| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹94.7 LAccepted-AOC 0 MANPUR CHITBARAGAON CHITBARAGAON BALLIA UTTAR PRADESH 221713 | BALLIA | UTTAR PRADESH | 221713 | ₹94.7 L Quoted ₹95.5 L | L1 | Accepted-AOC L1 Bidder |
| 2 | L2₹1.0 Cr+₹5.6 L (5.88%)Rejected-Finance | ₹1.0 Cr+₹5.6 L (5.88%) | L2 | Rejected-Finance Other than L1 Bidder |
| 3 | L3₹1.1 Cr+₹13.2 L (13.8%)Rejected-Finance | ₹1.1 Cr+₹13.2 L (13.8%) | L3 | Rejected-Finance Other than L1 Bidder |
| 4 | L4₹1.1 Cr+₹16.9 L (17.7%)Rejected-Finance | ₹1.1 Cr+₹16.9 L (17.7%) | L4 | Rejected-Finance Other than L1 Bidder |
| 5 | Rejected-Technical | - | - | Rejected-Technical Rejected due to three class below the eligible class as per NIT |
| Sl No | Description | Qty | Unit | R.K. Works L4 | M/s Mool Raj Ramesh Chander L2 | M/S PARVESH GUPTA L3 | NATIONAL TRADING COMPANY L1 |
|---|---|---|---|---|---|---|---|
| 1.00 | Scarifying or picking up gravelled macadam or bituminous macadam surfaces area not exc. 400 Sqm and depth exc. 50mm but not exc. 100mm deep, complete all as specified & directed. | 219 | 10 Sqm | 500 ₹1,09,500 | 450 ₹98,550 | 400 ₹87,600 | 40 ₹8,760 Lowest |
| 2.00 | 75 mm thick (compacted thickness) WBM, with coarse aggregates of grading 2 (63 to 40mm size) or of grading 3 (50 to 20mm size), spread, rolled and consolidated to gradient and camber required using Granite, trap or basalt and rolled with 10 to 12 tonnes power roller, each layer will be consolidated separately and to required gradient and camber, complete all as specified. | 219 | 10 Sqm | 2,500 ₹5,47,500 | 2,400 ₹5,25,600 | 2,200 ₹4,81,800 | 1,400 ₹3,06,600 Lowest |
| 3.00 | Repairs to pot holes any depth not exc 1 sqm each including sweeping free from dust and mud or water scoring sunken surfaces in roads paths etc cutting around edges to atlest 25mm in depth and making good by applying tack coat @ 5 kg per 10 sq m, putting in premixed bituminous macadam, well rammed and sealed with binder ( paving bitumen VG-30) 9.8 kg per 10 sq m, blinded with 0.09 cu m of stone chippings, 6.3 mm size and again well rammed (including supply of premixed macadam, binder and chippings). depth of pot holes exc 30 mm, complete all as specified and directed | 3.5 | 10 Sqm | 2,500 ₹8,750 | 2,200 ₹7,700 Lowest | 2,500 ₹8,750 | 6,800 ₹23,800 |
| 4.00 | Preparing water bound macadom surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surfaces with power sweeper or compressor to remove all loose dirt etc., applying evenly a priming/ tack coat with bituminous primer using paving bitumen VG-10 at 10 kg per 10 sq metre of road surface Complete all as specified and as directed. | 219 | 10 Sqm | 800 ₹1,75,200 | 800 ₹1,75,200 | 800 ₹1,75,200 | 300 ₹65,700 Lowest |
| 5.00 | Bituminous premix semi-dense asphaltic concrete 40 mm consolidated thickness using paving bitumen VG-30 wiith 5.5% binder content by weight of total mix rolled and compacted to required camber and gradient complete and rolled with 8 to 10 tonne power roller complete all as specified and directed. Note:- (I) In case the binder contents by weight of total mix is less than 5.5% as per per actual design mix, The prices adjustment shall be made as per average rates of all paid voucher for bitumen pertaining to this work. if the total binder contents as per design mix is more than 5.5% no prices adjustment shall be made for the same. (II) Job mix formula for Semi Dense asphaltic concrete shall be obtained from the institutions specified in CA prior to commencement of work and shall be got approved from the GE.
(iii) The Contractor shall submit certificate issued to Hot mix plant that plant is SDAC compliant before incorporating workat site. The Hot Mix plant visit has to be organized by Contractor for approval of GE.
(iv) The plant shall be automatic type which must have facility to print the details of composition of material incorporated with all batches of SDAC. | 219 | 10 Sqm | 6,000 ₹13,14,000 Lowest | 6,000 ₹13,14,000 Lowest | 6,600 ₹14,45,400 | 9,200 ₹20,14,800 |
| 6.00 | Preparing Black top surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surfaces with power sweeper or compressor to remove all loose dirt etc., applying evenly a priming/ tack coat with bituminous primer using paving bitumen VG-10 at 05 kg per 10 sq metre of road surface Complete all as specified and as directed. | 799 | 10 Sqm | 400 ₹3,19,600 | 300 ₹2,39,700 | 300 ₹2,39,700 | 120 ₹95,880 Lowest |
| 7.00 | Bituminous premix semi-dense asphaltic concrete 30 mm consolidated thickness using paving bitumen VG-30 wiith 5.5% binder content by weight of total mix rolled and compacted to required camber and gradient complete and rolled with 8 to 10 tonne power roller complete all as specified and directed. Note:- (I) In case the binder contents by weight of total mix is less than 5.5% as per per actual design mix, The prices adjustment shall be made as per average rates of all paid voucher for bitumen pertaining to this work. if the total binder contents as per design mix is more than 5.5% no prices adjustment shall be made for the same. (II) Job mix formula for Semi Dense asphaltic concrete shall be obtained from the institutions specified in CA prior to commencement of work and shall be got approved from the GE.
(iii) The Contractor shall submit certificate issued to Hot mix plant that plant is SDAC compliant before incorporating workat site. The Hot Mix plant visit has to be organized by Contractor for approval of GE.
(iv) The plant shall be automatic type which must have facility to print the details of composition of material incorporated with all batches of SDAC. | 580 | 10 Sqm | 5,000 ₹29,00,000 Lowest | 5,200 ₹30,16,000 | 6,000 ₹34,80,000 | 6,200 ₹35,96,000 |
| 8.00 | Providing premix bituminous macadam with 4% bitumen binder by weight of total mix laid/rolled and compacted to required gradient and camber (consolidated thickness 75mm or less) (paving bitumen VG-30) by weight of total mix spread, rolled and consolidated with 8 to 12 tonne power roller to required gradient and camber complete all as specified and directed. Note:- (I) In case the binder contents by weight of total mix is less than 4% as per per actual design mix, The prices adjustment shall be made as per average rates of all paid voucher for bitumen pertaining to this work. if the total binder contents as per design mix is more than 4% no prices adjustment shall be made for the same. (II) Job mix formula for bituminous macadam shall be obtained from the institutions specified in CA prior to commencement of work and shall be got approved from the GE.
(iii) The Contractor shall submit certificate issued to Hot mix plant that plant is SDAC compliant before incorporating workat site. The Hot Mix plant visit has to be organized by Contractor for approval of GE.
(iv) The plant shall be automatic type which must have facility to print the details of composition of material incorporated with all batches of SDAC. | 109.5 | Cum | 12,000 ₹13,14,000 | 10,000 ₹10,95,000 | 14,000 ₹15,33,000 | 8,500 ₹9,30,750 Lowest |
| 9.00 | M&L for preparing bituminous surfaces of road and making 2.5mm thick centre lines, stop lines, dashes, arrows etc, and the like not exceeding than 10cm wide on roads pavements with hot applied thermo plastic road marking paint of approved colour confirming to BS 3262-1989 with specifal applicator machine all as per manufacturer's instruction including cleaning the surface by removing all dirt, dust & all other forein matters, demarcation at site and traffic control, complete all as specified and directed. | 2,750 | Rm | 400 ₹11,00,000 | 100 ₹2,75,000 | 100 ₹2,75,000 | 95 ₹2,61,250 Lowest |
| 10.00 | Supply and fixing cat eye solar reflective type of metal body alloy of size 100mm x 100mm x 20mm with PAMA striplens reflector of model No. DA 972.0 fixed with and incl MS stud of suitable size as per manufactures instructions. including removal of old cat eye ,complete all as specified and directed. | 418 | Each | 500 ₹2,09,000 | 450 ₹1,88,100 Lowest | 450 ₹1,88,100 Lowest | 500 ₹2,09,000 |
Tender Value
₹1.0 Cr
EMD Value
₹1.8 L
Closing Date
2 Apr 2026, 6:00 pmClosed
CWE Rajouri
HQ CWE Rajouri C/o 56 APO
SPL REPAIR TO ROAD AT VARIOUS LOCATIONS AT NAUSHERA GARRASION(GARHI, KALSIYAN AND JHANGAR BASE ) UNDER GE 862 EWS
2026_MES_755076_1
CWE/RAJ-107/2025-26
Open Tender
Civil Works - Roads
Item Rate
180 days
GE 862 EWS
As per tender documents
8 documents required · 8 mandatory
₹1,000
GE 862 EWS
₹1.8 L
Yes
17 Jul 2026
4 Mar 2026
9 Apr 2026
4 Mar 2026
2 Apr 2026
25 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Scarifying or picking up gravelled macadam or bituminous macadam surfaces area not exc. 400 Sqm and depth exc. 50mm but not exc. 100mm deep, complete all as specified & directed. | 219 | 10 Sqm | - | - |
| 2 | 75 mm thick (compacted thickness) WBM, with coarse aggregates of grading 2 (63 to 40mm size) or of grading 3 (50 to 20mm size), spread, rolled and consolidated to gradient and camber required using Granite, trap or basalt and rolled with 10 to 12 tonnes power roller, each layer will be consolidated separately and to required gradient and camber, complete all as specified. | 219 | 10 Sqm | - | - |
| 3 | Repairs to pot holes any depth not exc 1 sqm each including sweeping free from dust and mud or water scoring sunken surfaces in roads paths etc cutting around edges to atlest 25mm in depth and making good by applying tack coat @ 5 kg per 10 sq m, putting in premixed bituminous macadam, well rammed and sealed with binder ( paving bitumen VG-30) 9.8 kg per 10 sq m, blinded with 0.09 cu m of stone chippings, 6.3 mm size and again well rammed (including supply of premixed macadam, binder and chippings). depth of pot holes exc 30 mm, complete all as specified and directed | 3.5 | 10 Sqm | - | - |
| 4 | Preparing water bound macadom surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surfaces with power sweeper or compressor to remove all loose dirt etc., applying evenly a priming/ tack coat with bituminous primer using paving bitumen VG-10 at 10 kg per 10 sq metre of road surface Complete all as specified and as directed. | 219 | 10 Sqm | - | - |
| 5 | Bituminous premix semi-dense asphaltic concrete 40 mm consolidated thickness using paving bitumen VG-30 wiith 5.5% binder content by weight of total mix rolled and compacted to required camber and gradient complete and rolled with 8 to 10 tonne power roller complete all as specified and directed. Note:- (I) In case the binder contents by weight of total mix is less than 5.5% as per per actual design mix, The prices adjustment shall be made as per average rates of all paid voucher for bitumen pertaining to this work. if the total binder contents as per design mix is more than 5.5% no prices adjustment shall be made for the same. (II) Job mix formula for Semi Dense asphaltic concrete shall be obtained from the institutions specified in CA prior to commencement of work and shall be got approved from the GE.
(iii) The Contractor shall submit certificate issued to Hot mix plant that plant is SDAC compliant before incorporating workat site. The Hot Mix plant visit has to be organized by Contractor for approval of GE.
(iv) The plant shall be automatic type which must have facility to print the details of composition of material incorporated with all batches of SDAC. | 219 | 10 Sqm | - | - |
| 6 | Preparing Black top surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surfaces with power sweeper or compressor to remove all loose dirt etc., applying evenly a priming/ tack coat with bituminous primer using paving bitumen VG-10 at 05 kg per 10 sq metre of road surface Complete all as specified and as directed. | 799 | 10 Sqm | - | - |
| 7 | Bituminous premix semi-dense asphaltic concrete 30 mm consolidated thickness using paving bitumen VG-30 wiith 5.5% binder content by weight of total mix rolled and compacted to required camber and gradient complete and rolled with 8 to 10 tonne power roller complete all as specified and directed. Note:- (I) In case the binder contents by weight of total mix is less than 5.5% as per per actual design mix, The prices adjustment shall be made as per average rates of all paid voucher for bitumen pertaining to this work. if the total binder contents as per design mix is more than 5.5% no prices adjustment shall be made for the same. (II) Job mix formula for Semi Dense asphaltic concrete shall be obtained from the institutions specified in CA prior to commencement of work and shall be got approved from the GE.
(iii) The Contractor shall submit certificate issued to Hot mix plant that plant is SDAC compliant before incorporating workat site. The Hot Mix plant visit has to be organized by Contractor for approval of GE.
(iv) The plant shall be automatic type which must have facility to print the details of composition of material incorporated with all batches of SDAC. | 580 | 10 Sqm | - | - |
| 8 | Providing premix bituminous macadam with 4% bitumen binder by weight of total mix laid/rolled and compacted to required gradient and camber (consolidated thickness 75mm or less) (paving bitumen VG-30) by weight of total mix spread, rolled and consolidated with 8 to 12 tonne power roller to required gradient and camber complete all as specified and directed. Note:- (I) In case the binder contents by weight of total mix is less than 4% as per per actual design mix, The prices adjustment shall be made as per average rates of all paid voucher for bitumen pertaining to this work. if the total binder contents as per design mix is more than 4% no prices adjustment shall be made for the same. (II) Job mix formula for bituminous macadam shall be obtained from the institutions specified in CA prior to commencement of work and shall be got approved from the GE.
(iii) The Contractor shall submit certificate issued to Hot mix plant that plant is SDAC compliant before incorporating workat site. The Hot Mix plant visit has to be organized by Contractor for approval of GE.
(iv) The plant shall be automatic type which must have facility to print the details of composition of material incorporated with all batches of SDAC. | 109.5 | Cum | - | - |
| 9 | M&L for preparing bituminous surfaces of road and making 2.5mm thick centre lines, stop lines, dashes, arrows etc, and the like not exceeding than 10cm wide on roads pavements with hot applied thermo plastic road marking paint of approved colour confirming to BS 3262-1989 with specifal applicator machine all as per manufacturer's instruction including cleaning the surface by removing all dirt, dust & all other forein matters, demarcation at site and traffic control, complete all as specified and directed. | 2,750 | Rm | - | - |
| 10 | Supply and fixing cat eye solar reflective type of metal body alloy of size 100mm x 100mm x 20mm with PAMA striplens reflector of model No. DA 972.0 fixed with and incl MS stud of suitable size as per manufactures instructions. including removal of old cat eye ,complete all as specified and directed. | 418 | Each | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.32 MB
Tender107.pdf
Tender Documents • 1.26 MB
BOQ_845709.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .