Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.3 LAccepted-AOC 520C MAIN ROAD WARD NO 12 METTU STREET ELAMBALUR PERAMBALUR | PERAMBALUR | PERAMBALUR | TAMIL NADU | 621220 | ₹3.3 L Quoted ₹2.8 L | L1 | Accepted-AOC L1 |
| 2 | Not Admitted-Fee/PreQual/Technical 1 367 SIVAN KOVIL STREET THONDAMATHURAI POST VEPPANTHATTAI TALUK PERAMBALUR DISTRICT | PERAMBALUR | TAMIL NADU | 621101 | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | KDM BUILDERS AND CONTRACTORS L1 |
|---|---|---|---|---|
| 1.01 | Earth work excavation for all type of soils and depositing on bank with initial lead of 10m and initial lift of 2m for foundations, grade beam, septick tank and water sump etc., including cost of all materials, lead, lift, T&Ps, etc., complete and as directed by the Engineer incharge of the work. | 35.6 | Cum | 243 ₹286.74 |
| 1.02 | Supplying and filling the basement and foundation with M.sand watering and consolidation etc., including cost of materials, labour, lead, lift, T&P etc., and as directed by the Engineer incharge of the work. | 5.11 | Cum | 1,950 ₹2,301 |
| 1.03 | PCC 1:4:8 using 40mm HB stone for foundation, flooring, etc., in the following levels as instructed by the Engineer in charge including cost of all materials, labour, lead lift, T&P, etc., complete. | 3.8 | Cum | 6,000 ₹7,080 |
| 1.04 | RCC M20 using 12-20mm HBG stone using minimum cement content of 360 KG for Raft with out form work for foundation including cost of all materials labour ,lead, lift etc complete and as directed by the Engineer incharge but excluding cost of steel reinforcement. | 3.8 | Cum | 9,000 ₹10,620 |
| 1.05 | RCC M20 using 12-20mm HBG stone using minimum cement content of 360 KG for cable trench side wall with form work for foundation including cost of all materials labour ,lead, lift etc complete and as directed by the Engineer incharge but excluding cost of steel reinforcement. | 6.8 | Cum | 15,000 ₹17,700 |
| 1.06 | RCC 1:1.5:3 using 12 to 20 mm HBG machine crushed metal for Precast slab including cost of cement and all lead, lift, T&Ps, curing, etc., complete and as directed by Engineer incharge of the work but excluding cost of steel reinforcement. but excluding cost of steel reinforcement. | 3 | Cum | 12,200 ₹14,396 |
| 1.07 | Providing steel reinforcement for RCC works including cost of steel, binding wire and labour for cutting, bending, tying and placing in position, lead lift, T&Ps, etc., complete and as directed by the Engineer incharge of the work. | 556 | Kg | 85 ₹100.3 |
| 1.08 | Supplying and fixing in position GI angle 50x50x6mm and channel of required length for fixing the cable duct, as per the direction of site Engineer including cost of all materials, lead, lifts, and cutting the GI angle required length and labour for fixing etc, complete. | 158 | Kg | 126 ₹148.68 |
Tender Value
₹2 L
EMD Value
₹2,000
Closing Date
4 Feb 2026, 2:00 pmClosed
Superintending Engineer/ PEDC / Perambalur
O/o. Superintending Engineer/ PEDC / Perambalur, 4road, Perambalur
Improvement works by providing RCC cable duct at Keelaperambalur 33 11 KV SS
2026_EB_645406_1
Civil-E-17/2025-26
Open Tender
Civil Works
60 days
Keela Perambalur
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹2,000
4 Mar 2026
21 Jan 2026
5 Feb 2026
21 Jan 2026
4 Feb 2026
21 Jan 2026
Earth work excavation for all type of soils and depositing on bank with initial lead of 10m and initial lift of 2m for foundations, grade beam, septick tank and water sump etc., including cost of all materials, lead, lift, T&Ps, etc., complete and as directed by the Engineer incharge of the work.
Supplying and filling the basement and foundation with M.sand watering and consolidation etc., including cost of materials, labour, lead, lift, T&P etc., and as directed by the Engineer incharge of the work.
PCC 1:4:8 using 40mm HB stone for foundation, flooring, etc., in the following levels as instructed by the Engineer in charge including cost of all materials, labour, lead lift, T&P, etc., complete.
RCC M20 using 12-20mm HBG stone using minimum cement content of 360 KG for Raft with out form work for foundation including cost of all materials labour ,lead, lift etc complete and as directed by the Engineer incharge but excluding cost of steel reinforcement.
RCC M20 using 12-20mm HBG stone using minimum cement content of 360 KG for cable trench side wall with form work for foundation including cost of all materials labour ,lead, lift etc complete and as directed by the Engineer incharge but excluding cost of steel reinforcement.
RCC 1:1.5:3 using 12 to 20 mm HBG machine crushed metal for Precast slab including cost of cement and all lead, lift, T&Ps, curing, etc., complete and as directed by Engineer incharge of the work but excluding cost of steel reinforcement. but excluding cost of steel reinforcement.
Providing steel reinforcement for RCC works including cost of steel, binding wire and labour for cutting, bending, tying and placing in position, lead lift, T&Ps, etc., complete and as directed by the Engineer incharge of the work.
Supplying and fixing in position GI angle 50x50x6mm and channel of required length for fixing the cable duct, as per the direction of site Engineer including cost of all materials, lead, lifts, and cutting the GI angle required length and labour for fixing etc, complete.
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.32 MB
Spc17.pdf
Tender Documents • 0.91 MB
BOQ_773448.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid