T dumpers as and when required within Contract Period. PER JOB COMPLETION WITHIN 6 DAYS. 3. Demounting and mounting of Transmission and its related parts of 10 Nos CAT 789D 190T dumpers as and when required within Contract Period.PER JOB COMPLETION WITHIN 4 DAYS. 4. Demounting and mounting of Torque Converter and its related parts of 10 Nos CAT 789D 190T dumpers as and when required within Contract Period.PER JOB COMPLETION WITHIN 4 DAYS. Note:-Manpower deployed for subjected job as per scope of work consisting of Skilled and Semi skilled manpower should have ITI qualification. Same shall be verified.
Repair and Maintenance work and Daily General Checking and Rectification work as per checklists of CAT 789D 190T dumpers. Maximum likely manpower to be deployed: 06 per shift (02 Nos Skilled fitter ,01 No. Skilled Electrician , Skilled Welder 01No. , Semi Skilled 02Nos. )
Cost/charges for Repair and Maintenance work and Daily General Checking and Rectification work in FIRST SHIFT as per checklists of CAT 789D 190T dumpers including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician and semi skilled Helper manpower)
Cost/charges for Repair and Maintenance work and Daily General Checking and Rectification work in GENERAL SHIFT as per checklists of CAT 789D 190T dumpers including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled welder ,Skilled Electrician and semi skilled Helper manpower)
Cost/charges for Repair and Maintenance work and Daily General Checking and Rectification work in SECOND SHIFT as per checklists of CAT 789D 190T dumpers including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician and semi skilled Helper manpower)
Cost/charges for 3 set Tools & Tackles per day for all the above jobs of Sl No. 2.
Demounting and Mounting of Engine and its related parts of 8 nos. CAT 789D 190T dumpers , Maximum likely manpower for each job to be deployed: 06 (02 Nos Skilled fitter ,01 No. Skilled Electrician , Semi Skilled 02Nos. , Unskilled 1 nos)
Cost/charges for demounting of Engine assy and its related parts for CAT 789D 190T dumper including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician , semi skilled and unskilled manpower) , Total 8 jobs
Cost / Charges for Tools and Tackles for all jobs at Sl no 3.01
Cost/charges for mounting of Engine assy and its related parts for. CAT 789D 190T dumper for CAT 789D 190T dumper including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician , semi skilled and unskilled manpower) , Total 8 jobs
Cost / Charges for Tools and Tackles for all jobs at Sl no 3.03
Demounting and Mounting of Transmission and its related parts of 10 nos. CAT 789D 190T dumpers ,Maximum likely manpower for each job to be deployed: 06 (02 Nos Skilled fitter ,01 No. Skilled Electrician , Semi Skilled 02Nos. , Unskilled 1 nos)
Cost/charges for demounting of Transmission assy and its related parts for CAT 789D 190T dumper including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician ,semi skilled and unskilled manpower) , Total 10 jobs
Cost / Charges for Tools and Tackles for all jobs at Sl no 4.01
Cost/charges for mounting of Transmission assy and its related parts for CAT 789D 190T dumper including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician , semi skilled and unskilled manpower) , Total 10 jobs
Cost / Charges for Tools and Tackles for all jobs at Sl no 4.03
Demounting and Mounting of Torque Converter and its related parts of 10 nos. CAT789D 190Tdumpers , Maximum likely manpower for each job to be deployed: 06 (02 Nos Skilled fitter ,01 No. Skilled Electrician , Semi Skilled 02Nos. , Unskilled 1 nos)
Cost/charges for demounting of Torque Converter assy and its related parts for CAT 789D 190T dumper including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician , semi skilled and unskilled manpower) , Total 10 jobs
Cost / Charges for Tools and Tackles for all jobs at Sl no 5.01
Cost/charges for mounting of Torque Converter assy and its related parts for CAT 789D 190T dumper including labour charges , contractor profit ,etc. (labour consisting of Skilled fitter, Skilled Electrician , semi skilled and unskilled manpower) , Total 10 jobs
Cost / Charges for Tools and Tackles for all jobs at Sl no 5.03
Total impact of GST for the purpose of CTC
stage.html
html • 0.02 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .