Road repair work by CC on the damaged road from A-78 to A-76 in Ward 94 Suryanagar Rampuri.
2026_DOLBU_1190645_36
132/Nirman/2026-27 Dated 18-09-2026 (401-600)
Open Tender
Civil Works
Percentage
Ghaziabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,416
₹54,659
30 Sept 2026
30 Sept 2026
15 Oct 2026
30 Sept 2026
15 Oct 2026
30 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantelling of old rcc/rb ramp in lime or cement concrete mortar and including stacking of material as direction be the engineer in charge Pwd sor 2022 iten no 17.3 | 6.94 | cum | 1,340 | ₹9,294.24 |
| - | S/l of 22.4 to 53 mm gauge stone ballast stacking for measurement etc all complete as per the direction of engineer charge (As per pwd sor 2020 RMR) | 7.33 | cum | 2,151.2 | ₹15,768.3 |
| - | Consolidation of stone ballast in aggreated 40 to 63 mm to 22. 4 to 53 mm aguge stone ballast size to water bound macadam specification including spreating in uniform thickness hand packing rolling with three wheels 80-100km static roller in satges to p | 7.33 | cum | 690 | ₹5,057.7 |
| 4 | Disposal of malba upto 8km lead as per direction in engineer in charge as per ped sor 2022 page no 18 si no 6.05 item no 305(a) | 13.87 | cum | 195.1 | ₹2,705.45 |
| - | S/L of Take coat of bitumin @ 0.30kg/sqm including heating the vg 10bitumin spraying the bitumin boiler & cleaning and preparing the existing road surface etc all complete as per the direction of engineer in charge (As per RMR) | 2,115.75 | sqm | 17.6 | ₹37,237.2 |
| - | Providing and laying dence graded (D.G.B.M)bituminious macadam with Hmp producing an average output of 75 tonnes per hoiur usng crused aggregate from approaved quarry of specification gradeing premixed the bitumin binder vg-30 @4.5 percenrt by weight of total mix and filler transportation the hot mix to work site laying for proper completion of work as per direction of enginner in charge including all labour T&P taxs labour cess etc as per RMR | 11.08 | cum | 14,199.6 | ₹1,57,331.57 |
| - | Recycling pavement by cold milling of exisiting bituminous layers using by bituminous concrete (grading 2) using bitumen VG 30 content is 5.4% bitumen weight of mix for reclaimed material fresh bitumen will be required to the extent of 60% of normal requiredment planning the surface after cold milling reclaiming excavated material to the extent of 30% of the required quantity hauling and stock pilling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation adding fresh material inluding rejuvenators as required mixing in a hot mix plant transporting and laying at site and compacting to the required grade level and thickness all as morth specified in clause 519 | 84.63 | cum | 14,854.9 | ₹12,57,170.19 |
| - | S/L of hot applied thermo plastic compound 2.5mm thick including reflectorising glass beads @250 gms per sqm area thickness of 2.5mm is exclusive of surface applied glass beads as per irc 35 the finished surface to be level uniformed and fee from streak and hole rates all including of all tax as per pwd sor 2022 si no 22.02 new item | 96.25 | sqm | 618 | ₹59,482.5 |
| 9 | GST | 18 | Percentage | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 20.10 MB
BOQ_2244502.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .