| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.5 LAccepted-AOC | ₹12.5 L Quoted ₹13.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹14.0 LRejected-AOC 40 E SUNDARAVELPURAM 7TH STREET TUTICORIN 628 002 | TUTICORIN | TAMIL NADU | 628002 | ₹14.0 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | S. MURUGAN CONTRACTOR | PARVATHI ENTERPRISES |
|---|---|---|---|---|---|
| 1.00 | 8 Ton and 5 Ton Hoist: Charges for Dismantling the 8/5Ton capacity electrical hoist with trolley from the existing beams by loosening the fixing bolt and nuts leading, lifting and lowering the hoist from its position to ground floor by using chain block.(Approximate height :5 mtr) | 6 | No. | 59,220 ₹69,879.60 | 56,496 ₹66,665.28 |
| 2.00 | Charges for draining the duty oil from the gear box by opening the top cover after loosening the fixing bolts and nuts. | 6 | No. | 53,460 ₹63,082.80 | 51,030 ₹60,215.40 |
| 3.00 | Charges for overhauling the hoist by dismantling the parts, cleaning and inspection, reassembly with new oil seal and gasket, greasing the wire rope and filling of oil in the gear box of 8/5 ton capacity hoists. | 6 | No. | 1,56,780 ₹1.9 L | 1,49,640 ₹1.8 L |
| 4.00 | Charges for overhauling of long travel assembly and travel mechanism with moving wheels, dismantling the parts with usual procedure complete cleaning and inspection, reassembling, greasing the moving wheel bearings, filling of oil including cost of oil seals gasket and hire charges for T&P. | 6 | No. | 1,88,610 ₹2.2 L | 1,80,012 ₹2.1 L |
| 5.00 | Charges for cleaning the control panel contactors and relays, cleaning the LT & CT cable trolleys and applying lubricants, tightness checking of cable terminals, testing the hoist with no load and adjusting the brakes. | 6 | No. | 51,390 ₹60,640.20 | 49,050 ₹57,879 |
| 6.00 | Charges for dismantling of rope drum, inspection, cleaning and applying compound & re winding the steel wire rope and assembling the drum with hoist. | 6 | No. | 78,870 ₹93,066.60 | 75,288 ₹88,839.84 |
| 7.00 | Dismantling and overhauling of raise/lower and long travel motors of hoist. Dismantling and re-erection of raise/lower motor (8Ton–7.46 KW & 5Ton–4.48 KW). | 6 | No. | 7,320 ₹8,637.60 | 6,966 ₹8,219.88 |
| 8.00 | Overhauling of raise/lower motor (8 Ton – 7.46 KW & 5 Ton – 4.48KW). | 6 | No. | 17,370 ₹20,496.60 | 16,578 ₹19,562.04 |
| 9.00 | Dismantling and re-erection of long travel motor (8 Ton & 5 Ton – 0.56KW). | 6 | No. | 2,940 ₹3,469.20 | 2,802 ₹3,306.36 |
| 10.00 | Overhauling of long travel motor (8 Ton & 5 Ton – 0.56 KW). | 6 | No. | 4,500 ₹5,310 | 4,290 ₹5,062.20 |
Tender Value
Refer Docs
EMD Value
₹11,200
Closing Date
17 Dec 2025, 2:00 pmClosed
Chief Engineer/TTPS
O/o CE/TTPS
ECHP-II Complete overhauling of 8 Ton, 5 Ton and 2 Ton capacity electrical hoist with trolley including dismantling and re-erection at TT-7 Top floor, Conveyor 61 tail end, Conveyor 61 head end, drive house floor of Conveyor-61, Conveyor-73 head
2025_EB_628133_1
CE/TTPS/SE/MI/181/2025-2026
Open Tender
Miscellaneous Works
160 days
TTPS
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹11,200
Yes
26 Mar 2026
2 Dec 2025
18 Dec 2025
2 Dec 2025
17 Dec 2025
2 Dec 2025
8 Ton and 5 Ton Hoist: Charges for Dismantling the 8/5Ton capacity electrical hoist with trolley from the existing beams by loosening the fixing bolt and nuts leading, lifting and lowering the hoist from its position to ground floor by using chain block.(Approximate height :5 mtr)
Charges for draining the duty oil from the gear box by opening the top cover after loosening the fixing bolts and nuts.
Charges for overhauling the hoist by dismantling the parts, cleaning and inspection, reassembly with new oil seal and gasket, greasing the wire rope and filling of oil in the gear box of 8/5 ton capacity hoists.
Charges for overhauling of long travel assembly and travel mechanism with moving wheels, dismantling the parts with usual procedure complete cleaning and inspection, reassembling, greasing the moving wheel bearings, filling of oil including cost of oil seals gasket and hire charges for T&P.
Charges for cleaning the control panel contactors and relays, cleaning the LT & CT cable trolleys and applying lubricants, tightness checking of cable terminals, testing the hoist with no load and adjusting the brakes.
Charges for dismantling of rope drum, inspection, cleaning and applying compound & re winding the steel wire rope and assembling the drum with hoist.
Dismantling and overhauling of raise/lower and long travel motors of hoist. Dismantling and re-erection of raise/lower motor (8Ton–7.46 KW & 5Ton–4.48 KW).
Overhauling of raise/lower motor (8 Ton – 7.46 KW & 5 Ton – 4.48KW).
Dismantling and re-erection of long travel motor (8 Ton & 5 Ton – 0.56KW).
Overhauling of long travel motor (8 Ton & 5 Ton – 0.56 KW).
Charges for re-erecting the 8/5 Ton capacity electrical hoist with trolley from ground floor to original position by using chain block with bolts & nuts.
2 Ton Hoist: Charges for Dismantling the 2 Ton capacity electrical hoist with trolley from the existing beams by loosening the fixing bolt and nuts leading, lifting and lowering the hoist from its position to ground floor by using chain block.(Approximate height :5 mtr).
Charges for draining the duty oil from the gear box by opening the top cover after loosening the fixing bolts and nuts.
Charges for overhauling the hoist by dismantling the parts, cleaning and inspection, reassembly with new oil seal and gasket, greasing the wire rope and filling of oil in the gear box of 2 ton capacity hoists.
Charges for dismantling of rope drum, inspection, cleaning and applying compound & re winding the steel wire rope and assembling the drum with hoist.
Charges for cleaning of all electrical accessories such as motors contactors, push buttons, limit switches, panel etc., and checking for proper operation.
Dismantling and Overhauling of raise/lower and long travel motors of hoist Dismantling and re-erection of raise / lower motor (2 Ton – 4.48KW).
Overhauling of raise/lower motor (2 Ton - 4.48KW)
Dismantling and re-erection of long travel motor (2 Ton – 0.56 KW)
Overhauling of long travel motor (2 Ton - 0.56 KW)
Charges for overhauling of equalizing pulley and hook pulleys of 2Ton capacity hoist including dismantling, re-assembling, greasing and normalizing.
Charges for re-erecting the 2 Ton capacity electrical hoist with trolley from ground floor to original position by using chain block with bolts & nuts.
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.23 MB
BOQ_750988.xls
BOQ • 0.31 MB