Loading…
Loading…
Tender Value
₹9.9 L
EMD Value
₹10,000
Closing Date
29 Sept 2026, 3:00 pm7d left
Executive officer
Arulmigu subramanyaswamy thirukoil at Vallakottai village, Sriperumpudhur Taluk, Kancheepuram district
Attending Renovation works in Annadhana koodam in Arulmigu subramanyaswamy thirukoil at Vallakottai village, Sriperumpudhur Taluk, Kancheepuram district
2026_HRCE_703684_1
02/2026
Open Tender
Civil Works
Lump-sum
90 days
vallakottai
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹10,000
Yes
11 Sept 2026
11 Sept 2026
29 Sept 2026
11 Sept 2026
29 Sept 2026
11 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismandling the existing damaged compound wall (Brick/stone masonry in cement mortar walls under 3m Dismandling brick work | 3 | cum | 283.14 | ₹849.42 |
| 2 | Earth work excavation for foundation (for narrow excavation) in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, hailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 10 mts and lift of following metres and clearing and levelling the site, etc., complete complying with standard specification | 3 | cum | 219.74 | ₹659.22 |
| 3 | Supplying and filling in foundation, baserment, etc with filling crushed stone sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specificating and as directed by the departmental officers. | 10 | cum | 1,574.16 | ₹15,741.6 |
| 4 | Cement concrete 1:5:10 (One part of cement five part of M-sand and ten part of HBG jelly) for foundation using 40mm gauge HBG jelly inclusive of shoring strutting and baling out water where ever necessary ramming curing etc..complete as per Std, Specification and as directed by the Dept, Officers | 5 | cum | 5,018.95 | ₹25,094.75 |
| 5 | Providing granolithic floor finish 20mm thick with cement mortar 1:2 (one part of cement and two part of sand) 10 to 12mm metal including cost of all materials and labor charges for laying rubbing the top surface for smooth etc., complete complying with standard specifications. | 46 | sqm | 159 | ₹7,314 |
| 6 | Providing and laying position, Standardised concrete mi M-20 Grade in accordance with IS:456-2000, using 20mm and down graded hard brocken granite stone jelly for all Rcc items of works with minimum cement content of 3250 kg/cum and maximum water cement ratio of 0.55,inculding admiture (plasticiser/super plasticiser) in recommended proportions as per IS:9103 to accelerate, retart setting of concrete, improve workablity without imparing strengh and durability with about (5 cum)7730 kg. of 20mm machine crushed stone jelly and with about (3.3 cu.m)5156 kg of 10-12 mm machine crushed stone jelly and with about(4.79 cu.m)7670 kg of M-sand, but eculding cost of reinforcement grill and fabricating charges.centering and shuttering and also including laying ,vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers. The coarse and fine aggregates to be used should comply with the requirements of IS Standards. (No separate payment will be made by the Department for the excess usage of materials). | 0.7 | cum | 8,377.97 | ₹5,864.58 |
| 7 | Supplying and erecting centering for sides and soffits including necessary supports and strutting ugto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 om spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre ete. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) | 6.2 | sqm | 1,036.55 | ₹6,426.61 |
| 8 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire) | 0.7 | qtl | 8,988.35 | ₹6,291.85 |
| 9Brick work in cement mortar 1:5 (one part of cement and five part of sand) using second class ground moulded Chamber bricks size 9" x 43/8" x 23/4" including cost and conveyance of all materials and labour charges and all other incidental charges etc complete complying with standard specification. | |||||
| 9.1 | Foundation & Basement | 1.5 | cum | 7,156.18 | ₹10,734.27 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.22 MB
conditions.pdf
Tender Documents • 0.80 MB
BOQ_845837.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .