Tender Value
₹2.6 Cr
EMD Value
₹5.3 L
Closing Date
5 Oct 2026, 4:00 pm
executive engineer IFC Div Sgr
BATAMALOO
Construction of Balhama khul from khanmoh via Balhama to Pampore by way of construction of lining walls for a length of 1800 mtrs on both sides 6 No culvert crossings desilting of canals
2026_IFC_325351_1
18
Open Tender
Civil Works
Percentage
Srinagar
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
Executive Engineer Ifc Division Srinagar
₹5.3 L
21 Sept 2026
21 Sept 2026
6 Oct 2026
21 Sept 2026
5 Oct 2026
21 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.
All kinds of soil : | 890.55 | cum | 187.3 | ₹1,66,800.02 |
| 2 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.
All kinds of soil : | 3,243.73 | cum | 592.9 | ₹19,23,207.52 |
| 3 | Silt clearance from canals. Inclusive of initial lead and lift ( 50m & 1.5m respectively ) Dry | 452.03 | cum | 111 | ₹50,175.33 |
| 3.1 | Wet | 3,254.58 | cum | 184.95 | ₹6,01,934.57 |
| 4 | Removal of unhygienic materials (so classified by the site engineer) from designated sites and its disposal as per directions, all inclusive. | 452.03 | cum | 189.2 | ₹85,524.08 |
| 5 | Dumping stone excluding cost of stones
in Horizontal on level | 464.89 | cum | 237.9 | ₹1,10,597.33 |
| 6 | Supply of stones/boulders | 464.89 | cum | 700 | ₹3,25,423 |
| 7 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:
1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 207.59 | cum | 5,202.9 | ₹10,80,070.01 |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form for:
Foundations, footings, bases of columns etc. for mass concrete. | 8,914.92 | Sqm | 286.35 | ₹25,52,787.34 |
| 8.1 | Suspended floors, roofs, landings, balconies and access platforms. | 37.2 | Sqm | 718.2 | ₹26,717.04 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.68 MB
BOQ_1099058.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .